FAA Orders Regular Checks for Cracks in Jet Engine Fan Blades
Published Date: 11/24/2026
Rule
Summary
If you operate CFM56-7B engines, listen up! The FAA updated the rules for checking fan blades for cracks using better inspection methods. Starting December 29, 2026, you’ll need to do these inspections regularly and replace any cracked parts to keep flying safe—no surprise costs, just smart maintenance.
Analyzed Economic Effects
6 provisions identified: 2 benefits, 4 costs, 0 mixed.
Mandatory fan-blade inspections every 1,600 flights
If you operate CFM56-7B engines, you must perform either an ultrasonic or an eddy-current inspection of the concave and convex sides of the fan blade dovetail on a schedule. Do an initial inspection before the blade reaches 17,000 cycles since new (CSN) or within 1,600 flight cycles (FCs) since the last inspection before December 29, 2026, whichever is later, and then repeat the inspection every 1,600 FCs.
Replace cracked blades before next flight
If any inspection finds an unserviceable indication on a fan blade, you must replace that fan blade before further flight. The AD requires replacement with a part eligible for installation and expressly prohibits installing non-eligible fan blades after December 29, 2026.
Installation limits for fan blades (17,000-cycle rule)
After December 29, 2026, you may not install a fan blade on any engine unless it is a part eligible for installation. A part eligible for installation is either a fan blade with fewer than 17,000 cycles since new (CSN) or a fan blade that passed the required inspection within the last 1,600 flight cycles before installation.
Estimated per-inspection and replacement costs
The FAA estimates the inspection labor is 2 work-hours at $85/hour and lists parts cost $340; the AD shows a U.S. operators cost figure of $1,548,020 for the affected fleet. The FAA estimates on-condition replacement (replace fan blade pair) labor at 1 work-hour ($85) and parts cost $208,300, for a total of $208,385 per replacement event.
No mandatory reporting or return-to-manufacturer
Although the referenced service bulletin or shop manual may ask you to report inspection results or send parts to the manufacturer, this AD does not require reporting inspection results and does not require sending parts to the manufacturer. Those service-bulletin-specified reporting/return actions are not mandated by the AD.
Credit allowed for earlier inspections using listed revisions
You may take credit for the required inspections if they were performed before December 29, 2026 using specified CFM service bulletins or the listed engine-shop-manual instructions. The AD lists specific documents eligible for credit, including CFM SB 72-1019 (March 24, 2017) and multiple revisions of CFM SB 72-1033 up through Revision 05 (July 28, 2026), and Subtask 72-21-01-220-091 from Engine Shop Manual Revision 67 (July 15, 2026).
Personalized for You
How does this regulation affect your finances?
Personalize government policy and PRIA will tell you what this federal register document means for your household, plus every other regulation we track. PRIA reads each provision against your financial profile to show you exactly what matters to your wallet.
Key Dates
Department and Agencies
Related Federal Register Documents
2026-15585, Requirements for Interference-Tolerant Radio Altimeter Systems
In July 2025, President Trump signed the One Big Beautiful Bill Act. Section 40002 of that law re-institutes the Federal Communications Commission's general auction authority and specifically directs the Commission to complete a system of competitive bidding for not less than 100 megahertz in the 3.98-4.2 gigahertz band (Upper C- band). This final rule supports the Federal Communications Commission's July 2026 Report and Order that makes 160 megahertz of the Upper C-band available for terrestrial wireless flexible use via a system of competitive bidding. To ensure safe, efficient, and reliable aviation operations in the presence of wireless signals in the C-band, the Federal Aviation Administration is issuing new regulations that require all radio altimeters to meet specific minimum performance requirements. These new radio altimeters must withstand interference from wireless signals in neighboring spectrum bands and continue to provide accurate altitude readings to both pilots and integrated aircraft safety systems. These regulations require all aircraft equipped with radio altimeters operating under part 121 and those aircraft with radio altimeters operating under part 129 with 30 or more passenger seats or a payload capacity of more than 7,500 pounds to comply with the minimum performance requirements by December 30, 2030, which is prior to the date the Federal Communications Commission authorizes the use of the Upper C-band for new wireless services, as stated in its Report and Order. All other aircraft equipped with radio altimeters that are required to comply with part 91, including aircraft operating under parts 125, 133, 135, 136, 137, 194, and all other aircraft operating under part 129 that are not subject to the initial deadline, must comply with the same minimum performance requirements on or before October 31, 2034.
2026-13440, Enabling Supersonic Overland Flight
The FAA wants to let supersonic planes fly over land again by updating old rules that banned them because of loud sonic booms. Thanks to new tech that keeps booms quiet, this change will open the door for faster, cooler flights across the U.S., helping America lead the world in supersonic travel. People and companies interested in supersonic flight should share their thoughts by August 17, 2026.
2026-13126, Designation-Restrict the Operation of Unmanned Aircraft in Close Proximity to a Fixed Site Facility; Extension of Comment Period
The FAA is giving more time—until August 5, 2026—for people to share their thoughts on new rules that would limit drone flights near important fixed sites like power plants or airports. This affects drone operators and facility owners who want to keep the skies safe and secure. No new costs yet, just extra time to weigh in and help shape the rules.
2026-08943, Designation-Restrict the Operation of Unmanned Aircraft in Close Proximity to a Fixed Site Facility
The FAA is proposing new rules to keep drones away from certain important fixed sites like power plants or airports to keep everyone safe and secure. If you own or operate one of these sites, you can request a drone flight restriction zone to protect your property and people nearby. Comments are open until July 6, 2026, and these changes could affect drone pilots and site operators, but no big costs are expected.
2025-14992, Normalizing Unmanned Aircraft Systems Beyond Visual Line of Sight Operations
The FAA and TSA want to make flying drones beyond what you can see easier and safer for everyone. This new rule will help businesses and hobbyists use drones for things like deliveries, farming, and surveys without needing to keep the drone in sight all the time. If you’re involved in drone flying or services, get ready for new rules by October 6, 2025, that could open up cool new drone opportunities while keeping skies secure.
2025-04846, Extension of the Prohibition Against Certain Flights in the Territory and Airspace of Libya
The FAA is extending the ban on certain flights over Libya for three more years, until March 20, 2028. This affects U.S. airlines, commercial operators, and pilots with FAA certificates flying in Libyan airspace, due to ongoing safety risks. The rule also reminds everyone how to apply for special approvals or exemptions if needed.
Previous / Next Documents
Previous: 2026-23851, Notification of Inflation Adjustments for Civil Money Penalties
Starting January 10, 2025, the Office of the Comptroller of the Currency is raising the maximum fines it can charge to keep up with inflation. This means anyone facing civil money penalties from the OCC for actions after November 2, 2015, might see higher fines. These updates help keep penalties fair and effective as prices change over time.
Next: 2026-23866, Personnel Appeals Board; Procedural Rules
The Government Accountability Office’s Personnel Appeals Board is updating its rules to make filing cases easier and faster by going digital and adding a new petition form. These changes affect anyone bringing a case to the Board and start on December 24, 2026. The updates also give judges more control over case steps and help people who represent themselves, with no extra costs involved.