312 sections in this chapter.
R14-2-307 Main Extensions
5.2K chars
A. General requirements 1. Each utility shall file for Commission approval a main extension tariff which incorporates the provisions of this rule and specifically defines the conditions governing main extensions. 2. Upon request by an applicant for a main extension, the utility s…
R14-2-308 Provision of Service
6.9K chars
A. Utility responsibility 1. Each utility shall be responsible for the safe transmission and distribution of gas until it passes the point of delivery to the customer. 2. Each utility shall be responsible for maintaining in safe operating condition all meters, regulators, service…
R14-2-309 Meter Reading
3.0K chars
A. Company or customer meter reading 1. Each utility may at its discretion allow for customer reading of meters. 2. It shall be the responsibility of the utility to inform the customer how to properly read his or her meter. 3. Where a customer reads his or her own meter, the util…
R14-2-310 Billing and Collection
10.1K chars
A. Frequency and estimated bills 1. Each utility shall bill monthly for services rendered. Meter readings shall be scheduled for periods of not less than 25 days or more than 35 days. 2. If the utility is unable to read the meter on the scheduled meter read date, the utility will…
R14-2-311 Termination of Service
18.2K chars
A. Restrictions on termination of service; recordkeeping and repayment 1. A utility shall not terminate service to a customer due to delinquency in payment for services rendered to a prior customer at the service address where service is being provided, unless the prior customer …
R14-2-312 Administrative and Hearing Requirements
12.6K chars
A. Customer service complaints 1. Each utility shall make a full and prompt investigation of each service complaint made by one of its customers, whether made directly or through the Commission. 2. Within five business days after a complaint is made, the utility shall respond to …
R14-2-313 Conservation
1.0K chars
Energy conservation plan 1. The Arizona Corporation Commission recognizes the need for conservation of energy resources in order to maintain an adequate and continuous supply of safe, dependable, and affordable energy. Therefore, in order to promote the state’s economic developme…
R14-2-314 Intermittent Gas Ignition
8.0K chars
A. Application and scope. The provisions of this rule are applicable to the following types of gas appliances: 1. All residential gas-fired space heating equipment requiring electrical supply for operation, 2. All residential gas-fired clothes dryers, 3. All residential gas-fired…
R14-2-315 Compliance by Gas Cooperatives
0.9K chars
A. The terms and conditions for termination of service, including customer notice, in a gas cooperative’s tariff approved by the Commission prior to the effective date of this Section shall substitute for the provisions of R14-2-311. B. Notwithstanding R14-2-312(F), a gas coopera…
R14-2-316 Termination of Service Reporting Requirements
3.3K chars
Beginning onApril 15, 2022, and on each July 15, October 15, January 15, and April 15 thereafter, each regulated Class A, B, and C gas utility that provides residential gas service shall file a quarterly report providing the following information for each month of the previous qu…
R14-2-401 Definitions
6.3K chars
In this Article, unless the context otherwise requires, the following definitions shall apply: 1. “Advance in aid of construction.” Funds provided to the utility by the applicant under the terms of a main extension agreement the value of which may be refundable. 2. “Applicant.” A…
R14-2-402 Certificates of Convenience and Necessity for
19.0K chars
Water Utilities; Extensions of Certificates of Convenience and Necessity forWater Utilities; Abandonment, Sale, Lease, Transfer, or Disposal of a Water Utility; Discontinuance orAbandonment of Water Utility Service A. In this Section, unless otherwise specified: 1. “Applicant” me…
R14-2-403 Establishment of Service
5.8K chars
A. Information from new applicants 1. A utility may obtain the following minimum information from each new applicant for service: a. Name or names of applicant(s). b. Service address or location and telephone number c. Billing address/telephone number, if different than service a…
R14-2-404 Minimum Customer Information Requirements
1.8K chars
A. Information for residential customers 1. Each utility shall make available upon customer request not later than 60 days from the date of request a concise summary of the rate schedule applied for by such customer. The summary shall include the following: a. Monthly minimum or …
R14-2-405 Service Connections and Establishments
4.6K chars
A. Priority and timing of service establishments 1. After an applicant has complied with the utility’s application and deposit requirements and has been accepted for service by the utility, the utility shall schedule that customer for service connection and/or establishment. 2. S…
R14-2-406 Main ExtensionAgreements
9.1K chars
A. Each utility entering into a main extension agreement shall comply with the provisions of this rule which specifically defines the conditions governing main extensions. B. An applicant for the extension of mains may be required to pay to the Company, as a refundable advance in…
R14-2-407 Provision of Service
4.5K chars
A. Utility responsibility. Each utility shall be responsible for providing potable water to the customer’s point of delivery. B. Customer responsibility 1. Each customer shall be responsible for maintaining all facilities on the customer’s side of the point of delivery in a safe …
