SDCL § 31-23-1 Performance bond required--Amount of bond--Conditions of bond
0.6K chars
Except as provided in § 31-12-15 , before any contract is entered into for the construction, repair, or improvement of any public highway by the State of South Dakota, or any public corporation within the State of South Dakota, the person to whom such contract is awarded shall fu…
SDCL § 31-23-2 Laborer's or materialman's suit on bond--Time for payment
0.7K chars
Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which such a performance bond is furnished under § 31-23-1 and who has not been paid in full therefor before the expiration of a period of six months after…
SDCL § 31-23-3 Subcontractor's creditors' right of action on bond--Time for payment--Written notice required--Contents of notice--Service of notice
1.0K chars
Any person having direct contractual relationship with a subcontractor but not contractual relationship express or implied with the contractor furnishing a performance bond under § 31-23-1 shall have a right of action upon the said bond upon giving written notice to said contract…
SDCL § 31-23-4 Title of suit--Venue--Limitations--Costs and expenses
0.6K chars
Every suit instituted under this chapter shall be brought in the name of the State of South Dakota for the use of the person suing, in the circuit court of the State of South Dakota within the circuit in which the contract was to be performed, and not elsewhere, irrespective of t…
SDCL § 31-23-5 Remedy as exclusive
0.1K chars
The remedy provided for in this chapter shall be exclusive. Source: SL 1941, ch 135 , § 4; SDC Supp 1960, § 28.1604.