§4707 Remission of Liquidated Damages

Title 41 › Subtitle I — Federal Procurement Policy › CHAPTER 47 — MISCELLANEOUS › § 4707

Last updated Aug 21, 2026|Official source

Summary

If a contract made by an agency head or an authorized officer has a late penalty for delay, the Treasury Secretary can reduce or cancel any part of that penalty if the agency head recommends it.

Full Legal Text

Title 41, §4707

Public Contracts, Source: USLM XML via OLRC

When a contract made on behalf of the Federal Government by the head of a Federal agency, or by an authorized officer of the agency, includes a provision for liquidated damages for delay, the Secretary of the Treasury on recommendation of the head of the agency may remit any part of the damages as the Secretary of the Treasury believes is just and equitable.

Legislative History

Notes & Related Subsidiaries

Historical and Revision Notes

Revised SectionSource (U.S. Code)Source (Statutes at Large) 470741:256a.Sept. 5, 1950, ch. 849, § 10(a), 64 Stat. 591; Pub. L. 104–316, title II, § 202(u), Oct. 19, 1996, 110 Stat. 3845.

Reference

Citations & Metadata

Citation

41 U.S.C. § 4707

Title 41, Public Contracts

Last Updated

Aug 21, 2026

Release point: 119-102