25,665 sections across 776 Alaska regulatory chapters.
18 AAC 75-420 Procedures to apply for oil discharge prevention and contingency plans; plan renewals
1.2K chars
(a) A plan holder must apply for renewal of the department's approval of an oil discharge prevention and contingency plan in accordance with 18 AAC 75.408. For submittals after October 16, 2016, the application must be submitted at least 180 days, or the number of days stated in …
18 AAC 75-421 Procedures to apply for streamlined oil discharge prevention and contingency plans
2.0K chars
(a) An application for approval of a new streamlined oil discharge prevention and contingency plan must be made on an application form supplied by the department. (b) An application for approval of an amendment to a streamlined plan must be submitted using an application form sup…
18 AAC 75-425 Oil discharge prevention and contingency plan contents (Repealed)
0.6K chars
Notes 18 AAC 75.425 Eff. 5/14/92, Register 122; am 9/25/93, Register 127; am 3/28/96, Register 137; am 4/4/97, Register 142; am 12/14/2002, Register 164; am 5/26/2004, Register 170; am 12/30/2006, Register 180; am 9/4/2014, Register 211, October 2014; am 3/23/2017, Register 221, …
18 AAC 75-426 Streamlined plan contents
6.9K chars
A streamlined plan application must contain the following information: (1) the name, address, and telephone number of the plan holder; (2) for each covered vessel, the (A) vessel's name, official number, and country of registry; (B) name and address of the owner; and (C) name and…
18 AAC 75-427 [Repealed]
0.4K chars
Notes 18 AAC 75.427 Eff. 11/27/2002, Register 164; repealed 3/23/2017, Register 221, April 2017 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More compariso…
18 AAC 75-428 Response planning facilitator
2.5K chars
(a) A response planning facilitator registered under 18 AAC 75.500 - 18 AAC 75.580 may submit a streamlined plan under 18 AAC 75.421 on behalf of a plan holder. A response planning facilitator may (1) act as an intermediary between the plan holder and one or more streamlined plan…
18 AAC 75-429 Equipment, training, personnel, and fuel transfer requirements for noncrude oil tank vessel or barge streamlined plans
2.1K chars
(a) A noncrude oil tank vessel or barge that has an approved streamlined plan must maintain the following equipment on board:(1) sorbent boom, not less than six times the length of the vessel and at least five inches in height, and equipment necessary to secure it; (2) a vessel c…
18 AAC 75-430 Response planning standards
2.4K chars
(a) Notwithstanding the response planning standards set out in 18 AAC 75.430 - 18 AAC 75.442, the plan must demonstrate the general procedures to clean up a discharge of any size, including the greatest possible discharge that could occur, subject to the provisions of AS 46.04.02…
18 AAC 75-432 Response planning standards for oil terminal facilities
3.3K chars
(a) For an oil terminal facility, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and other resour…
18 AAC 75-433 Response planning standards for railroad tank cars
0.9K chars
For a railroad tank car, the plan holder shall maintain, or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and other resources to (…
18 AAC 75-434 Response planning standards for exploration or production facilities
5.9K chars
(a) For an exploration or production facility, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and…
18 AAC 75-436 Response planning standards for crude oil pipelines
2.7K chars
(a) For a crude oil pipeline facility, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and other r…
18 AAC 75-438 Response planning standards for crude oil tank vessels and barges
3.0K chars
(a) For a crude oil tank vessel or barge, the plan holder shall maintain or have available under contract within its region of operation, sufficient discharge containment, storage, transfer, and cleanup equipment, personnel, and other resources to (1) contain or control, and clea…
18 AAC 75-440 Response planning standards for noncrude oil tank vessels and barges
1.3K chars
(a) For a noncrude oil tank vessel or barge, the plan holder shall maintain or have available under contract within the plan holder's region of operation or another approved location, sufficient oil discharge containment, storage, transfer, and cleanup equipment, personnel, and o…
18 AAC 75-441 Response planning standards for nontank vessels
1.5K chars
(a) For a nontank vessel, the plan holder shall maintain or have available under contract or membership agreement within the plan holder's region of operation, sufficient oil discharge containment and control equipment and shall maintain or have available under contract or member…
18 AAC 75-442 Response planning standards for multiple operations
0.7K chars
For a plan having multiple facility types that require an approved oil discharge prevention and contingency plan, the plan holder must plan to respond to a discharge of the applicable response planning standard volume for each separate facility type in the plan as established und…
18 AAC 75-443 Prevention credits for nontank vessels. (Repealed)
0.5K chars
Notes 18 AAC 75.443 Eff. 11/27/2002, Register 164; repealed 9/4/2014, Register 211, October 2014 Authority:AS 46.03.020 AS 46.04.030 AS 46.04.055 AS 46.04.065 AS 46.04.070 State regulations are updated quarterly; we currently have two versions available. Below is a comparison bet…
18 AAC 75-445 Approval criteria for oil discharge prevention and contingency plans (Repealed)
0.5K chars
Notes 18 AAC 75.445 Eff. 5/14/92, Register 122; am 9/25/93, Register 127; am 3/28/96, Register 137; am 4/4/97, Register 142; am 5/26/2004, Register 170; am 12/30/2006, Register 180; repealed 2/5/2023, Register 245, April 2023 State regulations are updated quarterly; we currently …
