“As built” plans required

R.I. Gen. Laws § 24-8.1-3.1., under Chapter 24-8.1 Relocation of Utility Services.

R.I. Gen. Laws § 24-8.1-3.1.

Each utility shall submit to the department of transportation a complete set of “as-built” plans, within sixty (60) days of the installation of new utility facilities, or within sixty (60) days of the relocation of existing utility facilities that affect state roads.