36 chapters · 230 sections in this title.
SDCL 46-2-11
0.1K chars
Source: SL 1983, ch 316 , § 18; SL 2021, ch 192 , § 4.
SDCL § 46-2A-1 Application of provisions of chapter
0.6K chars
The provisions of this chapter apply to any application for: (1) A permit to appropriate water; (2) An amendment of an existing permit or license, including change in use of water or change in place of use or diversion point of water; (3) A reservation for future use; (4) A permi…
SDCL § 46-2A-10 Reservation for future use--When approval allowed
0.3K chars
A reservation for a future use may be approved only if there is a reasonable probability that unappropriated water is available for appropriation, that the quantity of water reserved will be needed by the entity and that the proposed use will be a beneficial use and in the public…
SDCL § 46-2A-11 Flood control works--When permit may be issued
0.6K chars
A permit for flood control works may be issued only if the project will reduce the damage from flooding or erosion in the area proposed to be benefited, the project will not increase the likelihood or the severity of flood damages in areas other than the project area or the area …
SDCL § 46-2A-12 Amendment of permit or license--When granted
0.3K chars
An amendment of an existing permit or license may be granted for a change in use, a change in point of diversion or other change only if the change does not unlawfully impair existing rights and is for a beneficial use and in the public interest. Source: SL 1983, ch 316 , § 21.
SDCL § 46-2A-13 Well driller or well pump installer license--Issuance by chief engineer--Procedure on denial or deferral of decision
0.6K chars
In the case of an application for a well driller license or a well pump installer license, the chief engineer may issue the license. If the chief engineer's recommendation is to deny the license or to defer the decision on the license, the chief engineer shall mail a copy of the …
SDCL § 46-2A-14 Application and permit refer to one water use system--Location to be stated
0.3K chars
Any application and permit to appropriate water shall refer to one water use system, the location of which shall be described in the application. Source: SL 1955, ch 430 , § 1; SL 1957, ch 490 , § 1; SDC Supp 1960, § 61.0110; SDCL, § 46-5-12 ; SL 1983, ch 316 , § 3; SL 1985, ch 3…
SDCL § 46-2A-15 Date of receipt of application recorded--Correction of application
0.9K chars
The date of receipt by the chief engineer of an application for any permit, license, or amendment under Title 46 shall be endorsed thereon. If the chief engineer determines that the application is defective in form or incomplete, it shall be returned to the applicant with a state…
SDCL § 46-2A-16 Validation of vested water right claim--Notice
1.5K chars
Any claim for vested rights as defined in § 46-1-9 or 46-6-1 that has been accepted for filing by the chief engineer or Board of Water Management, prior to July 1, 1986, is eligible for validation. The chief engineer shall prepare a list based on the point of diversion of these v…
SDCL § 46-2A-17 Hearing to oppose validation--Notice
0.5K chars
If a petition of intent to oppose the validation of a recognized vested water right claim is filed pursuant to § 46-2A-16 , the Board of Water Management shall hear and determine the matter de novo. Further published notice is not necessary, but the parties shall be notified of t…
SDCL § 46-2A-18 Abandonment of validated vested right
0.6K chars
Recognition or validation of a vested right under § 46-5-49 or 46-6-2 does not protect the water right from a claim of abandonment or forfeiture based upon acts occurring in whole or in part after the date of the board's recognition or validation. The entry of an order under § 46…
SDCL § 46-2A-19 Adjustment and validation of certain interstate water right claims
1.5K chars
Any person claiming to be the owner of a right to appropriate water from any source for beneficial use other than domestic uses as defined in subdivision § 46-1-6(7), on property in the State of South Dakota which was located in the state of Nebraska prior to ratification and app…
SDCL § 46-2A-2 Recommendation of chief engineer on application--Schedule of hearing
0.6K chars
Within sixty days of receipt of a completed application, the chief engineer shall recommend in writing approval, disapproval or deferral until further notice and shall schedule the application for hearing by the Water Management Board. The recommendation shall include any terms, …
SDCL § 46-2A-20 Term limitation on water withdrawal from Madison formation in certain counties
0.8K chars
Notwithstanding §§ 46-1-14 and 46-2A-7 , no water permit for construction of works to withdraw water from the Madison formation in Butte, Fall River, Custer, Lawrence, Meade and Pennington counties may be issued for a term of more than twenty years, unless the Water Management Bo…
SDCL § 46-2A-21 Deletion of term limitation under certain conditions--Cancellation or amendment of permit
0.9K chars
At any time during the twenty - year term set forth in § 46-2A-20 , or following its expiration, the board may delete the term limitation condition upon a finding that sufficient information has become available to determine: (1) Whether the withdrawal would cause any significant…
SDCL § 46-2A-22 Correction of errors in published notice of vested right claims--Contents--Hearing only on filing of petition
0.2K chars
Any vested right claim published for validation in accordance with § 46-2A-16 may be readvertised to correct errors in the published notice pursuant to the publication time frame and comment period established by §
SDCL § 46-2A-23 Publication of notice to determine opposition to application or recommendation of chief engineer--Petition to contest--Notice of hearing
1.7K chars
Following the issuance of a recommendation to approve an application pursuant to § 46-2A-2 , the chief engineer may publish, at the expense of the applicant, a notice to determine whether any person opposes the application or recommendation of the chief engineer. The notice shall…
