27.5.B.91-91-902 27 CAR § 91-902. Preliminary engineering procedures
2.8K chars
27 CAR § 91-902. Preliminary engineering procedures. (a)(1) When the use of a consultant has been approved, the utility owner will be authorized to have the consultant proceed with preparing a preliminary engineering fee estimate and contract. (2) The engineer's fee shall not be …
27.5.B.91-91-903 27 CAR § 91-903. Construction engineering procedures
0.9K chars
27 CAR § 91-903. Construction engineering procedures. (a) Supervision and inspection by the consultant during the construction work will be considered as a part of the relocation agreement and reimbursed separately from the PE agreement. (b) These activities will consist of, but …
27.5.B.91-91-904 27 CAR § 91-904. Engineering costs
3.9K chars
27 CAR § 91-904. Engineering costs. Utility owners utilizing consulting engineers for design or construction engineering services shall comply with the following requirements: (1) Overhead rates. (A) Overhead rates must be computed in accordance with Federal Acquisition Regulatio…
27.5.B.91-91-905 27 CAR § 91-905. Engineering change orders
0.5K chars
27 CAR § 91-905. Engineering change orders. (a) When the utility owner identifies a need for change to the quantity, type, or scope of preliminary or construction engineering, the utility owner shall inform the Utilities Section Head or resident engineer, as applicable, of the re…
27.5.B.92-92-101 27 CAR § 92-101. Introduction
0.6K chars
27 CAR § 92-101. Introduction. (a) The design-build project delivery (design-build or D-B) method is an alternative delivery method utilized to deliver design-construction projects more efficiently and expeditiously than the more conventional design-bid-build project delivery (DB…
27.5.B.92-92-102 27 CAR § 92-102. Purpose
0.7K chars
27 CAR § 92-102. Purpose. (a) The purpose of this part is to describe general Arkansas Department of Transportation processes for efficiently and effectively procuring and administering design and construction services for a transportation facility utilizing the D-B method. (b) W…
27.5.B.92-92-103 27 CAR § 92-103. Authority
0.6K chars
27 CAR § 92-103. Authority. (a) Acts 2003, No. 460, of the Regular Session of the 84th General Assembly authorized the State Highway Commission to enter into design-build contracts for highway construction projects and is included as Appendix A. (b) Acts 2013, No. 541, of the Reg…
27.5.B.92-92-104 27 CAR § 92-104. Definitions
35.3K chars
27 CAR § 92-104. Definitions. The following definitions and acronyms apply to the design-build guidelines, processes, and procedures: (1)(A) “Adjusted price” means the value calculated at the completion of the proposal evaluation whereby the combination of the FMP, provided by th…
27.5.B.92-92-201 27 CAR § 92-201. Review
1.9K chars
27 CAR § 92-201. Review. (a)(1) To determine whether the project is a suitable candidate for a design-build (D-B) delivery process, the Arkansas Department of Transportation should conduct a thorough review of the project’s key goals and objectives as well as a complete assessmen…
27.5.B.92-92-202 27 CAR § 92-202. Project selection
0.6K chars
27 CAR § 92-202. Project selection. (a) Potential D-B projects may be proposed by Arkansas Department of Transportation staff for consideration by the Director of State Highways and Transportation. (b) The department may also receive an unsolicited project proposal (UPP) for a pr…
27.5.B.92-92-301 27 CAR § 92-301. Overview
1.3K chars
27 CAR § 92-301. Overview. (a) A D-B project will normally advance through the early stages of project development in the same manner as a DB-B project, however, each D-B project is unique and the Arkansas Department of Transportation must carefully assess the project development…
27.5.B.92-92-302 27 CAR § 92-302. Project programming
0.7K chars
27 CAR § 92-302. Project programming. (a) Most agencies and other Arkansas Department of Transportation program D-B projects in the same manner as projects delivered using the more traditional DB-B delivery method. (b) It is important to note, however, that if D-B delivery is sel…
27.5.B.92-92-303 27 CAR § 92-303. Project scope
2.1K chars
27 CAR § 92-303. Project scope. (a)(1) The project scope should be developed using existing work products and/or products from data gathered during the programming process. (2) These products and data should provide the basis to describe the existing conditions, the proposed proj…
27.5.B.92-92-304 27 CAR § 92-304. Project timeline and project schedule
1.1K chars