R14-2-408 Meter Reading
2.4K chars
A. Frequency. Each meter shall be read monthly on as close to the same day as practical. B. Measuring of service 1. All water delivered by the utility shall be billed upon the basis of metered volume sales except that the utility may, at its option, provide a fixed charge schedul…
R14-2-409 Billing and Collection
8.1K chars
A. Frequency and estimated bills 1. Each utility shall bill monthly for services rendered. Meter readings shall be scheduled for periods of not less than 25 days or more than 35 days. 2. If the utility is unable to read the meter on the scheduled meter read date, the utility will…
R14-2-410 Termination of Service
6.9K chars
A. Nonpermissible reasons to disconnect service. A utility may not disconnect service for any of the reasons stated below: 1. Delinquency in payment for services rendered to a prior customer at the premises where service is being provided, except in the instance where the prior c…
R14-2-411 Administrative and Hearing Requirements
6.8K chars
A. Customer service complaints 1. Each utility shall make a full and prompt investigation of all service complaints made by its customers, either directly or through the Commission. 2. The utility shall respond to the complainant and/or the Commission representative within five w…
R14-2-501 Definitions
3.9K chars
In this Article, unless the context otherwise requires, the following definitions shall apply: 1. “Advance in aid of construction.” Funds provided to the utility by the applicant under the terms of a construction agreement, which may be refundable. 2. “Applicant.” A person or age…
R14-2-502 Certificate of Convenience and Necessity for
2.4K chars
Telephone Utilities; Additions/Extensions; Abandonments A. Application for new Certificate of Convenience and Necessity 1. Six copies of each application for a new Certificate of Convenience and Necessity shall be submitted in a form prescribed by the Commission and shall include…
R14-2-503 Establishment of Service
6.4K chars
A. Information from new applicants 1. A utility may obtain the following minimum information from each new applicant for service: a. Name or names of applicant(s). b. Service address or location and telephone number c. Billing address, if different than service address. d. Addres…
R14-2-504 Minimum Customer Information Requirements
1.2K chars
A. Information for residential customers 1. Each utility shall make available upon customer request not later than 60 days from the date of request a concise summary of the rate schedule applied for by such customer. The summary shall include the following: a. The charges for bas…
R14-2-505 Service Connections and Establishments
3.9K chars
A. Priority and timing of service establishments 1. After an applicant has complied with the utility’s application, construction agreement, or tariff, deposit requirements and has been accepted for service by the utility, the utility shall schedule that customer for service conne…
R14-2-506 ConstructionAgreements
10.6K chars
A. General requirements 1. Each utility shall file for Commission approval a tariff which incorporates the provisions of this rule and specifically defines the conditions governing construction agreements. Subsections (A), (B), (C), and (D) of this Section do not apply to tariffs…
R14-2-507 Provision of Service
4.0K chars
A. Utility responsibility. Each utility shall be responsible for maintaining in safe operating condition all equipment and fixtures used in providing utility service to the customer that are owned by and under the exclusive control of the utility. B. Customer responsibility 1. Ea…
R14-2-508 Billing and Collection
6.8K chars
A. Frequency. Each utility shall bill monthly for services rendered. B. Minimum bill information. Each utility shall provide the following minimum information on customer bills: 1. Monthly charge for basic exchange service including delineation of the following: a. Total charge f…
R14-2-509 Termination of Service
8.2K chars
A. Nonpermissible reasons to disconnect service. A utility may not disconnect service for any of the reasons stated below: 1. Delinquency in payment for services rendered to a prior customer at the premises where service is being provided, except in the instance where the prior c…
R14-2-510 Administrative and Hearing Requirements
10.7K chars
A. Customer service complaints 1. Each utility shall make a full and prompt investigation of all service complaints made by its customers, either directly or through the Commission. 2. The utility shall respond to the complainant and/or the Commission representative within five w…
R14-2-601 Definitions
5.4K chars
In this Article, unless the context otherwise requires, the following definitions shall apply: 1. “Advance in aid of construction.” Funds provided to the utility by the applicant under the terms of a collection main extension agreement the value of which may be refundable. 2. “Ap…
R14-2-602 Certificates of Convenience and Necessity for
17.8K chars
Sewer Utilities; Extensions of Certificates of Convenience and Necessity for Sewer Utilities;Abandonment, Sale, Lease, Transfer, or Disposal of a Sewer Utility; Discontinuance orAbandonment of Sewer Utility Service A. In this Section, unless otherwise specified: 1. “Applicant” me…
R14-2-603 Establishment of Service
5.3K chars
