Use of fully coordinated permitting process.

RCW 80.50.065, under Energy facilities—Site locations..

RCW 80.50.065

Applicants utilizing the fully coordinated permitting process under chapter 43.158 RCW are not eligible for permitting under this chapter unless a substantial change is made to the proposed project. Prior to considering an application under this chapter from a project applicant that has previously used the fully coordinated permitting process under chapter 43.158 RCW for that project, the council must determine that the project applicant has made a substantial change to the project, relative to the project as it was proposed under the fully coordinated permitting process.

[ 2023 c 230 s 211.]

Notes:

Findings—Intent—2023 c 230: See note following RCW 43.394.010.