2025-12154RuleWallet

Transit Project Guidance Moves Out of an Outdated Appendix

Published Date: 7/1/2025

Rule

Summary

Starting July 1, 2025, the Federal Transit Administration is updating how it handles big transit project rules by removing an old appendix that had outdated info. Now, the latest project evaluation details will live only in the regularly updated policy guide, making things clearer and more current for transit planners and local governments seeking funding. This change helps speed up updates without confusing everyone with old rules.

Analyzed Economic Effects

7 provisions identified: 4 benefits, 1 costs, 2 mixed.

New Starts / Small Starts financial thresholds

A New Starts project is defined as a project with total capital cost of $250,000,000 or more or for which the sponsor requests $75,000,000 or more in New Starts funds. A Small Starts project has total capital cost under $250,000,000 and requests less than $75,000,000.

Rating thresholds to get construction grants

To be eligible for construction grants under 49 U.S.C. 5309, New Starts and Small Starts projects must receive a "medium" or better rating on project justification and a "medium" or better rating on local financial commitment before construction grant approval.

CIG Policy Guidance updated regularly

FTA will publish the detailed project evaluation measures in the CIG Policy Guidance, which must be updated at least once every two years and was last updated in December 2024. When the guidance imposes a "binding obligation," FTA follows notice-and-comment procedures so interested parties can comment.

Before-and-After study required for New Starts

During engineering, New Starts project sponsors must submit a plan to collect and analyze "before" and "after" data, including capital costs, operating costs, ridership, and service characteristics. A final report must be prepared within three years of project opening, and satisfactory progress on the plan is a prerequisite to approval of an FFGA.

Appendix A removed; guidance is definitive

Starting July 1, 2025, Appendix A is removed from 49 CFR part 611. You must rely on the Capital Investment Grant (CIG) Policy Guidance — not the old Appendix — for the detailed measures used to evaluate CIG projects.

No change to evaluation outcomes

FTA says removing Appendix A will have no substantive effect on how CIG projects are evaluated or rated. The change is intended to conform the regulation to current practice and avoid confusion from obsolete text.

Existing projects stay under old rules

Projects with an executed Full Funding Grant Agreement (FFGA) or Pre-Construction Grant Agreement (PCGA), or projects approved into final design or project development, continue under the prior regulations unless the project sponsor asks to be covered by the revised part 611.

Personalized for You

How does this regulation affect your finances?

Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.

Key Dates

Published Date
Rule Effective
7/1/2025
7/1/2025

Department and Agencies

Department
Independent Agency
Agency
Transportation Department
Federal Transit Administration
Source: View HTML

Related Federal Register Documents

Previous / Next Documents

Back to Federal Register