Require local or state partners to pay set shares and provide land for water projects. For flood control projects that are not nonstructural, the non-Federal partner must pay 5% of the flood-control cost during construction, give all needed land, rights-of-way, dredged material disposal areas, and do any relocations, and cover the flood-control part of any shared land costs. If those things add up to less than 35% of the flood-control cost, the partner must pay more during construction so the total equals 35%. The partner’s share cannot be more than 50%. If the partner’s required contribution is more than 30% of the flood-control cost, the extra amount may be paid to the federal government over 15 years after project completion with interest set under the law, but the 5% up front still must be paid during construction. For projects using nonstructural or nature-based features, the non-Federal share is 35%. The partner must still provide lands and relocations but may not have to pay cash during construction if land and relocation costs alone exceed 35%. If, during construction, land and partner contributions are expected to exceed 35%, the federal share will cover the excess up to 65% of total project costs. Other cost shares: hydroelectric power 100%, municipal and industrial water 100%, agricultural water 35%, recreation 50% of separable costs, hurricane and storm damage reduction 35%, aquatic plant control 50% of operations, and environmental protection and restoration 35%. Beach erosion and water-quality costs follow these purpose shares. Costs that benefit private shores or prevent private land loss are paid by non-Federal interests; costs to protect federally owned shores are paid by the United States. For periodic beach nourishment on projects authorized after December 31, 1999 (unless a District Engineer’s report was already done), non-Federal shares rise to 40% after January 1, 2001; 45% after January 1, 2002; and 50% after January 1, 2003. Apply these rules to projects that start construction after April 30, 1986, with a few named exceptions. A “separable element” is a physically separate part of a project that has its own effects or benefits. Some specified projects had a three-year delay in required payments starting November 17, 1986. Before work begins on a covered project (except hydroelectric), non-Federal partners must sign binding agreements to pay 100% of operation, maintenance, replacement, and rehabilitation costs, to pay their construction share, and to protect the United States from damages except for U.S. fault. Agreements must include an estimate of future operation and maintenance costs. If a partner fails to provide required funds, the Secretary can stop or suspend work or change the partner’s project rights. Partners may pay without interest during construction or choose repayment with interest over up to 30 years after completion; interest rates are recalculated every five years. The Secretary can renegotiate certain deferred-payment deals, credit partner costs that fix design or construction problems toward their share, and accept large early payments under special terms (including possible credit by providing fish and wildlife mitigation if conditions are met). A partner may delay the first payment up to one year after construction starts (with short interest charges), and the Secretary may grant one one-year waiver of interest accrual if it will help the partner pay and the partner is in good standing. Cost-sharing deals for many project types must consider the partner’s ability to pay, using local income, per-capita project cost, financial capacity, whether the community is economically disadvantaged, and other factors. The Secretary must create procedures for partners to ask for a reduced share and must report yearly to Congress on those requests and decisions. The Secretary may not ask partners for more than the required non-Federal share or make federal help conditional on extra contributions.

