Cancellation of preconstruction or construction lien -- Penalty for failure to cancel timely.

Utah Code § 38-1a-803, under Part 38-1a-8: Actions Affecting Preconstruction and Construction Liens.

Utah Code § 38-1a-803

38-1a-803. Cancellation of preconstruction or construction lien -- Penalty for failure to cancel timely.

(1) After the full amount owing under a preconstruction or construction lien, including costs and cancellation fees, has been paid, a person interested in the property that is the subject of the lien may request the claimant to submit for recording with the office of each applicable county recorder a cancellation of the lien.

(2) Within 10 days after receiving a request under Subsection, the claimant shall submit to the office of each applicable county recorder a cancellation of the preconstruction or construction lien, as applicable. (1)

(3) A claimant who fails to submit a cancellation within the time prescribed in Subsectionis liable to the person who requested the cancellation for $100 for each day after the time prescribed in Subsectionthat the cancellation is not submitted, or the person's actual damages, whichever is greater. (2) (2)