Transit Project Guidance Moves Out of an Outdated Appendix
Published Date: 7/1/2025
Rule
Summary
Starting July 1, 2025, the Federal Transit Administration is updating how it handles big transit project rules by removing an old appendix that had outdated info. Now, the latest project evaluation details will live only in the regularly updated policy guide, making things clearer and more current for transit planners and local governments seeking funding. This change helps speed up updates without confusing everyone with old rules.
Analyzed Economic Effects
7 provisions identified: 4 benefits, 1 costs, 2 mixed.
New Starts / Small Starts financial thresholds
A New Starts project is defined as a project with total capital cost of $250,000,000 or more or for which the sponsor requests $75,000,000 or more in New Starts funds. A Small Starts project has total capital cost under $250,000,000 and requests less than $75,000,000.
Rating thresholds to get construction grants
To be eligible for construction grants under 49 U.S.C. 5309, New Starts and Small Starts projects must receive a "medium" or better rating on project justification and a "medium" or better rating on local financial commitment before construction grant approval.
CIG Policy Guidance updated regularly
FTA will publish the detailed project evaluation measures in the CIG Policy Guidance, which must be updated at least once every two years and was last updated in December 2024. When the guidance imposes a "binding obligation," FTA follows notice-and-comment procedures so interested parties can comment.
Before-and-After study required for New Starts
During engineering, New Starts project sponsors must submit a plan to collect and analyze "before" and "after" data, including capital costs, operating costs, ridership, and service characteristics. A final report must be prepared within three years of project opening, and satisfactory progress on the plan is a prerequisite to approval of an FFGA.
Appendix A removed; guidance is definitive
Starting July 1, 2025, Appendix A is removed from 49 CFR part 611. You must rely on the Capital Investment Grant (CIG) Policy Guidance — not the old Appendix — for the detailed measures used to evaluate CIG projects.
No change to evaluation outcomes
FTA says removing Appendix A will have no substantive effect on how CIG projects are evaluated or rated. The change is intended to conform the regulation to current practice and avoid confusion from obsolete text.
Existing projects stay under old rules
Projects with an executed Full Funding Grant Agreement (FFGA) or Pre-Construction Grant Agreement (PCGA), or projects approved into final design or project development, continue under the prior regulations unless the project sponsor asks to be covered by the revised part 611.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-17904, National Environmental Policy Act Regulations
FHWA, FRA, and FTA (collectively referred to as the "Agencies") are finalizing the interim final rule (IFR) published on July 3, 2025, which revised the Agencies' National Environmental Policy Act (NEPA) of 1969 implementing regulations in light of the removal of the Council on Environmental Quality (CEQ) regulations, the amendments to NEPA included in the section of the Fiscal Responsibility Act (FR Act) of 2023, known as the Building United States Infrastructure through Limited Delays and Efficient Reviews (BUILDER) Act of 2023, amendments regarding efficient environmental reviews included in the Infrastructure Investment and Jobs Act (IIJA) of 2021, and the Supreme Court decision in Seven County Infrastructure Coalition. The Agencies provided a 30-day comment period for the public to review and comment on the IFR. This final rule addresses public comments received and finalizes the IFR with minor technical changes.
2026-08144, Administrative Rulemaking, Guidance, and Enforcement Procedures
The Department of Transportation is bringing back and improving its rules for making new policies, giving guidance, and enforcing laws. This affects anyone involved in transportation regulations, making the process clearer and more consistent. These changes kick in on May 27, 2026, aiming to save time and avoid confusion without adding extra costs.
2026-22168, Safety Advisory 26-01 Overhead Catenary System (OCS) and Pantograph Reliability
The Federal Transit Administration wants rail agencies to use their safety systems to spot and fix problems with overhead wires and pantographs that power trains. State safety groups must collect and share reports on these fixes within 180 days. This helps keep trains running safely and avoids costly accidents.
2026-21945, Transfer of Federally Assisted Property
NJ TRANSIT plans to transfer a 2.17-acre piece of land it no longer uses to Jersey City’s Utilities Authority for a new stormwater pump station to help fight flooding. Federal agencies have until November 27, 2026, to claim interest in the property before the transfer moves forward. This change helps turn unused land into a community asset without extra cost to the government.
2026-20514, Agency Information Collection Activity Under OMB Review: 49 U.S.C. 5307 Urbanized Area Formula Program
The Federal Transit Administration wants to keep collecting info for the Urbanized Area Formula Program without changing anything. This affects cities that get federal transit money and helps keep the funding process smooth. If you have thoughts, send them by December 7, 2026, so your voice counts!
2026-20515, Agency Information Collection Activity Under OMB Review: 49 U.S.C. 5317 New Freedom Program
The Federal Transit Administration wants to keep collecting info for the New Freedom Program, which helps people with disabilities get better transportation options. They’re asking for your thoughts by December 7, 2026, but no big changes or new costs are planned. This keeps the program running smoothly and making travel easier for those who need it most.
Previous / Next Documents
Previous: 2025-12153, Administrative Updates to the Railroad Safety Appliance Standards Regulations
Starting July 1, 2025, the Federal Railroad Administration is updating its railroad safety rules by fixing outdated addresses, changing how penalty amounts are referenced, and requiring email submissions for special approval petitions. These changes mainly affect railroad companies and safety officials, making processes smoother and more modern without adding new costs. It’s a smart cleanup that keeps safety standards clear and easy to follow!
Next: 2025-12155, Repealing a Redundant Reporting Requirement
The Federal Railroad Administration is scrapping a duplicate rule that made railroads file the same positive train control (PTC) report twice—once every six months and again every three months. Starting July 31, 2025, railroads only need to submit the report quarterly, saving time and hassle without extra costs. This change affects all railroads using PTC systems and keeps safety reporting sharp and simple.