Section 36. Indiana County.
(a) Local Bridges
(1) Cherryhill Township, T-686 over Two Lick Creek, Bridge Replacement
1,950,000
(Base Project Allocation - $1,600,000)
(Land Allocation - $30,000)
(Design and Contingencies - $320,000)
(2) Brush Valley Township, T-716 over Brush Creek, Bridge Replacement
1,470,000
(Base Project Allocation - $1,200,000)
(Land Allocation - $30,000)
(Design and Contingencies - $240,000)
(3) Banks Township, T-974 over Bear Run, Bridge Replacement
1,230,000
(Base Project Allocation - $1,000,000)
(Land Allocation - $30,000)
(Design and Contingencies - $200,000)
(4) Washington Township, T-488 over Crooked Creek, Bridge Replacement
2,010,000
(Base Project Allocation - $1,650,000)
(Land Allocation - $30,000)
(Design and Contingencies - $330,000)
(5) Black Lick Township, T-460 over Aultmans Run, Bridge Replacement
980,000
(Base Project Allocation - $750,000)
(Land Allocation - $30,000)
(Design and Contingencies - $200,000)
(6) Center Township, T-465 over Muddy Run, Bridge Replacement
980,000
(Base Project Allocation - $750,000)
(Land Allocation - $30,000)
(Design and Contingencies - $200,000)
(7) South Mahoning Township, T-373 over Ross Run, Bridge Replacement
980,000
(Base Project Allocation - $750,000)
(Land Allocation - $30,000)
(Design and Contingencies - $200,000)
(8) Brush Valley Township, T-734 over Brush Creek, Bridge Replacement
980,000
(Base Project Allocation - $750,000)
(Land Allocation - $30,000)
(Design and Contingencies - $200,000)
(9) Conemaugh Township, T-652 over Big Run, Bridge Replacement
1,530,000
(Base Project Allocation - $1,250,000)
(Land Allocation - $30,000)
(Design and Contingencies - $250,000)
(b) State Bridges
(1) SR 0056 over Walker Run, Armstrong Township, Bridge Replacement
261,000
(Base Project Allocation - $81,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(2) SR 4001 over Tributary of Mitchell Run, Armstrong Township, Bridge Replacement
229,000
(Base Project Allocation - $49,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(3) SR 4002 over Mitchell Run, Armstrong Township, Bridge Replacement
254,000
(Base Project Allocation - $74,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(4) SR 0286 over Horton Run, Banks Township, Bridge Replacement
294,000
(Base Project Allocation - $114,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(5) SR 1033 over South Branch of Bear Run, Banks Township, Bridge Replacement
236,000
(Base Project Allocation - $56,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(6) SR 0217 over Greys Run, Black Lick Township, Bridge Replacement
224,000
(Base Project Allocation - $44,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(7) SR 3013 over Stewart Run, Black Lick Township, Bridge Replacement
249,000
(Base Project Allocation - $69,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(8) SR 0217 over Falling Run, Blairsville Borough, Bridge Replacement
231,000
(Base Project Allocation - $51,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(9) SR 0056 over Little Brush Creek, Brush Valley Township, Bridge Replacement
344,000
(Base Project Allocation - $164,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(10) SR 2018 over Tributary of Brush Creek, Brush Valley Township, Bridge Replacement
224,000
(Base Project Allocation - $44,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(11) SR 2012 over Mardis Run, Buffington Township, Bridge Replacement
292,000
(Base Project Allocation - $112,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(12) SR 2013 over Tributary of Blacklick Creek, Buffington Township, Bridge Replacement
233,000
(Base Project Allocation - $53,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(13) SR 1038 over Broadhead Run, Canoe Township, Bridge Replacement
215,000
(Base Project Allocation - $35,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(14) SR 1038 over Straight Run, Canoe Township, Bridge Replacement
312,000
(Base Project Allocation - $132,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(15) SR 1038 over Brewer Run, Canoe Township, Bridge Replacement
239,000
(Base Project Allocation - $59,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(16) SR 1038 over Leasure Run, Canoe Township, Bridge Replacement
224,000
(Base Project Allocation - $44,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(17) SR 1045 over Painter Run, Canoe Township, Bridge Replacement
243,000
(Base Project Allocation - $63,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(18) SR 1047 over Tributary of Canoe Creek, Canoe Township, Bridge Replacement
235,000
(Base Project Allocation - $150,000)
(Land Allocation - $15,000)
(Design and Contingencies - $70,000)
(19) SR 1052 over Tributary of Canoe Creek, Canoe Township, Bridge Replacement
240,000
(Base Project Allocation - $60,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(20) SR 3014 over Stewart Run, Center Township, Bridge Replacement
203,000
(Base Project Allocation - $23,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(21) SR 0422 Eastbound over T-604, Metz Road, Cherryhill Township, Bridge Rehabilitation
750,000
(Base Project Allocation - $750,000)
(22) SR 0422 Westbound over T-604, Metz Road, Cherryhill Township, Bridge Rehabilitation
750,000
(Base Project Allocation - $750,000)
(23) SR 1012 over Penn Run, Cherryhill Township, Bridge Replacement
277,000
(Base Project Allocation - $97,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(24) SR 0286, Bridge No.19082 over Blacklegs Creek, Conemaugh Township, Bridge Replacement
