The Commission can approve a plan that shares costs for transmission upgrades or new generator connections even if the applicant is not a member of a Commission-approved transmission organization, as long as the resulting rates are fair, not unfairly discriminatory or preferential, and consistent with sections 824d and 824e of title 16.

Full Legal Text

Title 42, §16441

The Public Health and Welfare, Source: USLM XML via OLRC

The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that—
(1)are just and reasonable;
(2)are not unduly discriminatory or preferential; and
(3)are otherwise consistent with section 824d and 824e of title 16.