Pratt & Whitney Engines Face Mandatory Crack Checks
Published Date: 6/2/2025
Proposed Rule
Summary
The FAA wants to keep certain Pratt & Whitney engines safe by requiring regular special inspections for cracks in key parts. If cracks are found, those parts must be fixed or replaced to avoid engine problems. This affects specific engine models and could mean some downtime and repair costs, but it’s all about keeping flights safe and sound.
Analyzed Economic Effects
3 provisions identified: 1 benefits, 2 costs, 0 mixed.
Addresses engine-separation safety risk
The proposed AD is intended to address an unsafe condition after an event involving an IAE Model PW1127GA-JM engine that experienced HPC 7th-stage integrally bladed rotor (IBR-7) separation, which caused an engine shutdown and an aborted takeoff. The rule aims to reduce the risk of similar engine separations by requiring inspections and removals where needed.
Required repetitive ultrasonic inspections
If you operate the listed Pratt & Whitney engines (F117-PW-100, PW2037, PW2037D, PW2037M, PW2040, PW2040D, PW2043, PW2143, or PW2643), the FAA would require repetitive angled ultrasonic inspections (AUSIs) of certain high-pressure turbine (HPT) 1st-stage disks and turbine hubs to check for cracks. These inspections must be done repeatedly as the proposed airworthiness directive requires.
Mandatory removal and replacement for crack findings
If inspections find crack indications in the specified HPT 1st-stage disks or turbine hubs, those parts must be removed from service and replaced. The proposed AD also requires removal from service of certain HPT lenticular seal assemblies.
Your PRIA Score
Personalized for You
How does this regulation affect your finances?
Sign up for a PRIA Policy Scan to see your personalized alignment score for this federal register document and every other regulation we track. We analyze your financial profile against policy provisions to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-08943 — Designation-Restrict the Operation of Unmanned Aircraft in Close Proximity to a Fixed Site Facility
The FAA is proposing new rules to keep drones away from certain important fixed sites like power plants or airports to keep everyone safe and secure. If you own or operate one of these sites, you can request a drone flight restriction zone to protect your property and people nearby. Comments are open until July 6, 2026, and these changes could affect drone pilots and site operators, but no big costs are expected.
2026-09972 — Agency Information Collection Activities; Proposals, Submissions, and Approvals: Mitsubishi MU-2B Series Airplane Training Requirements
The FAA is renewing its paperwork rules for pilots flying the Mitsubishi MU-2B airplane to make sure they get special training and follow safety steps. This affects MU-2B pilots who must keep records proving they completed the required training. Comments on this plan are open until June 18, 2026, and the goal is to keep flying safer without adding extra hassle or costs.
2026-09953 — Agency Information Collection Activities: Requests for Comments; Clearance of Renewed Approval of Information Collection: Experimental Aircraft: Letters of Deviation Authority (LODA)
The FAA is renewing its approval to collect info from pilots who want special permission to give paid flight lessons in experimental aircraft. This helps make sure these lessons are safe. If you’re involved, you can comment by June 18, 2026, and there’s no new cost—just the usual paperwork.
2026-09971 — Notice of Draft FAA Order 5100-38E, Airport Improvement Program Handbook
The FAA is updating its Airport Improvement Program Handbook to reflect new laws and policies since 2017. This affects airports, states, and contractors who rely on federal funding for airport projects. You can review the draft and share your thoughts by August 17, 2026, so the FAA can finalize the new guide and keep airport funding running smoothly.
2026-09942 — Establishment of Class E Airspace; Geneva, OH
The FAA wants to create new Class E airspace around the University Hospitals Geneva Medical Center Heliport in Geneva, Ohio. This change will help pilots use special instrument flying rules safely when landing or taking off. If you have thoughts, you’ve got until July 2, 2026, to speak up—no costs or fees involved!
2026-09771 — Airworthiness Directives; Pilatus Aircraft Ltd. Airplanes
Pilatus PC-12 airplane owners and operators, heads up! The FAA is updating safety rules to fix a problem that could affect certain planes, meaning some extra checks or fixes might be needed. Comments on these changes are open until June 29, 2026, so get involved before then—these updates could cost some time and money but keep everyone flying safe.
Previous / Next Documents
Previous: 2025-09895 — Airworthiness Directives; Airbus Helicopters
If you fly Airbus Helicopters AS 332L2 or EC 225LP models, listen up! The FAA wants you to swap out some bolts on the main gearbox suspension bar because the old ones might be too long or bent. You'll also need to check those bolts and tell Airbus what you find—keeping your chopper safe and sound without breaking the bank.
Next: 2025-09931 — Prevailing Rate Systems; Abolishment of Hennepin, Minnesota, as a Nonappropriated Fund Federal Wage System Wage Area
The government is ending the special wage area for nonappropriated fund workers in Hennepin, Minnesota, because fewer people work there now. Most nearby counties will join other wage areas, while some won’t be part of any wage area. This change helps keep pay fair and up-to-date, with no immediate money changes announced.