FAA Proposes Sealant Checks for Boeing 787 Dreamliners
Published Date: 2/24/2026
Proposed Rule
Summary
The FAA wants Boeing 787-8, 787-9, and 787-10 airplanes checked because some sealant in their wing fuel tanks might not have been inspected properly during production. They’re proposing detailed inspections and tests to make sure everything sticks tight and safe. If you own or operate these planes, get ready for these checks soon—comments on the plan are open until April 10, 2026, and fixing issues could cost some time and money.
Analyzed Economic Effects
5 provisions identified: 2 benefits, 3 costs, 0 mixed.
Mandatory 787 sealant inspections
If you own or operate Boeing Model 787-8, 787-9, or 787-10 airplanes, the FAA would require a detailed inspection of certain sealant installations in the left, right, and center wing side-of-body areas and an adhesion test of that sealant, and you must perform any on-condition repairs per Boeing Alert Requirements Bulletin B787-81205-SB570053-00 RB, Issue 001, dated November 5, 2025.
Estimated inspection cost per aircraft
The FAA estimates the inspection and adhesion test will take 34 work-hours at $85 per hour (labor cost $2,890) with $0 parts cost, so cost per airplane is $2,890 and the FAA estimates the AD would affect 60 U.S.-registered airplanes for a total estimated cost to U.S. operators of $173,400.
Safety goal: prevent fuel tank ignition
The FAA says the inspections are needed because missing visual and adhesion inspections during production could leave sealant defects that might create an ignition source inside the center wing fuel tank and increase the risk of a fuel tank explosion during a lightning strike; the AD is intended to address that unsafe condition.
On-condition repair costs uncertain
The FAA states it has received no definitive data to estimate costs for any on-condition repairs that may be required after the inspection, so affected operators may incur additional repair expenses beyond the $2,890 inspection estimate.
Possible warranty coverage reduces operator cost
Boeing states some or all costs of the proposed AD may be covered under warranty, which could reduce the out-of-pocket cost for affected operators.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-13440, Enabling Supersonic Overland Flight
The FAA wants to let supersonic planes fly over land again by updating old rules that banned them because of loud sonic booms. Thanks to new tech that keeps booms quiet, this change will open the door for faster, cooler flights across the U.S., helping America lead the world in supersonic travel. People and companies interested in supersonic flight should share their thoughts by August 17, 2026.
2026-13126, Designation-Restrict the Operation of Unmanned Aircraft in Close Proximity to a Fixed Site Facility; Extension of Comment Period
The FAA is giving more time—until August 5, 2026—for people to share their thoughts on new rules that would limit drone flights near important fixed sites like power plants or airports. This affects drone operators and facility owners who want to keep the skies safe and secure. No new costs yet, just extra time to weigh in and help shape the rules.
2026-08943, Designation-Restrict the Operation of Unmanned Aircraft in Close Proximity to a Fixed Site Facility
The FAA is proposing new rules to keep drones away from certain important fixed sites like power plants or airports to keep everyone safe and secure. If you own or operate one of these sites, you can request a drone flight restriction zone to protect your property and people nearby. Comments are open until July 6, 2026, and these changes could affect drone pilots and site operators, but no big costs are expected.
2026-14881, Airworthiness Directives; Bell Textron Canada Limited Helicopters
This update affects owners and operators of Bell Textron Canada helicopters. It requires important safety checks and fixes to keep these helicopters flying safely. The changes must be done within set deadlines and might cost some money, but they help prevent serious problems in the air.
2026-14882, Airworthiness Directives; Rolls-Royce Deutschland Ltd & Co KG Engines
If you own certain Rolls-Royce Trent 1000 engines, the FAA wants you to keep checking a part called the high-pressure turbine triple seal for wear and replace it if needed. They’re updating the rules to remove some engines from this check because a new fix now makes inspections unnecessary for those. Comments on this change are open until September 8, 2026, so get ready to act and keep your engines safe without breaking the bank!
2026-14886, Airworthiness Directives; Airbus Helicopters
If you own or operate an Airbus EC130B4 helicopter, heads up! The FAA wants to fix weak door locks by requiring changes to the swinging and sliding door supports. You’ll need to update your helicopter soon to keep flying safely, and no new affected doors can be installed unless they meet the new rules. Comments on this plan are open until September 8, 2026, so don’t miss your chance to weigh in!
Previous / Next Documents
Previous: 2026-03610, Managing Senior Professional Performance
The government is updating how it reviews the work of senior professionals like top scientists and leaders. These changes will make performance reviews clearer, more fair, and more like those for senior executives. If you’re a senior pro, get ready for new rules starting soon, and don’t forget to share your thoughts by March 26, 2026!
Next: 2026-03619, Performance Appraisal for General Schedule, Prevailing Rate, and Certain Other Employees
The Office of Personnel Management is updating how performance reviews work for most federal workers, like General Schedule and prevailing rate employees. They’re simplifying rating levels, requiring agencies to check their appraisal systems every two years, and changing rules about rating disputes and reviews. These changes aim to make performance management smoother and start after public comments close on March 26, 2026.