63A-5b-401. Definitions.
As used in this part:
(1) "Capital development project" means: a remodeling or site or utility improvement project with a total cost of $3,500,000 or more; a new facility with a construction cost of $500,000 or more; or a purchase of real property if an appropriation is requested and made for the purchase. "Capital development project" does not include a capital improvement project.
(2) "Capital improvement project" means: a remodeling, alteration, replacement, repair, or site or utility improvement project: with a total cost of less than $3,500,000; or with a total cost of $3,500,000 or more; and that will be paid for with funds that are not state funds; a utility infrastructure improvement project that: has a total cost of less than $7,000,000; consists of two or more projects that, if done separately, would each cost less than $3,500,000; and the division determines is more cost effective or feasible to be completed as a single project; or a new facility with a total construction cost of less than $500,000.
(3) "New facility" means a new building constructed on state property regardless of the source of the funding that pays for construction of the new building. "New facility" includes: an addition to an existing building; and the enclosure of space that was not previously fully enclosed. "New facility" does not include: the replacement of state-owned space that is demolished or that is otherwise removed from state use, if the total construction cost of the replacement space is less than $3,500,000; or the construction of facilities that do not fully enclose a space.
(4) "Replacement cost" means, as determined by the Division of Risk Management: for state facilities, excluding auxiliary facilities as defined by the director, the cost to replace those facilities; and for infrastructure, as defined by the director, the cost to replace the infrastructure.
(5) "State funds" means public money appropriated by the Legislature.