Summary

The Federal Energy Regulatory Commission is making sure electric companies plan together for big, long-term power needs and share the costs fairly. This new rule affects transmission providers and aims to build smarter, cheaper electric grids by January 6, 2025. It’s all about teamwork to keep the lights on and save money for everyone.

Analyzed Economic Effects

5 provisions identified: 4 benefits, 0 costs, 1 mixed.

Long-Term Regional Transmission Planning

Transmission providers must participate in Long-Term Regional Transmission Planning that uses at least three plausible, diverse Long-Term Scenarios and accounts for seven specific categories of factors to identify and evaluate transmission needs and projects. The planning is intended to identify more efficient or cost-effective regional transmission facilities and to support just and reasonable Commission-jurisdictional rates.

No Mandatory Planning for Unenrolled Utilities

Transmission providers are not required to plan for the long-term transmission needs of non-jurisdictional transmission providers that have not enrolled in the transmission planning region. Voluntary arrangements to include unenrolled non-jurisdictional transmission providers are allowed only if the proposing transmission provider demonstrates the arrangement will not cause free-ridership and complies with cost causation precedent.

State-Agreed Cost Allocation Included in Filings

If Relevant State Entities agree on Long-Term Regional Transmission Cost Allocation Method(s) and/or a State Agreement Process during the six-month Engagement Period, transmission providers must include those agreed methods or processes and related state negotiation information in their Order No. 1920 compliance filing (transmittal or attachment). The Engagement Period referenced is a six-month period during which transmission providers must provide notice and a forum for negotiation.

Consult States Before Amending Cost Methods

Transmission providers must consult Relevant State Entities before amending Long-Term Regional Transmission Cost Allocation Method(s) and/or a State Agreement Process, or amend such methods/processes if Relevant State Entities seek amendment consistent with their chosen method. This consultation requirement applies after the Engagement Period.

Definition of Relevant State Entities

Relevant State Entities are defined as any state entity responsible for electric utility regulation or siting electric transmission facilities within the state or portion of a state located in the transmission planning region, including entities designated by state law for that purpose. That definition is used for participation in the Engagement Period and cost allocation discussions.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Rule Effective
Published Date
1/6/2025
4/28/2025

Department and Agencies

Department
Independent Agency
Agency
Energy Department
Federal Energy Regulatory Commission
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register