59 chapters · 815 sections in this title.
R.I. Gen. Laws § 39-33-1. Definitions
0.5K chars
As used in this chapter: (1) “Commission” means the public utilities commission. (2) “Energy storage system” means any technology capable of converting electrical energy to some form of stored energy for reconversion to electrical energy at a later time. (3) “Long-duration energy…
R.I. Gen. Laws § 39-33-2. Storage tariff
1.1K chars
No later than September 1, 2024, the public utilities commission shall engage stakeholders to adopt a framework for an energy storage system tariff for energy storage systems connected to the electric distribution system. (1) The tariff framework should, at a minimum, address the…
R.I. Gen. Laws § 39-33-3. Interconnection
0.7K chars
(a) No later than September 1, 2024, the commission shall commence a process, which includes stakeholder engagement, to adopt a framework for an interconnection tariff for energy storage systems connected to the electric distribution system that recognizes the flexible operating …
R.I. Gen. Laws § 39-33-4. Periodic storage assessment and procurement
2.1K chars
(a) Not less than every three (3) years, the commission shall conduct a market survey to assess the capabilities of storage technologies and whether those capabilities have the potential to meet the needs of, or provide net value to, the distribution system or the bulk power syst…