2025-00438Proposed RuleWallet

EPA Mixed Bag on South Carolina Air Permit Program Changes

Published Date: 1/21/2025

Proposed Rule

Summary

The EPA is reviewing South Carolina’s updates to its minor source air pollution permit rules, approving some parts and rejecting others. This affects small businesses and industries that need permits to operate cleanly. Comments on these changes are open until February 20, 2025, so now’s the time to speak up before any new rules take effect!

Analyzed Economic Effects

6 provisions identified: 3 benefits, 3 costs, 0 mixed.

Small boilers exempt if <10 MMBtu/hr

South Carolina's rule adding an exemption for boilers and space heaters with rated input under 10 million British thermal units per hour (MMBtu/hr) that burn only virgin gas fuels is proposed to be approved into the SIP. If you operate such a unit, you would not need a construction permit under this exemption.

No case-by-case unlimited exemptions

EPA is proposing to disapprove South Carolina's revisions that would have allowed case-by-case exemptions from construction permits without an upper emissions bound, including changes that would have raised an exemption to 5 tons per year (tpy) or otherwise allowed undefined exemptions. That means South Carolina cannot use those loose case-by-case exemption provisions in the SIP.

State must keep public notice for general permits

EPA is proposing to disapprove South Carolina's new general construction permit rules because the State's provisions do not require public notice and comment as required by Federal minor NSR rules. This means the State cannot implement general construction permits that skip the public notice procedures described in 40 CFR 51.161.

Synthetic minor permit revisions rejected

EPA proposes to disapprove South Carolina's revised synthetic minor construction permit provisions (subsection II(E)) because the revisions would remove or break the public participation steps. If finalized, the State's prior SIP-approved synthetic minor permitting provisions (state-effective June 24, 2005) would continue to apply instead of the revised rules.

Emergency generator exemption widened

EPA proposes to approve South Carolina's change exempting emergency generators of up to 150 kilowatt (kW) rated capacity and exempting generators designated for emergency use that operate 500 hours or less per year for testing and maintenance (with a method to record hours). If you own qualifying emergency generators, these units may be exempt from construction permitting under the State rule.

Package concrete plants: no PE review needed

South Carolina added an exemption from professional engineering (PE) review for package-type concrete batch plants (designed to be hauled, set up, and broken down quickly) in subparagraph II(C)(2)(d), and EPA is proposing to approve that addition into the SIP. Operators of qualifying package-type plants would not need a PE review for construction permit applications.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
1/21/2025

Department and Agencies

Department
Independent Agency
Agency
Environmental Protection Agency
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register