Title 41 › Subtitle I — Federal Procurement Policy › CHAPTER 45 — CONTRACT FINANCING › § 4504
Agencies must pay only for work that is actually finished and meets the contract’s standards, and contractors must give the information the agency needs to check that. Progress payments cannot be more than 80% of the value of completed work until the contract’s terms, specifications, and price are final. This applies to contracts over $25,000.