PacifiCorp Joins the 'Gimme More Time' Energy Parade
Published Date: 6/2/2025
Notice
Summary
PacifiCorp asked for more time—until October 15, 2027—to meet new energy rules that were supposed to be done by July 2025. They want to make sure their systems work well, avoid problems during busy summer months, and properly train their team. This delay helps keep the energy market steady and safe without rushing costly changes.
Analyzed Economic Effects
4 provisions identified: 4 benefits, 0 costs, 0 mixed.
Requested Deadline Push to Oct 15, 2027
PacifiCorp asked the Federal Energy Regulatory Commission to move its compliance deadline for Order No. 881 from July 12, 2025 to October 15, 2027. The motion was filed on May 2, 2025 and answers must be filed by June 17, 2025.
Avoiding Untested Line Ratings During Peak Summers
PacifiCorp said it needs the extension to avoid starting new, minimally tested transmission line ratings during the 2025 and 2026 peak summer loading periods. The motion requests the compliance date be moved to October 15, 2027.
Delay to Align With CAISO Integration Timelines
PacifiCorp seeks extra time so its Order No. 881 work can align with the California Independent System Operator's proposed integration timelines for the Western Energy Imbalance Market. The requested new deadline is October 15, 2027.
More Time for Testing, Training, Documentation
PacifiCorp asked for time to test critical vendor programs on its system, properly train staff on new programs, and meet Order No. 881 documentation requirements. The requested extension date is October 15, 2027 (originally July 12, 2025).
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-16739, Venture Global CP2 LNG, LLC, Venture Global CP Express, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed CP2 LNG Expansion Project, and Notice of Public Scoping Sessions
2026-16616, Regulatory Agenda
We are publishing our regulatory agenda (the Agenda) in accordance with Public Law 96-354, "The Regulatory Flexibility Act," and Executive Order 12866, "Regulatory Planning and Review." FERC's complete Agenda, available on OMB's website at https://www.reginfo.gov, is a compilation of all rulemaking activities on which we have recently completed action or have proposed or are considering action. Our last Agenda was provided in May 2025 and in this current agenda, we have listed 42 rulemaking activities. We also note that the Agency has one inactive rulemaking that is not listed in this Agenda. This issuance of our Agenda contains ten (10) Pre-Rules, eleven (11) Notice of Proposed Rules, eight (8) Final Rules, and thirteen (13) Completed activities. Four (4) rulemakings are Section 3(f)(1) Significant; two (2) are Other Significant; one (1) is a routine rulemaking activity; two (2) are administrative, and thirty-two (32) are Substantive, Nonsignificant rulemaking activities.
2026-16637, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about rate changes and rule updates. These changes could affect pipeline rates starting as soon as July 9, 2026, and some compliance updates kick in January 1, 2027. If you want to speak up or get involved, you need to comment by late August 2026.
2026-16633, Columbia Gulf Transmission, LLC; Notice of Availability of the Environmental Assessment for the Proposed Maysville Project
2026-16525, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas pipeline companies about their rates and refunds. These filings could change how much customers pay starting as soon as September 1, 2026. If you want to speak up or get involved, you need to act by mid to late August.
2026-16418, NorthWestern Corporation; Notice of Institution of Section 206 Proceeding and Refund Effective Date
Previous / Next Documents
Previous: 2025-09922, Nevada Power Company; Notice of Motion for Extension of Time To Comply
Nevada Power Company asked for more time—until October 15, 2027—to meet new rules about managing power lines safely and efficiently. They want to avoid problems during busy summer months by testing their systems thoroughly and training their staff properly. This delay helps keep the power grid reliable and aligns with California’s market plans, with no immediate cost changes announced.
Next: 2025-09924, City of Ketchikan, Alaska; Notice of Intent To File License Application, Filing of Pre-Application Document (Pad), Commencement of ILP Pre-Filing Process and Scoping, Request for Comments on the Pad and Scoping Document, and Identification of Issues and Associated Study Requests
The City of Ketchikan, Alaska, is starting the process to renew the license for its Ketchikan Lakes Hydroelectric Project. This means they’re gathering ideas, asking for public comments, and planning studies to make sure the project runs smoothly and safely for the environment and community. If you live nearby or care about local energy and nature, now’s the time to get involved before the official application is filed later this year.