15 chapters · 164 sections in this title.
Utah Code § 38-1a-803 Cancellation of preconstruction or construction lien -- Penalty for failure to cancel timely.
1.0K chars
38-1a-803. Cancellation of preconstruction or construction lien -- Penalty for failure to cancel timely. (1) After the full amount owing under a preconstruction or construction lien, including costs and cancellation fees, has been paid, a person interested in the property that is…
Utah Code § 38-1a-804 Notice of release of lien and substitution of alternate security.
7.3K chars
38-1a-804. Notice of release of lien and substitution of alternate security. (1) The owner of any interest in a project property that is subject to a recorded preconstruction or construction lien, or any original contractor or subcontractor affected by the lien, who disputes the …
Utah Code § 38-1a-805 Failure to file notice -- Petition to nullify preconstruction or construction lien -- Expedited proceeding.
5.7K chars
38-1a-805. Failure to file notice -- Petition to nullify preconstruction or construction lien -- Expedited proceeding. (1) An owner of an interest in a project property that is subject to a recorded preconstruction lien or a recorded construction lien may petition a court with ju…
Title.
0.1K chars
38-1b-101. Title. This chapter is known as "Government Construction Projects."