Full Legal Text

Title 33, §2213

Navigation and Navigable Waters — Source: USLM XML via OLRC

(a)(1)The non-Federal interests for a project with costs assigned to flood control (other than a nonstructural project) shall—
(A)pay 5 percent of the cost of the project assigned to flood control during construction of the project;
(B)provide all lands, easements, rights-of-way, and dredged material disposal areas required only for flood control and perform all related necessary relocations; and
(C)provide that portion of the joint costs of lands, easements, rights-of-way, dredged material disposal areas, and relocations which is assigned to flood control.
(2)If the value of the contributions required under paragraph (1) of this subsection is less than 35 percent of the cost of the project assigned to flood control, the non-Federal interest shall pay during construction of the project such additional amounts as are necessary so that the total contribution of the non-Federal interests under this subsection is equal to 35 percent of the cost of the project assigned to flood control.
(3)The non-Federal share under paragraph (1) shall not exceed 50 percent of the cost of the project assigned to flood control. The preceding sentence does not modify the requirement of paragraph (1)(A) of this subsection.
(4)If the total amount of the contribution required under paragraph (1) of this subsection exceeds 30 percent of the cost of the project assigned to flood control, the non-Federal interests may pay the amount of the excess to the Secretary over a 15-year period (or such shorter period as may be agreed to by the Secretary and the non-Federal interests) beginning on the date construction of the project or separable element is completed, at an interest rate determined pursuant to section 2216 of this title. The preceding sentence does not modify the requirement of paragraph (1)(A) of this subsection.
(b)(1)The non-Federal share of the cost of a flood risk management or hurricane and storm damage risk reduction measure using a nonstructural feature, or a natural feature or nature-based feature (as those terms are defined in section 2289a(a) of this title), shall be 35 percent of the cost of such measures. The non-Federal interests for any such measures shall be required to provide all lands, easements, rights-of-way, dredged material disposal areas, and relocations necessary for the project, but shall not be required to contribute any amount in cash during construction for a nonstructural feature if the costs of land, easements, rights-of-way, dredged material disposal areas, and relocations for such feature are estimated to exceed 35 percent.
(2)At any time during construction of a project, if the Secretary determines that the costs of land, easements, rights-of-way, dredged material disposal areas, and relocations for the project, in combination with other costs contributed by the non-Federal interests, will exceed 35 percent, any additional costs for the project (not to exceed 65 percent of the total costs of the project) shall be a Federal responsibility and shall be contributed during construction as part of the Federal share.
(c)The non-Federal share of the cost assigned to other project purposes shall be as follows:
(1)hydroelectric power: 100 percent, except that the marketing of such power and the recovery of costs of constructing, operating, maintaining, and rehabilitating such projects shall be in accordance with existing law: Provided, That after November 17, 1986, the Secretary shall not submit to Congress any proposal for the authorization of any water resources project that has a hydroelectric power component unless such proposal contains the comments of the appropriate Power Marketing Administrator designated pursuant to section 7152 of title 42 concerning the appropriate Power Marketing Administration’s ability to market the hydroelectric power expected to be generated and not required in the operation of the project under the applicable Federal power marketing law, so that, 100 percent of operation, maintenance and replacement costs, 100 percent of the capital investment allocated to the purpose of hydroelectric power (with interest at rates established pursuant to or prescribed by applicable law), and any other costs assigned in accordance with law for return from power revenues can be returned within the period set for the return of such costs by or pursuant to such applicable Federal power marketing law;
(2)municipal and industrial water supply: 100 percent;
(3)agricultural water supply: 35 percent;
(4)recreation, including recreational navigation: 50 percent of separable costs and, in the case of any harbor or inland harbor or channel project, 50 percent of joint and separable costs allocated to recreational navigation;
(5)hurricane and storm damage reduction: 35 percent;
(6)aquatic plant control: 50 percent of control operations; and
(7)environmental protection and restoration: 35 percent; except that nothing in this paragraph shall affect or limit the applicability of section 2283 of this title.
(d)(1)Costs of constructing projects or measures for beach erosion control and water quality enhancement shall be assigned to appropriate project purposes listed in subsections (a), (b), and (c) and shall be shared in the same percentage as the purposes to which the costs are assigned, except that all costs assigned to benefits to privately owned shores (where use of such shores is limited to private interests) or to prevention of losses of private lands shall be borne by non-Federal interests and all costs assigned to the protection of federally owned shores shall be borne by the United States.
(2)(A)In the case of a project authorized for construction after December 31, 1999, except for a project for which a District Engineer’s Report is completed by that date, the non-Federal cost of the periodic nourishment of the project, or any measure for shore protection or beach erosion control for the project, that is carried out—
(i)after January 1, 2001, shall be 40 percent;
(ii)after January 1, 2002, shall be 45 percent; and
(iii)after January 1, 2003, shall be 50 percent.
(B)All costs assigned to benefits of periodic nourishment projects or measures to privately owned shores (where use of such shores is limited to private interests) or to prevention of losses of private land shall be borne by the non-Federal interest.
(C)All costs assigned to the protection of federally owned shores for periodic nourishment measures shall be borne by the United States.
