The Federal Energy Regulatory Commission may approve and run new Alaska natural gas pipeline projects that are not part of the 1976 Alaska system. It must issue a certificate to build and operate a project if the applicant meets the Natural Gas Act’s section 7(e) rules. The Commission will assume the project is needed and that there will be enough downstream pipeline capacity. Within 60 days after the final environmental impact statement under section 720b, the Commission must grant or deny the certificate. No federal permit may be given for any pipeline that goes under or along the Beaufort Sea shoreline and then enters Canada north of 68 degrees north latitude. By 120 days after October 13, 2004, the Commission had to make rules for open seasons (how capacity is offered), including timing and criteria, promoting competition, and allowing non‑Prudhoe Bay/Point Thomson gas for expansions. Capacity is allocated under those rules unless an expansion is ordered under section 720c. Applications for extra pipeline work from Canada follow the Natural Gas Act, and the 1976 Act still applies to facilities built under it. Certificate holders must study Alaska in‑State needs and planned tie‑in points. After a hearing, the State can ask to use the pipeline for royalty gas for local use, but that access cannot raise rates for shippers who already have capacity. The Commission may make any other rules needed to carry out these provisions.

Full Legal Text

Title 15, §720a

Commerce and Trade — Source: USLM XML via OLRC

(a)Notwithstanding the Alaska Natural Gas Transportation Act of 1976 (15 U.S.C. 719 et seq.), the Commission may, in accordance with section 7(c) of the Natural Gas Act (15 U.S.C. 717f(c)), consider and act on an application for the issuance of a certificate of public convenience and necessity authorizing the construction and operation of an Alaska natural gas transportation project other than the Alaska natural gas transportation system.
(b)(1)The Commission shall issue a certificate of public convenience and necessity authorizing the construction and operation of an Alaska natural gas transportation project under this section if the applicant has satisfied the requirements of section 7(e) of the Natural Gas Act (15 U.S.C. 717f(e)).
(2)In considering an application under this section, the Commission shall presume that—
(A)a public need exists to construct and operate the proposed Alaska natural gas transportation project; and
(B)sufficient downstream capacity will exist to transport the Alaska natural gas moving through the project to markets in the contiguous United States.
(c)Not later than 60 days after the date of issuance of the final environmental impact statement under section 720b of this title for an Alaska natural gas transportation project, the Commission shall issue a final order granting or denying any application for a certificate of public convenience and necessity for the project under section 7(c) of the Natural Gas Act (15 U.S.C. 717f(c)) and this section.
(d)No license, permit, lease, right-of-way, authorization, or other approval required under Federal law for the construction of any pipeline to transport natural gas from land within the Prudhoe Bay oil and gas lease area may be granted for any pipeline that follows a route that—
(1)traverses land beneath navigable waters (as defined in section 1301 of title 43) beneath, or the adjacent shoreline of, the Beaufort Sea; and
(2)enters Canada at any point north of 68 degrees north latitude.
(e)(1)Not later than 120 days after October 13, 2004, the Commission shall issue regulations governing the conduct of open seasons for Alaska natural gas transportation projects (including procedures for the allocation of capacity).
(2)The regulations referred to in paragraph (1) shall—
(A)include the criteria for and timing of any open seasons;
(B)promote competition in the exploration, development, and production of Alaska natural gas; and
(C)for any open season for capacity exceeding the initial capacity, provide the opportunity for the transportation of natural gas other than from the Prudhoe Bay and Point Thomson units.
(3)Except in a case in which an expansion is ordered in accordance with section 720c of this title, initial or expansion capacity on any Alaska natural gas transportation project shall be allocated in accordance with procedures to be established by the Commission in regulations issued under paragraph (1).
(f)(1)An application for additional or expanded pipeline facilities that may be required to transport Alaska natural gas from Canada to markets in the contiguous United States may be made in accordance with the Natural Gas Act [15 U.S.C. 717 et seq.].
(2)To the extent that a pipeline facility described in paragraph (1) includes the expansion of any facility constructed in accordance with the Alaska Natural Gas Transportation Act of 1976 (15 U.S.C. 719 et seq.), that Act shall continue to apply.
(g)The holder of the certificate of public convenience and necessity issued, modified, or amended by the Commission for an Alaska natural gas transportation project shall demonstrate that the holder has conducted a study of Alaska in-State needs, including tie-in points along the Alaska natural gas transportation project for in-State access.
(h)(1)Except as provided in paragraph (2), the Commission, on a request by the State and after a hearing, may provide for reasonable access to the Alaska natural gas transportation project by the State (or State designee) for the transportation of royalty gas of the State for the purpose of meeting local consumption needs within the State.
(2)The rates of shippers of subscribed capacity on an Alaska natural gas transportation project described in paragraph (1), as in effect as of the date on which access under that paragraph is granted, shall not be increased as a result of such access.
(i)The Commission may issue such regulations as are necessary to carry out this section.

Legislative History

Notes & Related Subsidiaries

Editorial Notes

References in Text

The Alaska Natural Gas Transportation Act of 1976, referred to in subsecs. (a) and (f)(2), is Pub. L. 94–586, Oct. 22, 1976, 90 Stat. 2903, which is classified generally to chapter 15C (§ 719 et seq.) of this title. For complete classification of this Act to the Code, see

Short Title

note set out under section 719 of this title and Tables. The Natural Gas Act, referred to in subsec. (f)(1), is act June 21, 1938, ch. 556, 52 Stat. 821, which is classified generally to chapter 15B (§ 717 et seq.) of this title. For complete classification of this Act to the Code, see section 717w of this title and Tables.