520,000
(Base Project Allocation - $340,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(25) SR 3003 over Elders Run, Conemaugh Township, Bridge Replacement
256,000
(Base Project Allocation - $76,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(26) SR 3007 over Marshall Run, Conemaugh Township, Bridge Replacement
230,000
(Base Project Allocation - $50,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(27) SR 3007 over Roaring Run, Conemaugh Township, Bridge Replacement
235,000
(Base Project Allocation - $55,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(28) SR 3009 over Aultmans Run, Conemaugh Township, Bridge Replacement
1,276,000
(Base Project Allocation - $1,096,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(29) SR 0110 over Crooked Creek, Creekside Borough, Bridge Replacement
1,039,000
(Base Project Allocation - $859,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(30) SR 0119 over Pine Run, East Mahoning Township, Bridge Replacement
343,000
(Base Project Allocation - $163,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(31) SR 0403 over Pine Run, East Mahoning Township, Bridge Replacement
365,000
(Base Project Allocation - $185,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(32) SR 4015 over Ross Run, East Mahoning Township, Bridge Replacement
284,000
(Base Project Allocation - $104,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(33) SR 1020 over Little Mahoning Creek, Grant Township, Bridge Replacement
257,000
(Base Project Allocation - $77,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(34) SR 1034 over Little Mahoning Creek, Grant Township, Bridge Replacement
443,000
(Base Project Allocation - $263,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(35) SR 0240 over South Branch of Two Lick Creek, Green Township, Bridge Replacement
226,000
(Base Project Allocation - $46,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(36) SR 0286 over North Branch of Two Lick Creek, Green Township, Bridge Replacement
221,000
(Base Project Allocation - $41,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(37) SR 0403, Bridge No.19136 over Tributary of Dixon Run, Green Township, Bridge Replacement
240,000
(Base Project Allocation - $60,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(38) SR 0403, Bridge No.19138 over Tributary of Dixon Run, Green Township, Bridge Replacement
323,000
(Base Project Allocation - $143,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(39) SR 1014 over Whitaker Run, Green Township, Bridge Replacement
259,000
(Base Project Allocation - $79,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(40) SR 1015 over South Branch of Two Lick Creek, Green Township, Bridge Replacement
235,000
(Base Project Allocation - $55,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(41) SR 1018 over Tributary of Dixon Run, Green Township, Bridge Replacement
247,000
(Base Project Allocation - $67,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(42) SR 0286 over Marsh Run, Indiana Borough, Bridge Replacement
280,000
(Base Project Allocation - $100,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(43) SR 3035 over Stoney Run, Indiana Borough, Bridge Replacement
306,000
(Base Project Allocation - $126,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(44) SR 4032 over Tributary of Whites Run, Indiana Borough, Bridge Replacement
1,190,000
(Base Project Allocation - $540,000)
(Land Allocation - $150,000)
(Design and Contingencies - $500,000)
(45) SR 4032 over Whites Run, Indiana Borough, Bridge Replacement
282,000
(Base Project Allocation - $102,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(46) SR 0286 over Cush Creek, Montgomery Township, Bridge Replacement
262,000
(Base Project Allocation - $82,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(47) SR 1015 over Hazelet Run, Montgomery Township, Bridge Replacement
235,000
(Base Project Allocation - $55,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(48) SR 0210 over Little Mahoning Creek, North Mahoning Township, Bridge Replacement
794,000
(Base Project Allocation - $614,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(49) SR 0210 over Dutch Run, North Mahoning Township, Bridge Replacement
243,000
(Base Project Allocation - $63,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(50) SR 0403 over Little Yellow Creek, Pine Township, Bridge Replacement
245,000
(Base Project Allocation - $65,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(51) SR 1019 over Yellow Creek, Pine Township, Bridge Replacement
221,000
(Base Project Allocation - $41,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(52) SR 0085 over North Branch of Plum Creek, Plumville Borough, Bridge Replacement
288,000
(Base Project Allocation - $108,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000
(53) SR 0110 over Tributary of Mckee Run, Rayne Township, Bridge Replacement
267,000
(Base Project Allocation - $87,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000
(54) SR 0286 over Crooked Creek, Rayne Township, Bridge Replacement
278,000
(Base Project Allocation - $98,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000
(55) SR 1005 over Brush Run, Rayne Township, Bridge Replacement
239,000
(Base Project Allocation - $59,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000
(56) SR 1035 over Tributary of Dixon Run, Rayne Township, Bridge Replacement
236,000
(Base Project Allocation - $56,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000