18 AAC 75-446 [Repealed]
0.4K chars
Notes 18 AAC 75.446 Eff. 11/27/2002, Register 164; am 4/16/2016, Register 218, July 2016 repealed 3/23/2017, Register 221, April 2017 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the p…
18 AAC 75-447 Department examination of new technologies (Repealed)
0.4K chars
Notes 18 AAC 75.447 Eff. 4/4/97, Register 142; repealed 2/5/2023, Register 245, April 2023 State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison fea…
18 AAC 75-448 Oil discharge prevention and contingency plan; general plan requirements
2.7K chars
(a) An oil discharge prevention and contingency plan submitted for approval under 18 AAC 75.400 - 18 AAC 75.495 must be usable as a working plan for oil discharge control, containment, cleanup, and disposal. The plan must contain enough information, analyses, supporting data, and…
18 AAC 75-449 Part 1 - oil discharge prevention and contingency plan; Response Action Plan
15.6K chars
(a) The response action plan must include the following information in sufficient detail to clearly guide responders in an emergency event: (1) emergency action checklist - a short checklist of the immediate response and notification steps to be taken if an oil discharge occurs; …
18 AAC 75-450 Part 2 - oil discharge prevention and contingency plan; prevention plan
3.2K chars
(a) The prevention plan must demonstrate that the applicant meets all applicable requirements of 18 AAC 75.005 - 18 AAC 75.085 and must provide a detailed description of all oil discharge prevention measures, policies, and programs in place at the facility, with reference to the …
18 AAC 75-451 Part 3 - oil discharge prevention and contingency plan; supplemental information
19.9K chars
(a) The supplemental information section must provide the background and verification information identified in (b) - (n) of this section. (b) The plan holder must provide a facility description and operational overview. This is a general description of the oil storage, transfer,…
18 AAC 75-452 Part 4 - oil discharge prevention and contingency plan; best available technology review
5.6K chars
(a) Unless application of a state requirement would be preempted by federal law, the plan must provide for the use of best available technology consistent with the applicable criteria in (c) of this section. Technologies that are not subject to the response planning standards or …
18 AAC 75-453 Part 5 - oil discharge prevention and contingency plan; response planning standard
1.0K chars
The plan must (1) provide a mathematical calculation of the applicable response planning standards set out in 18 AAC 75.430 - 18 AAC 75.440 and 18 AAC 75.442; (2) include a detailed calculation and justification of reductions to the response planning standard; and (3) include an …
18 AAC 75-455 Department review procedures for oil discharge prevention and contingency plans; new plans, plan renewals, and major plan amendments
6.5K chars
(a) Not later than seven working days after receipt of an oil discharge prevention and contingency plan application package for a new plan, plan renewal or major amendment, the department will determine if the application package is sufficient for review. For an amendment applica…
18 AAC 75-456 Department decision on streamlined oil discharge prevention and contingency plans
2.1K chars
(a) The department will approve or disapprove a streamlined oil discharge prevention and contingency plan or plan amendment not later than five working days after receipt of a complete application. The department will approve a streamlined plan application submitted under 18 AAC …
18 AAC 75-457 Emergency modification of review process
1.2K chars
If, due to an emergency as described in AS 26.23, AS 46.04.080, or other applicable law, an applicant needs an expedited review, or if the commissioner or the commissioner's designee finds that an expedited review is necessary for the preservation of the public peace, health, saf…
18 AAC 75-459 Preissuance conference
1.4K chars
(a) After the department has determined that the application package is complete and before the department issues its decision under 18 AAC 75.460, the applicant may request a preissuance conference. The request must be made in writing, and will be granted if the applicant demons…
18 AAC 75-460 Department decision on oil discharge prevention and contingency plans; new plans, plan renewals, and major plan amendments
3.8K chars
(a) After considering the information, analyses, and commitments contained in a complete application package for approval of an oil discharge prevention and contingency plan and comments received not later than the close of the public comment period set out in 18 AAC 75.455, the …
18 AAC 75-465 Proof of approved plan
4.1K chars
(a) The owner or operator of an oil terminal facility may not cause or permit the transfer of oil to or from a vessel, barge, or railroad tank car unless (1) the operator of the vessel, barge, or railroad tank car has produced for inspection by the facility owner or operator the …
18 AAC 75-470 Transfers between plan holders
3.4K chars
(a) If approved under this section, a plan holder, or an oil spill response contractor or cooperative upon which one or more plan holders rely, may furnish to another plan holder or to another person, equipment, materials, or personnel to assist in response to an oil discharge. A…
18 AAC 75-475 Notification of nonreadiness
2.6K chars
(a) All spill response and other equipment identified in the approved oil discharge prevention and contingency plan or streamlined plan to meet the response planning standards set out in 18 AAC 75.430 - 18 AAC 75.442 must be maintained in operational condition. Equipment found no…
18 AAC 75-480 Inspections
3.1K chars