(e)(1)This section applies to any project (including any small project which is not specifically authorized by Congress and for which the Secretary has not approved funding before November 17, 1986), or separable element thereof, on which physical construction is initiated after April 30, 1986, as determined by the Secretary, except as provided in paragraph (2). For the purpose of the preceding sentence, physical construction shall be considered to be initiated on the date of the award of a construction contract.
(2)This section shall not apply to the Yazoo Basin, Mississippi, Demonstration Erosion Control Program, authorized by Public Law 98–8, or to the Harlan, Kentucky, or Barbourville, Kentucky, elements of the project authorized by section 202 of Public Law 96–367.
(f)For purposes of this Act, the term “separable element” means a portion of a project—
(1)which is physically separable from other portions of the project; and
(2)which—
(A)achieves hydrologic effects, or
(B)produces physical or economic benefits,
(g)(1)With respect to the projects listed in paragraph (2), no amount of the non-Federal share required under this section shall be required to be paid during the three-year period beginning on November 17, 1986.
(2)The projects referred to in paragraph (1) are the following:
(A)Boeuf and Tensas Rivers, Tensas Basin, Louisiana and Arkansas, authorized by the Flood Control Act of 1946;
(B)Eight Mile Creek, Arkansas, authorized by Public Law 99–88; and
(C)Rocky Bayou Area, Yazoo Backwater Area, Yazoo Basin, Mississippi, authorized by the Flood Control Act approved August 18, 1941.
(h)The share of the costs specified under this section for each project purpose shall apply to the joint and separable costs of construction of each project assigned to that purpose, except as otherwise specified in this Act.
(i)Except as provided under section 2283(c) of this title, the non-Federal interests for a project to which this section applies shall provide all lands, easements, rights-of-way, and dredged material disposal areas required for the project and perform all necessary relocations, except to the extent limited by any provision of this section. The value of any contribution under the preceding sentence shall be included in the non-Federal share of the project specified in this section.
(j)(1)(A)Any project to which this section applies (other than a project for hydroelectric power) shall be initiated only after non-Federal interests have entered into binding agreements with the Secretary to pay 100 percent of the operation, maintenance, and replacement and rehabilitation costs of the project, to pay the non-Federal share of the costs of construction required by this section, and to hold and save the United States free from damages due to the construction or operation and maintenance of the project, except for damages due to the fault or negligence of the United States or its contractors.
(B)An agreement under subparagraph (A) shall include a brief description and estimation of the anticipated operations, maintenance, and replacement and rehabilitation costs of the non-Federal interest for the project.
(2)The agreement required pursuant to paragraph (1) shall be in accordance with the requirements of section 1962d–5b of title 42 and shall provide for the rights and duties of the United States and the non-Federal interest with respect to the construction, operation, and maintenance of the project, including, but not limited to, provisions specifying that, in the event the non-Federal interest fails to provide the required non-Federal share of costs for such work, the Secretary—
(A)shall terminate or suspend work on the project unless the Secretary determines that continuation of the work is in the interest of the United States or is necessary in order to satisfy agreements with other non-Federal interests in connection with the project; and
(B)may terminate or adjust the rights and privileges of the non-Federal interest to project outputs under the terms of the agreement.
(k)(1)Except as otherwise provided in this section, the Secretary may permit the full non-Federal contribution to be made without interest during construction of the project or separable element, or with interest at a rate determined pursuant to section 2216 of this title over a period of not more than thirty years from the date of completion of the project or separable element. Repayment contracts shall provide for recalculation of the interest rate at five-year intervals.
(2)(A)At the request of a non-Federal interest, the Secretary and the non-Federal interest may renegotiate the terms and conditions of an eligible deferred payment, including—
(i)permitting the non-Federal contribution to be made without interest, pursuant to paragraph (1);
(ii)recalculation of the interest rate;
(iii)full or partial forgiveness of interest accrued during the period of construction; and
(iv)a credit against construction interest for a non-Federal investment that benefits the completion or performance of the project or separable element.
(B)An eligible deferred payment agreement under subparagraph (A) is an agreement for which—
(i)the non-Federal contribution was made with interest;
(ii)the period of project construction exceeds 10 years from the execution of a project partnership agreement or appropriation of funds; and
(iii)the construction interest exceeds $45,000,000.
(3)(A)The Secretary is authorized to credit any costs incurred by the non-Federal interest (including in-kind contributions) to remedy a design or construction deficiency of a covered project or separable element toward the non-Federal share of the cost of the covered project, if the Secretary determines the remedy to be integral to the completion or performance of the covered project.
(B)If the non-Federal interest incurs costs or in-kind contributions for a project to remedy a design or construction deficiency of a project or separable element which has a 100 percent Federal cost share, and the Secretary determines the remedy to be integral to the completion or performance of the project, the Secretary is authorized to credit such costs to any interest accrued on a deferred non-Federal contribution.
(4)(A)Notwithstanding a deferred payment agreement with a non-Federal interest, the Secretary shall accept, without interest of any type, the repayment of a non-Federal contribution for any eligible deferred payment described in paragraph (2)(B) for which—
(i)the non-Federal interest made a payment of at least $200,000,000 for that eligible deferred payment agreement on or before September 30, 2021;