A. Information from new applicants 1. A utility may obtain the following minimum information from each new applicant for service: a. Name or names of applicant(s). b. Service address or location and telephone number. c. Billing address or location and telephone number, if differe…
R14-2-604 Minimum Customer Information Requirements
1.6K chars
A. Information for residential customers 1. Each utility shall make available upon customer request not later than 60 days from the date of request a concise summary of the rate schedule applied for by such customer. The summary shall include the following: a. Monthly minimum or …
R14-2-605 Service Connections
2.6K chars
A. Priority and timing 1. After an applicant has complied with the utility’s application and deposit requirements and has been accepted for service by the utility, the utility shall schedule that customer for service connection. 2. Service connections shall be scheduled for compl…
R14-2-606 Collection Main Extension Agreements
5.3K chars
A. General requirements 1. Each utility entering into a main extension agreement shall comply with the provisions of this rule, which specifically defines the conditions governing collection main extensions. December 31, 2025 Supp. 25-4 Page 121 Arizona Administrative Code 14 A.A…
R14-2-607 Provision of Service
3.6K chars
A. Utility responsibility 1. Each utility shall be responsible for the safe conduct and handling of the sewage from the customer’s point of collection. 2. The utility may, at its option, refuse service until the customer has obtained all required permits and/or inspections indica…
R14-2-608 Billing and Collection
3.4K chars
A. Frequency. Each utility shall bill monthly for services rendered. B. Minimum bill information. Each bill for residential service will contain the following minimum information: 1. Billed discharge, where applicable 2. Utility telephone number 3. Amount due and due date 4. Cust…
R14-2-609 Termination of Service
6.3K chars
A. Nonpermissible reasons to disconnect service. A utility may not disconnect service for any of the reasons stated below: 1. Delinquency in payment for services rendered to a prior customer at the premises where service is being provided, except in the instance where the prior c…
R14-2-610 Administrative and Hearing Requirements
6.9K chars
A. Customer service complaints 1. Each utility shall make a full and prompt investigation of all service complaints made by its customers, either directly or through the Commission. 2. The utility shall respond to the complainant and/or the Commission representative within five w…
R14-2-701 Definitions
9.1K chars
In thisArticle, unless otherwise specified: 1. “Acknowledgment” means a Commission determination, under R14-2-704, that a plan meets the basic requirements of thisArticle. December 31, 2025 Supp. 25-4 Page 125 Arizona Administrative Code 14 A.A.C. 2 TITLE 14. PUBLIC SERVICE CORPO…
R14-2-702 Applicability
2.1K chars
A. This Article applies to each load-serving entity, whether the power generated is for sale to end users or is for resale. B. An electricity public service corporation that becomes a loadserving entity by increasing its generating capacity to at least 50 megawatts combined shall…
R14-2-703 Load-serving Entity Reporting Requirements
17.1K chars
A. A load-serving entity shall, by April 1 of each year, file with Docket Control a compilation of the following items of demand-side data, including for each item for which no record is maintained the load-serving entity’s best estimate and a full description of how the estimate…
R14-2-704 Commission Review of Load-serving Entity
3.4K chars
Resource Plans A. By October 1 of each even year, Staff shall file a report that contains its analysis and conclusions regarding its statewide review and assessments of the load-serving entities’ filings made under R14-2-703(C), (D), (E), (F), and (H). B. By February 1 of each od…
R14-2-705 Procurement
2.1K chars
A. Except as provided in subsection (B), a load-serving entity may use the following procurement methods for the wholesale acquisition of energy, capacity, and physical power hedge transactions: 1. Purchase through a third-party online trading system; 2. Purchase from a third-par…
R14-2-706 Independent Monitor Selection and Responsibilities
3.1K chars
A. When a load-serving entity contemplates engaging in an RFP process, the load-serving entity shall consult with Staff regarding the identity of companies or consultants that could serve as independent monitor for the RFPprocess. B. After consulting with Staff, a load-serving en…
R14-2-801 that, in relation to a cooperative, meets the
19.4K chars
definition of an “affiliate” inA.A.C. R14-2-801. 2. “Base revenue” means the revenue generated by permanent rates and charges, excluding: a. Revenue generated through adjustor mechanisms, and b. Revenue generated through miscellaneous service charges. 3. “CFC” means the National …
R14-2-802 Applicability
0.9K chars
A. These rules are applicable to all Class A investor-owned utilities under the jurisdiction of the Commission and are applicable to all transactions entered into after the effective date of these rules. B. Notwithstanding subsection (A), these rules shall not apply to a telecomm…
R14-2-803 Organization of Public Utility Holding Companies
3.0K chars
A. Any utility or affiliate intending to organize a public utility holding company or reorganize an existing public utility holding company will notify the Commission’s Utilities Division in writing at least 120 days prior thereto. The notice of intent will include the following …