§4504 Conditions for Progress Payments

Title 41 › Subtitle Subtitle I— Federal Procurement Policy › Chapter 45— CONTRACT FINANCING › § 4504

Last updated Apr 5, 2026|Official source

Summary

Agencies may pay only for completed work that meets contract standards, with the contractor providing proof; payments are capped at 80% until terms, specs, and price are definite, and this applies to contracts over $25,000.

Full Legal Text

Title 41, §4504

Public Contracts — Source: USLM XML via OLRC

(a)The executive agency shall ensure that a payment for work in progress (including materials, labor, and other items) under a contract of an executive agency that provides for those payments is commensurate with the work accomplished that meets standards established under the contract. The contractor shall provide information and evidence the executive agency determines is necessary to permit the executive agency to carry out this subsection.
(b)The executive agency shall ensure that progress payments referred to in subsection (a) are not made for more than 80 percent of the work accomplished under the contract as long as the executive agency has not made the contractual terms, specifications, and price definite.
(c)This section applies to a contract in an amount greater than $25,000.

Legislative History

Notes & Related Subsidiaries

Historical and Revision Notes

Revised SectionSource (U.S. Code)Source (Statutes at Large) 450441:255(e).June 30, 1949, ch. 288, title III, § 305(e), as added Pub. L. 103–355, title II, § 2051(e), Oct. 13, 1994, 108 Stat. 3304, as amended Pub. L. 104–106, title XLIII, § 4321(a)(4), Feb. 10, 1996, 110 Stat. 671.

Reference

Citations & Metadata

Citation

41 U.S.C. § 4504

Title 41Public Contracts

Last Updated

Apr 5, 2026

Release point: 119-73not60