(ii)the non-Federal interest made a payment of an additional $200,000,000 for that eligible deferred payment agreement on or before September 30, 2023; and
(iii)the non-Federal interest repays the balance of remaining principal by June 1, 2032.
(B)Repayment of a non-Federal interest’s contribution under subparagraph (A)(iii) may be satisfied through the provision by the non-Federal interest of fish and wildlife mitigation for one or more projects or separable elements, if the Secretary determines that—
(i)the non-Federal interest has incurred costs for the provision of mitigation that—
(I)equal or exceed the amount of the required repayment; and
(II)are in excess of any required non-Federal interest’s contribution for the project or separable element for which the mitigation is provided; and
(ii)the mitigation is integral to the project for which it is provided.
(C)Any agreement made that applied credits to satisfy the terms of a pre-payment made under subsection (k)(4)(A) that resulted in total payment in excess of the amount now required under subsection (k)(4)(A) shall be modified to indicate that the excess credits continue to apply toward any remaining principal of the respective project, or at the request of the non-Federal interest, the agreement shall be modified to retroactively transfer back those excess credits to the non-Federal interest such that those credits may be applied by the non-Federal interest to any cost-shared project identified by the non-Federal interest.
(5)(A)Upon receipt of a request for a renegotiation of terms by a non-Federal interest under paragraph (2), the Secretary shall submit to the Committee on Transportation and Infrastructure of the House and the Committee on Environment and Public Works of the Senate a report 30 days after enactment and quarterly thereafter regarding the status of the request.
(B)It is the sense of Congress that the Secretary should respond to any request for a renegotiation of terms submitted under paragraph (2) in a timely manner.
(l)(1)At the request of any non-Federal interest the Secretary may permit such non-Federal interest to delay the initial payment of any non-Federal contribution under this section or section 2211 of this title for up to one year after the date when construction is begun on the project for which such contribution is to be made. Any such delay in initial payment shall be subject to interest charges for up to six months at a rate determined pursuant to section 2216 of this title.
(2)(A)At the request of any non-Federal interest, the Secretary may waive the accrual of interest on any non-Federal cash contribution under this section or section 2211 of this title for a project for a period of not more than 1 year if the Secretary determines that—
(i)the waiver will contribute to the ability of the non-Federal interest to make future contributions; and
(ii)the non-Federal interest is in good standing under terms agreed to under subsection (k)(1).
(B)The Secretary may grant not more than 1 waiver under subparagraph (A) for the same project.
(m)(1)Any cost-sharing agreement under this section for a feasibility study, or for construction of an environmental protection and restoration project, a flood control project, a project for navigation, storm damage protection, shoreline erosion, hurricane protection, or recreation, or an agricultural water supply project, shall be subject to the ability of the non-Federal interest to pay.
(2)The Secretary shall determine the ability of a non-Federal interest to pay under this subsection by considering—
(A)per capita income data for the county or counties in which the project is to be located;
(B)the per capita non-Federal cost of construction of the project for the county or counties in which the project is to be located;
(C)the financial capabilities of the non-Federal interest for the project;
(D)the extent to which the non-Federal interest is an economically disadvantaged community (as defined pursuant to section 160 of the Water Resources Development Act of 2020 (33 U.S.C. 2201 note)); and
(E)any additional criteria relating to the non-Federal interest’s financial ability to carry out its cost-sharing responsibilities determined appropriate by the Secretary.
(3)For purposes of carrying out paragraph (2), the Secretary shall develop procedures—
(A)to allow a non-Federal interest to identify the amount such non-Federal interest would likely be able to pay; and
(B)for a non-Federal interest to submit a request to the Secretary to reduce the required non-Federal share.
(4)Notwithstanding subsection (a), the Secretary may reduce the requirement that a non-Federal interest make a cash contribution for any project that is determined to be eligible for a reduction in the non-Federal share under criteria and procedures in effect under paragraphs (1), (2), and (3).
(5)This subsection shall not apply to project costs greater than the national economic development plan.
(6)(A)Not less frequently than annually, the Secretary shall submit to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate a report describing all determinations of the Secretary under this subsection regarding the ability of a non-Federal interest to pay.
(B)The Secretary shall include in each report required under subparagraph (A) a description, for the applicable year, of—
(i)requests by a non-Federal interest to reduce the non-Federal share required in a cost-sharing agreement, including—
(I)the name of the non-Federal interest that submitted to the Secretary a request for a determination under this subsection; and
(II)the name and location of the project;
(ii)the determination of the Secretary with respect to each such request;
(iii)the basis for each such determination; and
(iv)the adjusted share of the costs of the project of the non-Federal interest, if applicable.
(C)The Secretary may include a determination to reduce the non-Federal share required in a cost-sharing agreement for construction of a project in the report of the Chief of Engineers for the project.
(n)(1)The Secretary may not—
(A)solicit contributions from non-Federal interests for costs of constructing authorized water resources projects or measures in excess of the non-Federal share assigned to the appropriate project purposes listed in subsections (a), (b), and (c); or
(B)condition Federal participation in such projects or measures on the receipt of such contributions.
(2)Nothing in this subsection shall be construed to affect the Secretary’s authority under section 903(c).11 See References in Text note below.

