Section 52. Northampton County.
(a) Local Bridges
(1) City of Easton, Bushkill Street over Bushkill Creek, Bridge Rehabilitation
1,000,000
(Base Project Allocation - $1,000,000)
(2) City of Easton, Glendon Hill Road over Lehigh River, Bridge Rehabilitation
1,000,000
(Base Project Allocation - $1,000,000)
(3) Washington Township, County Bridge No.189 over Waltz Creek, Bridge Replacement
850,000
(Base Project Allocation - $433,000)
(Land Allocation - $167,000)
(Design and Contingencies - $250,000)
(4) Bushkill Township, T-638 over Sobers Run, Bridge Construction
536,000
(Base Project Allocation - $500,000)
(Design and Contingencies - $36,000)
(b) State Bridges
(1) PA 611 over Tributary of Oughoughton Creek, Lower Mt. Bethel Township, Bridge Replacement
800,000
(Base Project Allocation - $400,000)
(Land Allocation - $50,000)
(Design and Contingencies - $350,000)
(2) SR 0946 over Hokendauqua Creek, Moore Township, Bridge Replacement
975,000
(Base Project Allocation - $475,000)
(Land Allocation - $50,000)
(Design and Contingencies - $450,000)
(3) SR 2017, Bushkill Street over Bushkill Creek, Stockertown Borough, Bridge Removal
615,000
(Base Project Allocation - $505,000)
(Land Allocation - $10,000)
(Design and Contingencies - $100,000)
(4) PA 191 over SR 0033, Stockertown Borough, Bridge Rehabilitation
695,000
(Base Project Allocation - $135,000)
(Land Allocation - $20,000)
(Design and Contingencies - $540,000)
(5) SR 1033, North Main over Martins Creek, Washington Township, Bridge Replacement
300,000
(Base Project Allocation - $80,000)
(Land Allocation - $50,000)
(Design and Contingencies - $170,000)
(6) SR 1002 over Bushkill Creek, Tatamy Borough, Bridge Replacement
2,000,000
(Base Project Allocation - $2,000,000)
(7) PA 611, LR 166 over Slateford Creek, Upper Mt. Bethel Township, Bridge Rehabilitation
330,000
(Base Project Allocation - $231,000)
(Design and Contingencies - $99,000)
(8) SR 1004, LR 48025 over Tributary of Delaware River, Lower Mt. Bethel Township, Bridge Rehabilitation
59,000
(Base Project Allocation - $41,000)
(Design and Contingencies - $18,000)
(9) SR 1004, LR 48025 over Tributary of Delaware River, Lower Mt. Bethel Township, Bridge Rehabilitation
65,000
(Base Project Allocation - $45,000)
(Design and Contingencies - $20,000)
(10) SR 1012, LR 48087 over Bushkill Creek, Bushkill Township, Bridge Rehabilitation
630,000
(Base Project Allocation - $441,000)
(Design and Contingencies - $189,000)
(11) SR 1015, LR 165, Bridge No.28674 over Martins Creek, Washington Township, Bridge Rehabilitation
380,000
(Base Project Allocation - $266,000)
(Design and Contingencies - $114,000)
(12) SR 1015, LR 165, Bridge No.28678 over Martins Creek, Bangor Borough, Bridge Rehabilitation
277,000
(Base Project Allocation - $194,000)
(Design and Contingencies - $83,000)
(13) SR 1032, LR 166 over Jacoby Creek and Mill Race, Portland Borough, Bridge Rehabilitation
250,000
(Base Project Allocation - $175,000)
(Design and Contingencies - $75,000)
(14) SR 1033, LR 48075 over Tributary of Martins Creek, Washington Township, Bridge Rehabilitation
78,000
(Base Project Allocation - $54,000)
(Design and Contingencies - $24,000)
(15) SR 1039, LR 517, Bridge No.28701 over Tributary of Delaware River, Upper Mt. Bethel Township, Bridge Rehabilitation
108,000
(Base Project Allocation - $75,000)
(Design and Contingencies - $33,000)
(16) SR 1039, LR 517, Bridge No.28702 over Tributary of Delaware River, Upper Mt. Bethel Township, Bridge Rehabilitation
66,000
(Base Project Allocation - $46,000)
(Design and Contingencies - $20,000)
(17) SR 0191, Appl.1019 over SR 0033, LR 1098, Stockertown Borough, Bridge Rehabilitation
3,700,000
(Base Project Allocation - $2,700,000)
(Design and Contingencies - $1,000,000)
(18) SR 0248, LR 471 over Hokendauqua Creek, Moore Township, Bridge Rehabilitation
302,000
(Base Project Allocation - $211,000)
(Design and Contingencies - $91,000)
(19) SR 3020, LR 48063 over Tributary of Monacacy Creek, Lower Nazareth Township, Bridge Rehabilitation
246,000
(Base Project Allocation - $172,000)
(Design and Contingencies - $74,000)
(20) SR 3020, LR 48063 over East Branch of Monacacy Creek, Upper Nazareth Township, Bridge Rehabilitation
214,000
(Base Project Allocation - $150,000)
(Design and Contingencies - $64,000)
(21) SR 4007, LR 48055, Bridge No.28783 over Tributary of Hokendauqua Creek, Moore Township, Bridge Rehabilitation
88,000
(Base Project Allocation - $61,000)
(Design and Contingencies - $27,000)
(22) SR 4007, LR 48055, Bridge No.28784 over Tributary of Hokendauqua Creek, Moore Township, Bridge Rehabilitation
92,000
(Base Project Allocation - $64,000)
(Design and Contingencies - $28,000)
(23) SR 4014, LR 48043 over Branch of Hokendauqua Creek, Moore Township, Bridge Rehabilitation
63,000
(Base Project Allocation - $44,000)
(Design and Contingencies - $19,000)
(24) SR 4019, LR 48044 over Tributary of Bushkill Creek, Bushkill Township, Bridge Rehabilitation
92,000
(Base Project Allocation - $64,000)
(Design and Contingencies - $28,000)
(25) SR 4019, LR 48044 over Horn Creek, Bushkill Township, Bridge Rehabilitation
73,000
(Base Project Allocation - $51,000)
(Design and Contingencies - $22,000)
(26) SR 0512, LR 166 over Brush Meadow Creek, Bangor Borough, Bridge Rehabilitation
94,000
(Base Project Allocation - $66,000)
(Design and Contingencies - $28,000)
(27) SR 0512, LR 48046 over Tributary of Monocacy Creek, East Allen Township, Bridge Rehabilitation
246,000
(Base Project Allocation - $172,000)
(Design and Contingencies - $74,000)
(28) SR 0512, LR 752 over Bushkill Creek, Bushkill Township, Bridge Rehabilitation
420,000
(Base Project Allocation - $294,000)
(Design and Contingencies - $126,000)
(29) SR 0946, LR 752 over Hokendauqua Creek, Moore Township, Bridge Replacement
550,000
(Base Project Allocation - $425,000)
(Design and Contingencies - $125,000)
(30) SR 1033, LR 48075Sp. over Martins Creek, Washington Township, Bridge Replacement
1,025,000
(Base Project Allocation - $525,000)
(Design and Contingencies - $500,000)
(31) SR 0191, LR 297 over Monocacy Creek, Lower Nazareth Township, Deck Replacement
850,000
(Base Project Allocation - $700,000)
(Design and Contingencies - $150,000)