Ampersand Ogdensburg Hydro Applies for License Renewal

Published Date: 6/17/2025

Notice

Summary

Ampersand Ogdensburg Hydro, LLC has applied to renew its license for the Ogdensburg Hydroelectric Project on the Oswegatchie River in New York. The public and agencies have until July 29, 2025, to ask for extra studies or join the review process. This relicensing could affect local energy production and environmental rules, so stay tuned for updates and possible changes.

Analyzed Economic Effects

4 provisions identified: 2 benefits, 1 costs, 1 mixed.

Operations, Flow Rules, and Environmental Measures

Ampersand proposes to continue operating the project in run-of-river mode, maintain the impoundment at or above the spillway crest elevation of 258.0 feet mean sea level, and follow specific flow rules (minimum and maximum powerhouse capacities of 183 and 3,650 cfs, minimum flow releases and operational discharge patterns including 183 cfs, 450 cfs, 632 cfs, and 730 cfs thresholds). Ampersand also proposes to implement an Invasive Species Management Plan and to consult with the New York State Historic Preservation Officer before land-clearing or land-disturbing activities.

Application Filed; Public Can Participate

Ampersand Ogdensburg Hydro filed a new license application for the Ogdensburg Hydroelectric Project (P-9821-109) on May 30, 2025. The public and agencies can view the filing and participate in the relicensing process, and are specifically invited to request additional studies or cooperating-agency status.

Deadline to Request Extra Studies

If you want the Commission to require extra scientific studies, you must file a study request and serve the applicant by 5:00 p.m. Eastern Time on July 29, 2025. Use FERC's eFiling system or submit a paper filing that clearly identifies Ogdensburg Hydroelectric Project (P-9821-109).

Cooperating Agencies Can't Also Intervene

Agencies that choose to cooperate in preparing the Commission's environmental document are subject to the Commission's policy that cooperating agencies cannot also intervene in the proceeding (see 94 FERC ¶ 61,076 (2001)).

Your PRIA Score

Score Hidden

Personalized for You

How does this regulation affect your finances?

Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.

Free to start

Key Dates

Published Date
6/17/2025

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML
Back to Federal Register

Take It Personal

Get Your Personalized Policy View

Start a Free Government Policy Watch to see how policy affects your household, then upgrade to PRIA Full Coverage for year-round monitoring.

Already have an account? Sign in