RCW 60.28.011 Retained percentage—Public transportation projects—Labor and material lien created—Bond in lieu of retained funds—Termination before completion—Chapter deemed exclusive—Release of ferry contract payments—Projects of farmers home administration—General contractor/construction manager procedure—Definitions.
11.4K chars
(1)(a) Except as provided in (b) of this subsection, public improvement contracts must provide, and public bodies must reserve, a contract retainage not to exceed five percent of the moneys earned by the contractor as a trust fund for the protection and payment of: (i) The claims…
RCW 60.28.015 Recovery from retained percentage—Written notice to contractor of materials furnished.
1.5K chars
Every person, firm, or corporation furnishing materials, supplies, or equipment to be used in the construction, performance, carrying on, prosecution, or doing of any work for the state, or any county, city, town, district, municipality, or other public body, shall give to the co…
RCW 60.28.021 Excess over lien claims paid to contractor.
1.7K chars
After the expiration of the forty-five day period for giving notice of lien provided in RCW 60.28.011(2), and after receipt of the certificates of the department of revenue, the employment security department, and the department of labor and industries, and the public body is sat…
RCW 60.28.030 Foreclosure of lien—Limitation of action—Release of funds.
1.9K chars
Any person, firm, or corporation filing a claim against the reserve fund shall have four months from the time of the filing thereof in which to bring an action to foreclose the lien. The lien shall be enforced by action in the superior court of the county where filed, and shall b…