54-26-502. Operating requirements -- Registration suspension.
(1) A large-scale generation provider that fails to satisfy the requirements of this chapter: may not initiate new service to a large load customer; shall remedy any deficiencies within 90 days after the day on which the deficiency arises; and may have reasonable conditions imposed by the commission on the provider's registration status.
(2) If the commission suspends or revokes a large-scale generation provider's registration: the provider may not continue to provide service to a large load customer after the large load customer has been given a reasonable opportunity to secure alternative service arrangements; and the large load customer may not receive electric service from another large-scale generation provider or a qualified electric utility except pursuant to agreement and commission approval of the terms of a new large load contract consistent with this chapter.