Title 33 › Chapter 36— WATER RESOURCES DEVELOPMENT › Subchapter I— COST SHARING › § 2213a
For flood risk or coastal storm projects in areas with moderate or high earthquake risk, the Secretary must not count extra design and construction costs for seismic safety when doing the project's benefit‑cost analysis. Outside the benefit‑cost analysis, those extra seismic costs must be included in the total project cost and follow the normal cost‑sharing rules for the project.
Full Legal Text
Navigation and Navigable Waters — Source: USLM XML via OLRC
Legislative History
Reference
Citation
33 U.S.C. § 2213a
Title 33 — Navigation and Navigable Waters
Last Updated
Apr 5, 2026
Release point: 119-73not60