(a) To verify that an owner or operator of a facility subject to AS 46.04.030 or AS 46.04.055 and to 18 AAC 75.400 - 18 75.496 is in compliance with those statutes and regulations, or to verify compliance with an approved oil discharge prevention and contingency plan or a streaml…
18 AAC 75-485 Discharge exercises
5.2K chars
(a) The department may conduct announced and unannounced discharge exercises appropriate to the plan holder's current status of operations to ensure that an oil discharge prevention and contingency plan or the initial response actions in a streamlined plan for a noncrude oil tank…
18 AAC 75-489 Definition
0.7K chars
In 18 AAC 75.400 - 18 AAC 75.496, "temporary basis" means the use of an aboveground oil storage tank located at a facility for a duration of less than 12 consecutive months and is limited to aboveground oil storage tanks used for project or maintenance activities. Notes 18 AAC 75…
18 AAC 75-490 Failure to comply
1.9K chars
(a) If a plan holder fails to comply with an approved oil discharge prevention and contingency plan or streamlined plan, demonstrates an inability to maintain continuous access to the quality or quantity of resources identified in the plan, fails to respond with those resources i…
18 AAC 75-495 Regional master discharge prevention and contingency plan boundaries
7.6K chars
(a) Three coastal areas and one inland area, and associated geographic zones as described in (b) of this section, are established for the regional master oil and hazardous substance discharge prevention and contingency plan boundaries as required by AS 46.04.210. Planning areas a…
18 AAC 75-496 Regional response operations plan boundaries for nontank vessels
2.6K chars
The regions described in this section and depicted on the map at Figure 2 are established for the purpose of establishing boundaries for nontank vessel plans: Figure. 1 Regional Response Operations Plan Boundaries (18 AAC 75.496) CLICK TO VIEW MAP (1) Southeast Alaska Region: tha…
18 AAC 75-500 Definition of oil spill primary response action contractor; applicability
2.3K chars
(a) As used in AS 46.04.035 and 18 AAC 75.500 - 18 AAC 75.580, "oil spill primary response action contractor" means a person who is or intends to be obligated under contract to the holder of an approved oil discharge prevention and contingency plan issued under AS 46.04.030 to pr…
18 AAC 75-501 Applicability with respect to streamlined plan cleanup contractors, incident management teams, and response planning facilitators
2.9K chars
(a) The department will not consider a person to be a streamlined plan cleanup contractor, incident management team, or response planning facilitator, or to be otherwise subject to the registration requirements of AS 46.04.055 as applicable 18 AAC 75.500 - 18 AAC 75.580, if the p…
18 AAC 75-510 General provisions
1.4K chars
(a) The resources of a response action contractor listed in an oil discharge prevention and contingency plan to contain, control, or clean up an oil discharge and to demonstrate compliance with all or part of a response planning standard under 18 AAC 75.432 - 18 AAC 75.442 will n…
18 AAC 75-520 Application for oil spill primary response action contractor registration or renewal
1.5K chars
(a) Oil spill primary response action contractor registration under this section is effective for three years after the date of issuance under 18 AAC 75.550. (b) A person seeking registration or renewal of registration as an oil spill primary response action contractor must submi…
18 AAC 75-521 Application for streamlined plan cleanup contractor registration
1.1K chars
(a) Streamlined plan cleanup contractor registration is effective for as long as the contractor is in compliance with the applicable requirements of this chapter. (b) A person seeking registration as a streamlined plan cleanup contractor must submit an application to the departme…
18 AAC 75-522 Application for streamed plan incident management team registration
1.2K chars
(a) Streamlined plan vessel' incident management team registration is effective for as long as the contractor is in compliance with the applicable requirements of this chapter. (b) A person seeking registration as a streamlined plan incident management team must submit an applica…
18 AAC 75-523 Application for response planning facilitator registration
1.1K chars
(a) A response planning facilitator registration is effective for as long as the contractor is in compliance with the applicable requirements of this chapter. (b) A person seeking registration as a response planning facilitator must submit an application to the department, on a f…
18 AAC 75-530 Registration application contents for oil spill primary response action contractors for oil discharge prevention and contingency plans
2.4K chars
(a) An application required under 18 AAC 75.520(b) must (1) include the applicant's name, address, telephone number, and facsimile machine number; (2) identify each region described in 18 AAC 75.495 where the applicant's oil spill response resources will be made available for use…
18 AAC 75-531 Registration application contents for streamlined plan cleanup contractors
3.1K chars
An application submitted under 18 AAC 75.521 must include the following information: (1) the applicant's name, address, and telephone number, and any facsimile number; (2) a current list of streamlined plans that rely on the contracted services of the applicant and (A) the number…
18 AAC 75-532 Registration application contents for streamlined plan incident management teams
3.8K chars
An application submitted under 18 AAC 75.522 must include the following information: (1) the applicant's name, address, and telephone number, and any facsimile number; (2) a current list of streamlined plans that rely on the contracted services of the applicant and (A) the number…