Section 44. Luzerne County.
(a) Local Bridges
(1) Fairmount Township, T-654 over Kitchen Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(2) New Colombus Borough, T-486 over Little Pine Creek, Bridge Replacement
430,000
(Base Project Allocation - $430,000)
(3) Lehman Township, T-581 over Pikes Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(4) Exeter Township, County Road No.10 over Sutton Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(5) Exeter Township, County Road No.10 over Sutton Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(6) Rice Township, County Road No.23 over Wapwallopen Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(7) Nescopeck Township, T-376 over Nescopeck Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(8) Salem Township, T-436 over Beach Haven Creek, Bridge Replacement
630,000
(Base Project Allocation - $630,000)
(9) Shickshinny Borough, Glen Avenue over Shickshinny Creek, Bridge Replacement
150,000
(Base Project Allocation - $150,000)
(10) Shickshinny Borough, Bartoli Lane over Shickshinny Creek, Bridge Replacement
150,000
(Base Project Allocation - $150,000)
(11) Avoca Borough, County-owned Railroad over McAlpine Street, Bridge Rehabilitation
50,000
(Base Project Allocation - $45,000)
(Design and Contingencies - $5,000)
(12) Avoca Borough, County-owned Railroad over CP Railroad, Bridge Rehabilitation
63,000
(Base Project Allocation - $57,000)
(Design and Contingencies - $6,000)
(13) Avoca Borough, County-owned Railroad over RBMN Railroad, Bridge Rehabilitation
66,000
(Base Project Allocation - $60,000)
(Design and Contingencies - $6,000)
(14) Avoca Borough, County-owned Railroad over York Avenue, Bridge Rehabilitation
55,000
(Base Project Allocation - $50,000)
(Design and Contingencies - $5,000)
(15) Avoca Borough, County-owned Railroad over Kerr McGee, Bridge Rehabilitation
22,000
(Base Project Allocation - $20,000)
(Design and Contingencies - $2,000)
(16) City of Wilkes-Barre, County-owned Railroad over Laurel Run Creek, Bridge Rehabilitation
110,000
(Base Project Allocation - $100,000)
(Design and Contingencies - $10,000)
(17) Ashley Borough, County-owned Railroad over Ashley Street, Bridge Rehabilitation
61,000
(Base Project Allocation - $55,000)
(Design and Contingencies - $6,000)
(18) Ashley Borough, County-owned Railroad over Cemetery Street, Bridge Demolition
132,000
(Base Project Allocation - $120,000)
(Design and Contingencies - $12,000)
(19) Ashley Borough, County-owned Railroad over Carey Street, Bridge Demolition
55,000
(Base Project Allocation - $50,000)
(Design and Contingencies - $5,000)
(20) City of Pittston, County-owned Railroad over Susquehanna River, Bridge Rehabilitation
550,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $50,000)
(21) City of Wilkes-Barre, County-owned Railroad over Mill Creek, Bridge Rehabilitation
34,000
(Base Project Allocation - $30,000)
(Design and Contingencies - $4,000)
(22) City of Wilkes-Barre, County-owned Railroad over Scott Street, Bridge Rehabilitation
165,000
(Base Project Allocation - $150,000)
(Design and Contingencies - $15,000)
(23) City of Wilkes-Barre, County-owned Railroad over Shelbourne Street, Bridge Rehabilitation
39,000
(Base Project Allocation - $35,000)
(Design and Contingencies - $4,000)
(24) Pittston Township, County-owned Railroad over Suscon Road, New Bridge Construction
2,750,000
(Base Project Allocation - $2,500,000)
(Design and Contingencies - $250,000)
(25) Pittston Township, County-owned Railroad over Suscon Mill Creek, Bridge Rehabilitation
22,000
(Base Project Allocation - $20,000)
(Design and Contingencies - $2,000)
(26) Wycoming Borough, County-owned Railroad over Abrahams Creek, Bridge Rehabilitation
22,000
(Base Project Allocation - $20,000)
(Design and Contingencies - $2,000)
(27) Exeter Borough, County-owned Railroad over Stephens Road, Bridge Rehabilitation
22,000
(Base Project Allocation - $20,000)
(Design and Contingencies - $2,000)
(28) City of Wilkes-Barre, County-owned Railroad over Laurel Run Creek, Bridge Rehabilitation
