Title 43Public LandsRelease 119-73not60

§1528 Authorization of Appropriations

Title 43 › Chapter 32— COLORADO RIVER BASIN PROJECT › Subchapter III— AUTHORIZED UNITS; PROTECTION OF EXISTING USES › § 1528

Last updated Apr 5, 2026|Official source

Summary

Authorizes $832,180,000 for building the Central Arizona Project. That amount covers construction and prepaying power generation and transmission but does not cover distribution and drainage for non-Indian lands. The amount can be adjusted up or down for normal changes in construction costs as shown by engineering cost indexes. Money is also allowed for operating and maintaining the project. Also authorizes $100,000,000 for building distribution and drainage for non-Indian lands, with the same kind of cost-index adjustments from September 30, 1968. The Secretary must make agreements so non-Federal partners pay at least 20 percent of those construction costs. Even though section 1543 might say otherwise, these appropriations and revenues for those facilities will not go into the Lower Colorado River Basin Development Fund, and no payments will be made from that fund back to the Treasury to recover any of those facility costs.

Full Legal Text

Title 43, §1528

Public Lands — Source: USLM XML via OLRC

(a)There is hereby authorized to be appropriated for construction of the Central Arizona Project, including prepayment for power generation and transmission facilities but exclusive of distribution and drainage facilities for non-Indian lands, $832,180,000 plus or minus such amounts, if any, as may be justified by reason of ordinary fluctuations in construction costs as indicated by engineering cost indices applicable to the types of construction involved therein and, in addition thereto, such sums as may be required for operation and maintenance of the project.
(b)There is also authorized to be appropriated $100,000,000 for construction of distribution and drainage facilities for non-Indian lands plus or minus such amounts, if any, as may be justified by reason of ordinary fluctuations in construction costs as indicated by engineering and cost indices applicable to the types of construction involved therein from September 30, 1968: Provided, That the Secretary shall enter into agreements with non-Federal interests to provide not less than 20 per centum of the total cost of such facilities during the construction of such facilities. Notwithstanding the provisions of section 1543 of this title, neither appropriations made pursuant to the authorization contained in this subsection nor revenues collected in connection with the operation of such facilities shall be credited to the Lower Colorado River Basin Development Fund and payments shall not be made from that fund to the general fund of the Treasury to return any part of the costs of construction, operation, and maintenance of such facilities.

Legislative History

Notes & Related Subsidiaries

Editorial Notes

Amendments

1983—Subsec. (b). Pub. L. 97–373 substituted “There is also authorized to be appropriated $100,000,000 for

Construction

of distribution and drainage facilities for non-Indian lands plus or minus such amounts, if any, as may be justified by reason of ordinary fluctuations in

Construction

costs as indicated by engineering and cost indices applicable to the types of

Construction

involved therein from September 30, 1968: Provided, That the Secretary shall enter into agreements with non-Federal interests to provide not less than 20 per centum of the total cost of such facilities during the

Construction

of such facilities” for “There is also authorized to be appropriated $100,000,000 for

Construction

of distribution and drainage facilities for non-Indian lands”.

Reference

Citations & Metadata

Citation

43 U.S.C. § 1528

Title 43Public Lands

Last Updated

Apr 5, 2026

Release point: 119-73not60