Preconstruction liens on equal footing.

Utah Code § 38-1a-405, under Part 38-1a-4: Preconstruction Lien Provisions.

Utah Code § 38-1a-405

38-1a-405. Preconstruction liens on equal footing.

(1) Each preconstruction lien on a project property is on equal footing with every other preconstruction lien on the project property, regardless of: when the claimant submitted the claimant's notice of preconstruction service for recording; when the claimant submitted the claimant's notice of preconstruction lien for recording; or when the preconstruction service related to the lien occurs.

(2) Subsectiondoes not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter. (1)