Bath County Pumped-Storage Review Slips From November to February
Published Date: 10/27/2026
Notice
Summary
Dominion Energy and partners are updating the timeline for their environmental review of the Bath County Pumped Storage Project in Virginia. Instead of November 2026, the Environmental Assessment will now come out by February 2027. This delay affects local communities and stakeholders but ensures a thorough review before any final decisions.
No Economic Impacts Identified for this Document
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-21875, Combined Notice of Filings
The Federal Energy Regulatory Commission got new filings about natural gas pipeline rates and refunds that could affect pipeline companies and their customers. Some rate changes and contract updates are set to start soon, with chances to comment or protest by specific deadlines. These updates might impact how much people pay or get refunded for natural gas services.
2026-21877, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got several new filings from energy companies about big projects and changes in how they operate. These include wind farms, solar storage, and tariff updates that could affect energy prices and services soon. If you’re involved in energy or just curious, keep an eye on deadlines for comments by late October and November 2026!
2026-21870, Florida Gas Transmission Company, LLC; Notice of Scoping Period Requesting Comments on Environmental Issues for the Proposed Phase IX Project
Florida Gas Transmission Company wants to build new gas facilities in Mississippi, Alabama, and Florida as part of their Phase IX Project. The government is asking people to share their thoughts on how this might affect the environment before November 23, 2026. This feedback will help decide if the project moves forward and how to protect nature while doing it.
2026-21770, Combined Notice of Filings #1
The Federal Energy Regulatory Commission got a bunch of filings from energy companies about changes to rates, programs, and project statuses. These updates affect energy providers and customers, with some changes kicking in as soon as October 17, 2026, and others starting in early 2027. If you’re involved in energy or just curious, keep an eye on deadlines for comments and new rules that could impact costs and services.
2026-21721, Sandy Hollow Power Company, Inc.; Notice of Application for Surrender of License Accepted for Filing and Soliciting Comments, Motions To Intervene, and Protests
Sandy Hollow Power Company wants to give up its license to run the Sandy Hollow Hydroelectric Project on the Indian River in New York. This means the project might stop operating, affecting local energy and the environment. People have until November 20, 2026, to share their thoughts or ask to get involved before the decision moves forward.
2026-21490, Combined Notice of Filings
The Federal Energy Regulatory Commission got several filings from natural gas pipeline companies about rate changes and refunds. These updates could affect pipeline customers starting as soon as November 1, 2026, with some changes kicking in by January 1, 2027. If you want to speak up or get involved, you need to act before the late October deadlines.
Previous / Next Documents
Previous: 2026-21867, Fall River Electric Cooperative, Inc.; Notice of Revised Schedule for Environmental Assessment
Fall River Electric Cooperative’s hydroelectric project in Idaho is getting an updated timeline for its environmental review. Instead of October 30, 2026, the Environmental Assessment will now come out by December 15, 2026, giving everyone more time to weigh in. This change affects local communities, environmental groups, and the project’s future, but no extra costs or delays beyond this new date are expected.
Next: 2026-21869, Erie Boulevard Hydropower, L.P.; Notice of Intent To Prepare an Environmental Assessment
Erie Boulevard Hydropower wants to renew its license for the Beaver River Hydroelectric Project in New York. The government will prepare an environmental assessment to make sure the project won’t harm the environment. The assessment will be ready by October 22, 2027, and the public can share their thoughts during a 30-day comment period.