27 CAR § 92-304. Project timeline and project schedule. (a) The project timeline, which includes the entire project period from initial development through the project final acceptance, must allow sufficient time for all required tasks outside of the D-B period, including: (1) En…
27.5.B.92-92-305 27 CAR § 92-305. Project funding
0.7K chars
27 CAR § 92-305. Project funding. (a) In all D-B projects, the Arkansas Department of Transportation should identify funding sufficient to support the project, considering total project cost as well as cash flow requirements, prior to the initiation of the procurement process. (b…
27.5.B.92-92-306 27 CAR § 92-306. Project risk overview
7.1K chars
27 CAR § 92-306. Project risk overview. (a)(1) Allocation of the project risks inherent in highway projects is a major factor in and underlying the D-B development model. (2) The definition of ownership and responsibility for each task and its associated risk is an important cons…
27.5.B.92-92-307 27 CAR § 92-307. Preliminary design and engineering
1.9K chars
27 CAR § 92-307. Preliminary design and engineering. (a)(1) The level of preliminary design and engineering provided by the Arkansas Department of Transportation for a D-B project can vary from project to project, but a twenty percent (20%) to thirty percent (30%) level of design…
27.5.B.92-92-308 27 CAR § 92-308. Environmental documentation
1.7K chars
27 CAR § 92-308. Environmental documentation. (a) The preparation of project environmental documents (PED), and the subsequent obtaining of required environmental and regulatory clearances, should normally be performed by the Arkansas Department of Transportation in accordance wi…
27.5.B.92-92-309 27 CAR § 92-309. Right-of-way coordination
1.9K chars
27 CAR § 92-309. Right-of-way coordination. (a)(1) Right-of-way acquisition will normally be the responsibility of the Arkansas Department of Transportation. (2) In order to prevent proposers from arbitrarily pricing uncertainty of ROW availability, right-of-way acquisition will …
27.5.B.92-92-310 27 CAR § 92-310. Geotechnical considerations
19.7K chars
27 CAR § 92-310. Geotechnical considerations. (a)(1)(A) In a more traditional DB-B project, any geotechnical investigation and subsequent report are provided by the Arkansas Department of Transportation or an authorized representative firm prior to design to enable the department…
27.5.B.92-92-311 27 CAR § 92-311. Inter-agency agreement
0.9K chars
27 CAR § 92-311. Inter-agency agreement. (a) An inter-agency agreement (IAA) between the Arkansas Department of Transportation and another state or local agency, such as the Division of Environmental Quality, Union Pacific Railroad, BNSF Railway, or a city or county government, i…
27.5.B.92-92-312 27 CAR § 92-312. Utilities agreement
1.4K chars
27 CAR § 92-312. Utilities agreement. (a) A project utility agreement (PUA), either formal or informal, required for an adjustment, whether for protection only or relocation of the utility, is normally obtained by the Arkansas Department of Transportation prior to the issuance of…
27.5.B.92-92-313 27 CAR § 92-313. Public involvement
0.7K chars
27 CAR § 92-313. Public involvement. (a) A D-B project does not reduce the need for a comprehensive public involvement program from what would be required for the more traditional DB-B project. (b) In most cases, a D-B project will require that the public involvement be more comp…
27.5.B.92-92-314 27 CAR § 92-314. Public information
1.9K chars
27 CAR § 92-314. Public information. (a) The Arkansas Department of Transportation must maintain superior public communication throughout the duration of any project in order to: (1) Maintain the department’s role as a good neighbor; (2) Maintain a positive opinion; and (3) Avoid…
27.5.B.92-92-315 27 CAR § 92-315. Reference information documents
2.2K chars
27 CAR § 92-315. Reference information documents. (a)(1) As noted in an earlier section, the outcomes of the preliminary engineering and environmental processes for a D-B project provide important information and requirements to be relayed to the short-list proposers as part of t…
27.5.B.92-92-316 27 CAR § 92-316. Value engineering
0.9K chars
27 CAR § 92-316. Value engineering. (a) A value engineering study (VES) is not required for projects delivered using the D-B method (Section 1503(a)(3) of the Moving Ahead for Progress in the 21st Century Act, Pub. L. No. 112-141), however, based on the parameters of a specific p…
27.5.B.92-92-317 27 CAR § 92-317. Stipend for unsuccessful proposers
1.1K chars
