Reapplication for permit--Discussion of commission as to applicant's burden of proof

SDCL § 49-41B-22.2 — under ENERGY CONVERSION AND TRANSMISSION FACILITIES.

SDCL § 49-41B-22.2

If a second or subsequent reapplication is filed within three years, or a reapplication is filed after three years, following a denial of a permit pursuant to § 49-41B-24 or 49-41B-25 , the Public Utilities Commission may in its discretion decide if an applicant shall have the burden of proof to establish all criteria required in an original application. Source: SL 1982, ch 333 , § 2.