11,000
(Base Project Allocation - $10,000)
(Design and Contingencies - $1,000)
(29) City of Wilkes-Barre, County-owned Railroad over Thomas Street, Bridge Rehabilitation
22,000
(Base Project Allocation - $20,000)
(Design and Contingencies - $2,000)
(30) City of Wilkes-Barre, County-owned Railroad over Mayock Street, Bridge Rehabilitation
44,000
(Base Project Allocation - $40,000)
(Design and Contingencies - $4,000)
(31) Lehman Township, T-581 over Pikes Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(32) Fairmount Township, T-654 over Kitchen Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(33) City of Wilkes-Barre, Hanover Township, Division Street over Solomon Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(34) Hanover Township, West Liberty Street over Solomon Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(35) Exeter Township, County Road No.10 over Sutton Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(36) Exeter Township, County Road No.10 over Sutton Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(37) Rice Township, County Road No.23 over Wapwallopen Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $60,000)
(38) New Columbus Borough, T-486 over Little Pine Creek, Bridge Replacement
460,000
(Base Project Allocation - $430,000)
(Land Allocation - $30,000)
(39) Nescopeck Township, T-376 over Nescopeck Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(40) Salem Township, T-436 over Beach Haven Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(41) Black Creek Township, T-514 over Black Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(42) Butler Township, County Road No.39 over Nescopeck Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(43) Butler Township, T-356 over Nescopeck Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(44) Sugarloaf Township, T-342 over Nescopeck Creek, Bridge Replacement
660,000
(Base Project Allocation - $630,000)
(Land Allocation - $30,000)
(45) Kingston Township, Center Street T-846 over Toby's Creek, Bridge Replacementt
718000
(Base Project Allocation - $718,000)
(b) State Bridges
(1) SR 3010 over Branch of Wapwallopen Creek, Dorrance Township, Bridge Rehabilitation
41,000
(Base Project Allocation - $28,000)
(Land Allocation - $3,000)
(Design and Contingencies - $10,000)
(2) SR 4020 over Pine Creek, Fairmount Township, Bridge Rehabilitation
154,000
(Base Project Allocation - $106,000)
(Land Allocation - $11,000)
(Design and Contingencies - $37,000)
(3) SR 0011 over Abrahams Creek, Forty Fort Borough, Bridge Rehabilitation
442,000
(Base Project Allocation - $304,000)
(Land Allocation - $30,000)
(Design and Contingencies - $108,000)
(4) SR 4005 over Hunlock Creek, Hunlock Township, Bridge Replacement
70,000
(Base Project Allocation - $48,000)
(Land Allocation - $5,000)
(Design and Contingencies - $17,000)
(5) SR 4010 over Huntington Creek, Huntington Township, Bridge Rehabilitation
250,000
(Base Project Allocation - $173,000)
(Land Allocation - $17,000)
(Design and Contingencies - $60,000)
(6) SR 1012 over Branch of Harvey's Creek, Jackson Township, Bridge Replacement
635,000
(Base Project Allocation - $500,000)
(Land Allocation - $35,000)
(Design and Contingencies - $100,000)
(7) SR 4037 over Stone Church Hollow Creek, Salem Township, Bridge Rehabilitation
110,000
(Base Project Allocation - $76,000)
(Land Allocation - $8,000)
(Design and Contingencies - $26,000)
(8) SR 0080, East Bound over Linesville Creek, White Haven Borough, Bridge Rehabilitation
52,000
(Base Project Allocation - $35,000)
(Land Allocation - $4,000)
(Design and Contingencies - $13,000)
(9) SR 2032, near Intersection of SR 2030, over Abandoned Railroad, Duryea and Hughestown Boroughs, Railroad Abutments Removal
18,000
(Base Project Allocation - $18,000)
(10) SR 2029, York Avenue near Intersection with Wood Street, over Abandoned Railroad, Duryea Borough, Railroad Abutments Removal
26,000
(Base Project Allocation - $18,000)
(Land Allocation - $8,000)