Legislative History

Notes & Related Subsidiaries

Editorial Notes

References in Text

Public Law 98–8, referred to in subsec. (e)(2), is Pub. L. 98–8, Mar. 24, 1983, 97 Stat. 13. For complete classification of this Act to the Code, see Tables. section 202 of Public Law 96–367, referred to in subsec. (e)(2), is section 202 of Pub. L. 96–367, title II, Oct. 1, 1980, 94 Stat. 1339, which is not classified to the Code. This Act, referred to in subsecs. (f) and (h), is Pub. L. 99–662, Nov. 17, 1986, 100 Stat. 4082, known as the Water Resources Development Act of 1986. For complete classification of this Act to the Code, see

Short Title

note set out under section 2201 of this title and Tables. The Flood Control Act of 1946, referred to in subsec. (g)(2)(A), is act
July 24, 1946, ch. 596, 60 Stat. 641. For complete classification of this Act to the Code, see Tables. Public Law 99–88, referred to in subsec. (g)(2)(B), is Pub. L. 99–88, Aug. 15, 1985, 99 Stat. 293, known as the Supplemental Appropriations Act, 1985. Provisions of Pub. L. 99–88 authorizing the project for Eight Mile Creek, Arkansas, are not classified to the Code. For complete classification of this Act to the Code, see Tables. The Flood Control Act approved
August 18, 1941, referred to in subsec. (g)(2)(C), is act Aug. 18, 1941, ch. 377, 55 Stat. 638. For complete classification of this Act to the Code, see Tables. section 160 of the Water Resources Development Act of 2020, referred to in subsec. (m)(2)(D), is section 160 of div. AA of Pub. L. 116–260, which is set out as a note under section 2201 of this title. section 903(c), referred to in subsec. (n)(2), is section 903(c) of Pub. L. 99–662, title IX, Nov. 17, 1986, 100 Stat. 4184, which is not classified to the Code.

Amendments

2025—Subsec. (k)(4)(A)(i). Pub. L. 118–272, § 1358(1)(A), substituted “made” for “makes”. Subsec. (k)(4)(A)(ii). Pub. L. 118–272, § 1358(1)(B), substituted “made a payment of an additional $200,000,000 for that eligible deferred payment agreement on or before” for “repays an amount equal to ⅔ of the remaining principal by”. Subsec. (k)(4)(B), (i)(II). Pub. L. 118–272, § 1358(2), which directed amendment of subpar. (B) by inserting “interest’s” after “non-Federal”, was executed by making the insertion after “non-Federal” the first and fourth place appearing, to reflect the probable intent of Congress. Subsec. (k)(4)(C). Pub. L. 118–272, § 1358(3), added subpar. (C). Subsec. (k)(5). Pub. L. 118–272, § 1359, added par. (5). Subsec. (m)(2), (3). Pub. L. 118–272, § 1139(a)(1), added pars. (2) and (3) and struck out former pars. (2) and (3) which related to criteria and procedures and revision of criteria and procedures, respectively. Subsec. (m)(5), (6). Pub. L. 118–272, § 1139(a)(2), added pars. (5) and (6). 2022—Subsec. (k)(4). Pub. L. 117–263, § 8386, designated existing provisions as subpar. (A) and inserted heading, redesignated former subpars. (A) and (B) as cls. (i) and (ii), respectively, and realigned margins, substituted “$200,000,000” for “$200 million” in cl. (i), inserted “an amount equal to ⅔ of” after “repays” in cl. (ii), and added cl. (iii) of subpar. (A) and subpar. (B). Subsec. (l). Pub. L. 117–263, § 8385, struck out “initial” before “payment” in subsec. heading, designated existing provisions as par. (1) and inserted par. heading, and added par. (2). 2020—Subsec. (b). Pub. L. 116–260, § 115(b)(1), substituted “Projects using nonstructural, natural, or nature-based features” for “Nonstructural flood control projects” in heading. Subsec. (b)(1). Pub. L. 116–260, § 115(b)(2), substituted “a flood risk management or hurricane and storm damage risk reduction measure using a nonstructural feature, or a natural feature or nature-based feature (as those terms are defined in section 2289a(a) of this title),” for “nonstructural flood control measures” and “cash during

