Gas Pipeline Wants Pennsylvania's Eco Worries on Expansion Project
Published Date: 10/6/2026
Notice
Summary
Transcontinental Gas Pipe Line Company wants to expand its gas pipeline in Luzerne, Pennsylvania, and the government is asking the public to share their thoughts on how this might affect the environment. People have until November 2, 2026, to send in comments about possible impacts and better ways to do the project. This feedback will help decide if the project moves forward and how it’s done safely and responsibly.
Analyzed Economic Effects
3 provisions identified: 1 benefits, 2 costs, 0 mixed.
Easement offers and eminent domain risk
If you own land in the project area, Transcontinental may contact you to negotiate an easement to construct, operate, and maintain the pipeline. You are not required to agree, but if FERC approves the project the Natural Gas Act gives the company the right to seek condemnation in court; any compensation would be determined by a judge under state law.
Construction will disturb 95 acres; 20 acres permanent
Construction of the Leidy Access Expansion would disturb about 95 acres of land, and after construction Transco would maintain about 20 acres for permanent operation (including about 0.3 acres for access roads); the rest would be restored and revert to former uses.
FERC will do NEPA review; comments due November 2, 2026
FERC will prepare an environmental document (an Environmental Assessment or an Environmental Impact Statement) that will analyze effects on geology and soils; water resources and wetlands; vegetation and wildlife; threatened and endangered species; cultural resources; land use; air quality and noise; and reliability and safety. The Commission requests public comments on the scope of issues and will accept written comments in Washington, DC on or before 5:00 p.m. Eastern Time on November 2, 2026.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-22946, International Falls Power Company; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed International Falls Hydroelectric Project
International Falls Power Company wants to renew its license to run a hydroelectric project on the Rainy River in Minnesota. The government is asking the public to share their thoughts on how this project might affect the environment before deciding. If you care about clean energy or local nature, now’s the time to speak up—your input could shape the future of this power plant!
2026-22949, GB Energy Park, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
GB Energy Park, LLC is asking for more time to start and finish building their Gordon Butte Pumped Storage Project in Montana. This affects local communities and energy users waiting for this new hydroelectric power source. The public can share their thoughts or objections by December 7, 2026, so don’t miss your chance to weigh in!
2026-22878, ConocoPhillips Company; Notice of Institution of Section 206 Proceeding and Refund Effective Date
The Federal Energy Regulatory Commission is investigating whether ConocoPhillips’ electricity rates are fair or not. If found unfair, refunds could be required starting from November 10, 2026. Anyone interested has 21 days to join the case and share their views.
2026-22877, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from natural gas companies about rate changes and reports. These updates could affect customers and businesses by changing pipeline rates or how penalties are handled, with some changes starting as soon as October 2026. If you want to speak up or get involved, you need to comment by specific deadlines in November or January.
2026-22879, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies like ATCO, Emera, and Google Energy. These filings include requests for approvals, complaints, and updates on company statuses. If you’re involved or interested, note the comment deadlines in November—they could affect how energy businesses operate and possibly impact prices or services.
2026-22803, Northern Illinois Hydropower, LLC; Notice of Request for Extension of Time To Commence and Complete Construction Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests
Northern Illinois Hydropower, LLC asked for more time to start and finish building their Brandon Road Hydroelectric Project in Illinois. The project sits on federal land near Rockdale and needs approval from the Federal Energy Regulatory Commission (FERC). People have until December 4, 2026, to share their thoughts or objections, so this extension could affect the project’s timeline and future energy plans.
Previous / Next Documents
Previous: 2026-20449, Submission for OMB Review; Comment Request
The Department of Agriculture wants your feedback on a form they use to help farmers with emergency conservation and biomass crop programs. They’re checking if the form is useful, clear, and not too much work to fill out. If you have thoughts, send them by November 5, 2026, so they can keep things running smoothly without wasting anyone’s time or money.
Next: 2026-20451, Alaska Energy Authority Notice Soliciting Recommendations, Terms and Conditions, and Fishway Prescriptions for Application for Non-Capacity Amendment of License
The Alaska Energy Authority is updating the license for its Bradley Lake hydro project in Alaska and wants your ideas on rules and fish protections by November 30, 2026. This affects local communities, fish habitats, and anyone interested in clean energy. Get your comments in on time to help shape the project without changing its power output.