54-26-402. Alternative service requirements.
(1) A large load customer may enter into a large load contract with a large-scale generation provider if: a qualified electric utility fails to complete an evaluation or provide a written response within the time period specified in Section; or 54-26-202 the qualified electric utility and large load customer cannot agree to a large load contract within 90 days after the day on which the large load customer receives the evaluation described in Section, unless the qualified electric utility and the large load customer mutually agree to a longer period of time. 54-26-202
(2) After submitting a large-scale service request, a large load customer: may negotiate a contract with one or more large-scale generation providers; and may not execute a contract with a large-scale generation provider unless the conditions described in Subsection (1) are met.