Summary
Erie Boulevard Hydropower asked New York DEC for permission to make sure their project keeps water clean. New York DEC has one year, until October 2, 2027, to decide. If they don’t respond by then, their approval is automatically given, so the project can move forward without delay.
Analyzed Economic Effects
1 provisions identified: 1 benefits, 0 costs, 0 mixed.
One-year deadline for state water certification
Erie Boulevard Hydropower submitted a Clean Water Act section 401 water quality certification request received October 2, 2026. New York DEC has one year, until October 2, 2027, to act; if New York DEC does not act by that date, the certification is deemed waived under section 401(a)(1), allowing the project to move forward without delay.
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-21365, Erie Boulevard Hydropower, L.P.; Notice of Reasonable Period of Time for Water Quality Certification Application
Erie Boulevard Hydropower asked New York DEC for permission to make sure their project keeps water clean. New York DEC has one year, until October 2, 2027, to decide. If they don’t respond by then, their approval is automatically given, helping the project move forward without delays or extra costs.
2026-21283, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings from several natural gas pipeline companies about their rates and refunds. These changes mostly affect pipeline customers and could change prices starting November 1, 2026, or January 1, 2027. If you want to comment, you’ve got until October 26, 2026, so don’t miss out!
2026-21284, Erie Boulevard Hydropower, L.P.; Notice of Reasonable Period of Time for Water Quality Certification Application
Erie Boulevard Hydropower asked New York DEC for a water quality check on October 2, 2026. New York DEC has one year, until October 2, 2027, to approve or deny it. If they don’t decide by then, their approval is automatically given, which could speed up the project without extra costs or delays.
2026-21191, Gulf South Pipeline Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Texas Gateway Project
Gulf South Pipeline Company wants to build the Texas Gateway Project, a new pipeline in parts of Texas and Louisiana. The government is checking how this might affect the environment and wants your thoughts by November 12, 2026. This project could change local areas and impact communities, so your voice matters before any big money or construction moves forward!
2026-21074, Commission Information Collection Activities (FERC-725A, 725L, and 725Z); Comment Request; Revision
FERC is updating how certain energy companies report important data to keep the power grid reliable. These changes affect operators who manage electricity flow and require them to provide updated info by November 16, 2026. No big cost changes are expected, but your feedback is welcome to help shape the final rules!
2026-21070, Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
Columbia Gas Transmission wants to safely shut down an old gas well and pipeline in Ohio to reduce risks without affecting service. The project costs about $900,000 and won’t impact customers or storage operations. If you want to speak up or get involved, you have until December 8, 2026, to file your comments or protests.
Previous / Next Documents
Previous: 2026-21362, Certain Steel Nails From Taiwan: Final Results of Antidumping Duty Administrative Review; 2024-2025
The U.S. Department of Commerce found that certain steel nails from Taiwan were sold in the U.S. at unfairly low prices from July 2024 to June 2025. This means importers might have to pay extra duties to level the playing field. These final results take effect on October 19, 2026, impacting businesses dealing with these nails and protecting U.S. manufacturers.
Next: 2026-21364, Moraga Storage, LLC, River Mill Storage, LLC, Hecate Energy Medway Energy Center LLC, Brough Storage, LLC, Partridge Storage, LLC v. ISO New England Inc.; Notice on Comment Periods
Five energy storage companies want a faster review to decide if they’ll sign or drop a big power connection deal with ISO New England. They asked for a quick 10-day comment period, but ISO New England wants the full 30 days. The government gave a mix: 10 days to comment on the waiver and 25 days for ISO New England to respond, with key deadlines in mid and late October 2026.