Title 33 › CHAPTER 36 — WATER RESOURCES DEVELOPMENT › SUBCHAPTER I — COST SHARING › § 2213a
For flood or coastal storm projects in areas with moderate or high earthquake risk, the Secretary must not count extra design or construction costs from addressing seismic concerns when doing the project's benefit‑cost analysis. Those extra seismic costs still get added to the project's total cost and must follow the project's normal cost‑sharing rules.