SDCL § 46-2A-3 Recommendation of chief engineer on application--Mailing to applicant--Duties of applicant
0.9K chars
In all cases except applications for a well driller license or a well pump installer license, the chief engineer shall mail a copy of the recommendation to the applicant and, if the recommendation is to approve or defer the application, a copy of the newspaper notice to be publis…
SDCL § 46-2A-4 Publication of application and recommendation of chief engineer--Time for publication--Contents of notice
0.6K chars
Except in the case of an application for a well driller license or a well pump installer license, if a recommendation is to approve or defer an application or if an applicant has filed a petition to oppose a recommendation to deny an application, the applicant shall publish notic…
SDCL § 46-2A-5 Postponement of hearing on application--Time for notice
0.5K chars
The applicant or any person who has filed a petition to oppose an application, may file a written notice to the chief engineer requesting a postponement of the date set for hearing on the application. Upon receipt of the written notice, the chief engineer shall cancel the origina…
SDCL § 46-2A-6 Service and filing of pleadings, petitions, and motions
0.6K chars
The originals of all pleadings, including petitions to contest, petitions to intervene, and motions, shall be filed with the chief engineer and served upon other parties, either personally or by mail. The chief engineer shall provide copies to all Water Management Board members. …
SDCL § 46-2A-7 Approval or disapproval of permit, license, or amendment--Applications for groundwater source determined to be fully appropriated
0.7K chars
If the Water Management Board determines, based upon the evidence presented at the hearing, that the applicable requirements for the permit, license, or amendment have been met, it shall approve the permit, license, or amendment. If the board determines that the requirements have…
SDCL § 46-2A-7.1 Notice of determination that groundwater source fully appropriated--Applications for future consideration
1.0K chars
If the board determines a groundwater source to be fully appropriated pursuant to § 46-6-3.1 , the chief engineer shall publish a notice within thirty days of the board's final decision at least once in at least one official newspaper in each county where the groundwater source i…
SDCL § 46-2A-7.2 Date of receipt--Incomplete application--One irrigation permit application per parcel
1.0K chars
The date of receipt affixed to any application submitted pursuant to § 46-2A-7.1 shall be the date of the thirtieth day of the thirty day application period. An incomplete application will be returned to the applicant with notification of the deficiencies. The applicant has thirt…
SDCL § 46-2A-7.3 Applications submitted prior to board decision that aquifer is fully appropriated or prior to July 1, 2014
0.4K chars
Any application submitted prior to the board's decision that an aquifer is fully appropriated pursuant to § 46-6-3.1 or prior to July 1, 2014, is not eligible to be included in the process established by §§ 46-2A-7.1 to 46-2A-7.7 , inclusive, and shall be considered by the board …
SDCL § 46-2A-7.4 Priority list for future unappropriated water
0.6K chars
From the list of complete applications submitted pursuant to § 46-2A-7.1 and assigned a common priority date, the board shall create a priority list using a random selection process to be determined by the board. The priority list determines the order of eligibility for any unapp…
SDCL § 46-2A-7.5 Public hearing to review groundwater source--Notice--Retention of eligibility by applicant
1.4K chars
For any groundwater source determined to be fully appropriated pursuant to § 46-6-3.1 , the board shall hold a public hearing to review the groundwater source, all permits appropriating water from that source, and all held applications at least once every five years to determine …
SDCL § 46-2A-7.6 Unappropriated water to be available to held applications based on priority
0.3K chars
If the board determines that unappropriated water has become available from a fully appropriated groundwater source during the five-year review under § 46-2A-7.5 , the board shall make the unappropriated water available to the applications being held by the chief engineer based o…
SDCL § 46-2A-7.7 Transfer of water permit application
0.4K chars
No water permit application approved by the board pursuant to § 46-2A-7.6 may be transferred until the water has been placed to beneficial use as specified in the permit. For a permit to irrigate, no transfer of water or acreage may be approved for an amount of water or acres gre…
SDCL § 46-2A-8 Time for completion of construction and use of water--Application for lesser amount of water or variance in periods of use
0.5K chars
Any construction necessary to put the water to beneficial use shall be completed within five years of approval of the permit and the water shall be put to beneficial use within an additional four years. The Water Management Board may, in its discretion, approve any application fo…
SDCL § 46-2A-8.1 Reinstatement of permit after expiration of time for construction--Application--Priority
0.2K chars
The Water Management Board may reinstate any water permit with a priority date after March 31, 1977, if unappropriated water is available and construction necessary to put water to beneficial use was not completed pursuant to § 46-2A-8 or
SDCL § 46-2A-9 Appropriation of water--When permit may be issued
0.5K chars
A permit to appropriate water may only be issued if there is reasonable probability that unappropriated water is available for the applicant's proposed use, the proposed diversion can be developed without unlawful impairment of existing domestic water uses and water rights, the p…