A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in §
SDCL § 49-41B-5 — under ENERGY CONVERSION AND TRANSMISSION FACILITIES.
SDCL § 49-41B-5
A notification of intent to apply for a permit for construction of an energy conversion facility or AC/DC conversion facility shall be filed with the Public Utilities Commission at least six months before filing an application as required in §