Construction

for a nonstructural feature if the costs of land, easements, rights-of-way, dredged material disposal areas, and relocations for such feature are estimated to exceed 35 percent” for “cash during

Construction

of the project”. Subsec. (j)(1). Pub. L. 116–260, § 143, designated existing provisions as subpar. (A), inserted heading, and added subpar. (B). Subsec. (k). Pub. L. 116–260, § 351, designated existing provisions as par. (1), inserted heading, and added pars. (2) to (4). 2007—Subsec. (m)(2). Pub. L. 110–114, § 2019(a), substituted “
December 31, 2007” for “180 days after
December 11, 2000”. Subsec. (n). Pub. L. 110–114, § 2001, added subsec. (n). 2000—Subsec. (m)(1), (2). Pub. L. 106–541, § 204(1), added pars. (1) and (2) and struck out former pars. (1) and (2) which required any cost-sharing agreement to be subject to the ability of a non-Federal interest to pay and required the Secretary to determine ability to pay using certain criteria and procedures. Subsec. (m)(3)(B), (C). Pub. L. 106–541, § 204(2), redesignated subpar. (C) as (B) and struck out former subpar. (B) which read as follows: “shall not consider criteria (other than criteria described in subparagraph (A)) in effect on the day before
October 12, 1996; and”. 1999—Subsec. (b). Pub. L. 106–53, § 219(c)(1), which directed insertion of the par. (1) designation and heading before “The non-Federal”, was executed by making the insertion before that phrase the first place it appeared to reflect the probable intent of Congress. Subsec. (b)(2). Pub. L. 106–53, § 219(c)(2), added par. (2). Subsec. (d). Pub. L. 106–53, § 215(a), designated existing provisions as par. (1), inserted heading, and added par. (2). Subsec. (d)(2)(A). Pub. L. 106–109 substituted “except for a project for which a District Engineer’s Report is completed by that date,” for “or for which a feasibility study is completed after that date,”. 1996—Subsecs. (a)(2), (b). Pub. L. 104–303, § 202(a)(1)(A), substituted “35 percent” for “25 percent” wherever appearing. Subsec. (c)(7). Pub. L. 104–303, § 210(a), added par. (7). Subsec. (e)(1). Pub. L. 104–303, § 202(a)(2), inserted at end “For the purpose of the preceding sentence, physical

Construction

shall be considered to be initiated on the date of the award of a

Construction

contract.” Subsec. (m). Pub. L. 104–303, § 202(b)(1), reenacted heading without change and amended text generally. Prior to amendment, text read as follows: “Any cost-sharing agreement under this section for flood control or agricultural water supply shall be subject to the ability of a non-Federal interest to pay. The ability of any non-Federal interest to pay shall be determined by the Secretary in accordance with procedures established by the Secretary.” 1992—Subsec. (i). Pub. L. 102–580, § 333(b)(2), substituted “Except as provided under section 2283(c) of this title, the non-Federal” for “The non-Federal”. Subsec. (m). Pub. L. 102–580, § 201(a), amended subsec. (m) generally. Prior to amendment, subsec. (m) read as follows: “(1) General rule.—Any cost-sharing agreement under this section for flood control or agricultural water supply shall be subject to the ability of a non-Federal interest to pay. “(2) Procedures.— “(A) In general.—The ability of any non-Federal interest to pay shall be determined by the Secretary in accordance with procedures established by the Secretary. “(B) Limitations.—The procedures established pursuant to this subsection shall provide for a reduction in any non-Federal cash contribution required under subsection (a)(2) of this section. In addition, such procedures shall provide for determination of the eligibility of the non-Federal interest for a reduction in the required cash contribution on the basis of local, not statewide, economic and financial data. “(C)

