A contracting officer (the official who handles federal contracts) can reduce what the government owes a prime contractor by the amount of any kickback the prime contractor gave, took, or was charged in violation of the law. If the contracting officer directs it, the prime contractor must hold back the same amount from a subcontractor’s pay. The withheld money must either be sent to the agency or kept by the prime contractor if the government already reduced its payment. The prime contractor must tell the contracting officer when it keeps the money. Any such reduction or order is treated as a government claim under federal contracting rules.