Title 42The Public Health and WelfareRelease 119-73not60

§16441 Funding New Interconnection and Transmission Upgrades

Title 42 › Chapter 149— NATIONAL ENERGY POLICY AND PROGRAMS › Subchapter XII— ELECTRICITY › Part C— Transmission Rate Reform › § 16441

Last updated Apr 5, 2026|Official source

Summary

Commission may approve funding for transmission upgrades or interconnection, regardless of transmission‑organization membership, if rates are fair, non‑discriminatory, and consistent with 16 U.S.C. 824d and 824e.

Full Legal Text

Title 42, §16441

The Public Health and Welfare — Source: USLM XML via OLRC

The Commission may approve a participant funding plan that allocates costs related to transmission upgrades or new generator interconnection, without regard to whether an applicant is a member of a Commission-approved Transmission Organization, if the plan results in rates that—
(1)are just and reasonable;
(2)are not unduly discriminatory or preferential; and
(3)are otherwise consistent with section 824d and 824e of title 16.

Reference

Citations & Metadata

Citation

42 U.S.C. § 16441

Title 42The Public Health and Welfare

Last Updated

Apr 5, 2026

Release point: 119-73not60