Regulations

.—Not later than 1 year after November 28, 1990, the Secretary shall issue

Regulations

establishing the procedures required by this paragraph.” 1990—Subsec. (m). Pub. L. 101–640 amended subsec. (m) generally. Prior to amendment, subsec. (m) read as follows: “Any cost-sharing agreement under this section for flood control or agricultural water supply shall be subject to the ability of a non-Federal interest to pay. The ability of any non-Federal interest to pay shall be determined by the Secretary in accordance with procedures established by the Secretary.”

Statutory Notes and Related Subsidiaries

Effective Date

of 1996 Amendment Pub. L. 104–303, title II, § 202(a)(1)(B), Oct. 12, 1996, 110 Stat. 3673, provided that: “The

Amendments

made by subparagraph (A) [amending this section] shall apply to any project authorized after the date of the enactment of this Act [Oct. 12, 1996] and to any flood control project that is not specifically authorized by Congress for which a Detailed Project Report is approved after such date of enactment or, in the case of a project for which no Detailed Project Report is prepared,

Construction

is initiated after such date of enactment.” Pub. L. 104–303, title II, § 202(b)(2), Oct. 12, 1996, 110 Stat. 3674, provided that: “(A) Generally.—Subject to subparagraph (C), the amendment made by paragraph (1) [amending this section] shall apply to any project, or separable element thereof, with respect to which the Secretary and the non-Federal interest enter into a project cooperation agreement after December 31, 1997. “(B) Amendment of cooperation agreement.—If requested by the non-Federal interest, the Secretary shall amend a project cooperation agreement executed on or before the date of the enactment of this Act [Oct. 12, 1996] to reflect the application of the amendment made by paragraph (1) to any project for which a contract for

Construction

has not been awarded on or before such date of enactment. “(C) Non-federal option.—If requested by the non-Federal interest, the Secretary shall apply the criteria and procedures established pursuant to section 103(m) of the Water Resources Development Act of 1986 [subsec. (m) of this section] as in effect on the day before the date of the enactment of this Act for projects that are authorized before the date of the enactment of this Act.” [Reference to “project cooperation agreement” deemed to be reference to “project partnership agreement”, see section 2003(f)(2) of Pub. L. 110–114, set out as a note under section 1962d–5b of Title 42, The Public Health and Welfare.] Pub. L. 104–303, title II, § 210(b), Oct. 12, 1996, 110 Stat. 3681, provided that: “The

Amendments

made by subsection (a) [amending this section] apply only to projects authorized after the date of the enactment of this Act [Oct. 12, 1996].” Continuation of Existing

Regulations

Pub. L. 101–640, title III, § 305(b), Nov. 28, 1990, 104 Stat. 4635, provided that: “

Regulations

issued to carry out section 103(m) of the Water Resources Development Act of 1986 [33 U.S.C. 2213(m)] before the date of the enactment of this Act [Nov. 28, 1990] and in effect on such date shall continue in effect until

Regulations

are issued pursuant to paragraph (2)(C) of such section, as added by subsection (a) of this section.” Update to Guidance Pub. L. 118–272, div. A, title I, § 1139(b), Jan. 4, 2025, 138 Stat. 3027, provided that: “Not later than 1 year after the date of enactment of this Act [Jan. 4, 2025], the Secretary [of the Army] shall update any agency guidance or regulation relating to the ability of a non-Federal interest to pay as necessary to reflect the

Amendments

made by this section [amending this section].” Reports to Congress Pub. L. 100–71, title I,
July 11, 1987, 101 Stat. 401, provided that: “The Secretary of the Army shall file a report with the appropriate committees of the House of Representatives and the Senate within ninety days after a written request is made pursuant to the provisions of subsection (m) of section 103 of Public Law 99–662 [33 U.S.C. 2213(m)] indicating the action taken on the request. In addition, the Secretary of the Army shall file a report with the appropriate committees of the House of Representatives and the Senate within ninety days after enactment of this Act [
July 11, 1987] listing any project or study falling under the provisions of subsection (e)(1) of section 103 of Public Law 99–662.”