(57) SR 4008 over Tributary of Crooked Creek, Rayne Township, Bridge Replacement
220,000
(Base Project Allocation - $150,000)
(Design and Contingencies - $70,000)
(58) SR 4012 over Tributary of Crooked Creek, Rayne Township, Bridge Replacement
221,000
(Base Project Allocation - $41,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(59) SR 0286 over Kiskiminetas River, Saltsburg Borough, Bridge Rehabilitation
2,486,000
(Base Project Allocation - $2,306,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(60) SR 4021 over Condron Run, Smicksburg Borough, Bridge Replacement
342,000
(Base Project Allocation - $162,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(61) SR 0210 over Ross Run, South Mahoning Township, Bridge Replacement
305,000
(Base Project Allocation - $125,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(62) SR 0210, Bridge No.19052 over Tributary of Ross Run, South Mahoning Township, Bridge Replacement
251,000
(Base Project Allocation - $71,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(63) SR 0210, Bridge No.19053 over Tributary of Ross Run, South Mahoning Township, Bridge Replacement
254,000
(Base Project Allocation - $74,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(64) SR 0954 over North Branch of Plum Creek, South Mahoning Township, Bridge Replacement
235,000
(Base Project Allocation - $55,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(65) SR 4015 over Goose Run, South Mahoning Township, Bridge Replacement
208,000
(Base Project Allocation - $28,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(66) SR 4018 over Little Mahoning Creek, South Mahoning Township, Bridge Replacement
677,000
(Base Project Allocation - $497,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(67) SR 4001 over Mudlick Run, Washington Township, Bridge Replacement
275,000
(Base Project Allocation - $95,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(68) SR 0259 over West Branch of Richards Run, West Wheatfield Township, Bridge Replacement
333,000
(Base Project Allocation - $153,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(69) SR 0259, Bridge No.19070 over Ramsey Run, West Wheatfield Township, Bridge Replacement
237,000
(Base Project Allocation - $57,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(70) SR 0259, Bridge No.19071 over Ramsey Run, West Wheatfield Township, Bridge Replacement
248,000
(Base Project Allocation - $68,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(71) SR 2008 over Richards Run, West Wheatfield Township, Bridge Replacement
268,000
(Base Project Allocation - $88,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(72) SR 2011 over Tributary of Conemaugh River, West Wheatfield Township, Bridge Replacement
255,000
(Base Project Allocation - $75,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(73) SR 0110 over McKee Run, White Township, Bridge Replacement
278,000
(Base Project Allocation - $98,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(74) SR 0954 over Fulton Run, White Township, Bridge Replacement
249,000
(Base Project Allocation - $69,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(75) SR 1002 over Ramsey Run, White Township, Bridge Replacement
339,000
(Base Project Allocation - $159,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(76) SR 3024 over McCarthy Run, White Township, Bridge Replacement
270,000
(Base Project Allocation - $90,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(77) SR 4005 over Tributary of McKee Run, White Township, Bridge Replacement
284,000
(Base Project Allocation - $104,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(78) SR 4032 over Tributary of McCarthy Run, White Township, Bridge Rehabilitation
1,077,000
(Base Project Allocation - $427,000)
(Land Allocation - $150,000)
(Design and Contingencies - $500,000)
(79) SR 0286, Bridge No.19087 over Blacklegs Creek, Young Township, Bridge Replacement
595,000
(Base Project Allocation - $415,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(80) SR 3021 over Harpers Run, Young Township, Bridge Replacement
275,000
(Base Project Allocation - $95,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(81) SR 3023 over Whisky Run, Young Township, Bridge Replacement
243,000
(Base Project Allocation - $63,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(82) SR 3025 over Nesbit Run, Young Township, Bridge Replacement
277,000
(Base Project Allocation - $97,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(83) SR 3029 over Tributary of Neal Run, Young Township, Bridge Replacement
231,000
(Base Project Allocation - $51,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(84) SR 3056 over Tributary of Blacklegs Creek, Young Township, Bridge Replacement
228,000
(Base Project Allocation - $48,000)
(Land Allocation - $40,000)
(Design and Contingencies - $140,000)
(85) SR 2019, LR 32023, Coy No.1 over Tributary of Tearing Run, Center Township, Bridge Replacement
259,000
(Base Project Allocation - $169,000)
(Land Allocation - $17,000)
(Design and Contingencies - $73,000)
(86) SR 0422, Eastbound, Chestnut Ridge, Eastbound over T-840, Chestnut Ridge Road, Cherryhill Township, Deck Rehabilitation
399,000
(Base Project Allocation - $342,000)
(Design and Contingencies - $57,000)
(87) SR 2014, Muddy Run Bridge No.2 over Muddy Run, Black Lick Township, Bridge Replacement
196,000
(Base Project Allocation - $133,000)
(Land Allocation - $16,000)
(Design and Contingencies - $47,000)