Preconstruction liens on equal footing.

Utah Code § 38-1a-405, under Part 38-1a-4: Preconstruction Lien Provisions.

Utah Code § 38-1a-405

38-1a-405. Preconstruction liens on equal footing.

(1) Each preconstruction lien on a project property is on equal footing with every other preconstruction lien on the project property, regardless of:

(a) when the claimant submitted the claimant's notice of preconstruction service for recording;

(b) when the claimant submitted the claimant's notice of preconstruction lien for recording; or

(c) when the preconstruction service related to the lien occurs.

(2) Subsection (1) does not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter.