When preconstruction service considered complete.

Utah Code § 38-1a-404, under Part 38-1a-4: Preconstruction Lien Provisions.

Utah Code § 38-1a-404

38-1a-404. When preconstruction service considered complete.

Preconstruction service is considered complete for any project, project phase, or bid package as of the date that construction work for that project, project phase, or bid package, respectively, commences.