Pipeline Giant Seeks Permission to Bend Federal Safety Rules
Published Date: 6/26/2025
Notice
Summary
Tennessee Gas Pipeline Company, part of Kinder Morgan, wants a special permit to skip some pipeline safety rules for a bit. The government is asking everyone to share their thoughts by July 28, 2025, before deciding. This could affect pipeline safety rules and how the company operates, but no direct costs or deadlines beyond the comment period are set yet.
Analyzed Economic Effects
2 provisions identified: 1 benefits, 0 costs, 1 mixed.
TGP Seeks 327‑Foot Special Permit Extension
Tennessee Gas Pipeline Company (TGP) asked PHMSA to extend an existing special permit by 327 feet (about 0.062 miles) for a 30‑inch pipeline segment in Robertson County, Tennessee. The extension would increase the active permit coverage from 42,298 feet to 42,625 feet (about 8.073 miles) under special permit PHMSA-2022-0035, which is effective until July 24, 2033, and would allow relief from certain Federal pipeline safety regulations in 49 CFR 192.611(a), (d), and 192.619(a).
PHMSA Found No Significant Environmental Impact
PHMSA reviewed the Final Environmental Assessment (FEA) and determined that adding the requested segment to the special permit would not result in significant impacts to the human environment, and that the existing FEA and Finding of No Significant Impact remain adequate under the National Environmental Policy Act. PHMSA states no further environmental assessment is required and will consider public comments submitted by July 28, 2025 before deciding on the request.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22396, Pipeline Safety: Amendments to Liquefied Natural Gas Facilities
The government wants to update safety rules for liquefied natural gas (LNG) facilities to match the latest industry standards and new technology. These changes affect LNG operators and aim to make facilities safer by using smarter, risk-based approaches. Comments on the proposal are open until January 4, 2027, with no immediate cost changes announced.
2026-13805, Pipeline Safety: Repair Criteria for Hazardous Liquid and Gas Transmission Pipelines
The government wants to update pipeline safety rules to make fixing gas and liquid pipelines smarter, safer, and cheaper. These changes affect pipeline operators who’ll use new tech and clearer guidelines to spot and repair problems faster. Comments are open until September 8, 2026, so get ready to weigh in before the rules get final—and yes, this could save money and prevent accidents!
2026-10969, Pipeline Safety: Breakout Tank Inspection Rule
The Pipeline Safety folks want to update rules for breakout tanks—those tanks that help manage and store hazardous liquids in pipelines. They’re switching to a newer, smarter inspection method that checks tanks based on risk, not just a set schedule. This affects pipeline operators, who should get ready to follow these updated inspections and can share their thoughts by August 3, 2026.
2026-10782, Pipeline Safety: Class Location Change Requirements; Correction
PHMSA fixed a small but important detail in a new pipeline safety rule from January 2026. Pipeline operators can now confirm or restore safe pressure levels when neighborhoods change around their pipes, with a clear 24-month deadline starting either from the rule’s effective date or when they begin work. This helps keep gas pipelines safe without confusion about timing, so operators know exactly when to act and avoid costly delays.
2026-08144, Administrative Rulemaking, Guidance, and Enforcement Procedures
The Department of Transportation is bringing back and improving its rules for making new policies, giving guidance, and enforcing laws. This affects anyone involved in transportation regulations, making the process clearer and more consistent. These changes kick in on May 27, 2026, aiming to save time and avoid confusion without adding extra costs.
2026-08058, Pipeline Safety: Safety of Gas Transmission Pipelines: MAOP Reconfirmation, Expansion of Assessment Requirements, and Other Related Amendments; Correction
This update fixes a numbering mistake in the rules for checking the maximum safe pressure of gas pipelines. Pipeline operators must follow the corrected list to avoid confusion, but no new costs or deadlines are added. The fix takes effect on August 3, 2026, making safety rules clearer and easier to follow.
Previous / Next Documents
Previous: 2025-11787, Pipeline Safety: Request for Special Permit
Columbia Gas Transmission System wants a special permit to skip some pipeline safety rules for a bit. PHMSA is asking the public to share their thoughts by July 28, 2025, before deciding. This affects pipeline safety rules and could save time or money for the company while keeping safety in check.
Next: 2025-11789, Pipeline Safety: Request for Special Permit
Tennessee Gas Pipeline Company, part of Kinder Morgan, is asking for a special permit to skip some pipeline safety rules for a bit longer. The government wants your thoughts on this by July 28, 2025, before deciding. This affects pipeline safety rules but won’t cost the public extra money right now.