27 CAR § 92-317. Stipend for unsuccessful proposers. (a) In the more traditional DB-B process, the Arkansas Department of Transportation does not reimburse the contractors that submit responsive bids but are unsuccessful in selection for the project. (b) In the D-B process, the c…
27.5.B.92-92-401 27 CAR § 92-401. Introduction
3.7K chars
27 CAR § 92-401. Introduction. (a)(1) The Arkansas Department of Transportation will normally utilize a two-step process during the procurement phase of the project to select a design-builder. (2) The first step is the Arkansas Department of Transportation solicitation for potent…
27.5.B.92-92-402 27 CAR § 92-402. Project director
1.8K chars
27 CAR § 92-402. Project director. (a)(1) A project of the size and importance that will be attractive to the Arkansas Department of Transportation as a D-B project will extend several years from initial project identification through all the stages of the project, i.e., prelimin…
27.5.B.92-92-403 27 CAR § 92-403. Department procurement team
2.8K chars
27 CAR § 92-403. Department procurement team. (a)(1) Development of the procurement documents and the process utilized to select a design-builder is a unique experience in that the effort involves creating documents other than plans, technical specifications, and selection factor…
27.5.B.92-92-404 27 CAR § 92-404. Project training
2.7K chars
27 CAR § 92-404. Project training. (a)(1) Each individual assigned to the procurement, evaluation, or monitoring during the procurement process should be required to attend training. (2) It is important for each individual to understand: (A) How a D-B procurement process function…
27.5.B.92-92-405 27 CAR § 92-405. Confidentiality and security
2.7K chars
27 CAR § 92-405. Confidentiality and security. (a)(1) It is important to understand that the procurement process and the requisite evaluations and selection is a very competitive process. (2) As such, the Arkansas Department of Transportation as a whole, and the DPT and PET in pa…
27.5.B.92-92-406 27 CAR § 92-406. Proposer request for clarification
0.7K chars
27 CAR § 92-406. Proposer request for clarification. (a) The Arkansas Department of Transportation, and similarly the DPO, should be aware that the development of the D-B proposal involves an extensive design effort by each short-list proposer and will likely generate a greater n…
27.5.B.92-92-407 27 CAR § 92-407. Location and logistics
1.0K chars
27 CAR § 92-407. Location and logistics. (a) Due to the sensitive and confidential nature of the SOQs and proposals, and the necessity for SOQ and proposal details to remain secure, all evaluations should take place in a single secure location, with PET members involved in the ev…
27.5.B.92-92-501 27 CAR § 92-501. Generally
0.2K chars
27 CAR § 92-501. Generally. (a) An example of a flow diagram representing a design-build procurement process is included as Appendix G. (b) Some of the general steps included in the process are discussed in this subpart.
27.5.B.92-92-502 27 CAR § 92-502. Step 1: Issue solicitation of interest (optional)
1.4K chars
27 CAR § 92-502. Step 1: Issue solicitation of interest (optional). (a) Prior to the initiation of the formal procurement process that occurs when an RFQ is released for a D-B project, the Arkansas Department of Transportation may consider releasing a solicitation of interest (SO…
27.5.B.92-92-503 27 CAR § 92-503. Step 2: Prequalification (optional)
3.3K chars
27 CAR § 92-503. Step 2: Prequalification (optional). (a)(1) The Arkansas Department of Transportation may require that the proposers, or possibly only the design-builder, or any component firms/personnel be prequalified prior to execution of the DBA with the department. (2) Wher…
27.5.B.92-92-504 27 CAR § 92-504. Step 3: Prepare the request for qualifications
8.4K chars
27 CAR § 92-504. Step 3: Prepare the request for qualifications. (a)(1) The request for qualifications (RFQ) is a request from the Arkansas Department of Transportation to interested proposers to submit a well-defined package typically outlining: (A) Historical information relate…
27.5.B.92-92-505 27 CAR § 92-505. Step 4: Evaluate the statement of qualifications
4.6K chars
27 CAR § 92-505. Step 4: Evaluate the statement of qualifications. (a)(1) The evaluation and scoring of the statement of qualifications (SOQ) should be performed by the project evaluation team (PET), which should ideally be comprised of individuals who possess a broad array of ex…
27.5.B.92-92-506 27 CAR § 92-506. Step 5: Prepare the request for proposals
8.2K chars
27 CAR § 92-506. Step 5: Prepare the request for proposals. (a) General. (1) The purpose of the request for proposals (RFP) is to furnish sufficient information for a short-list proposer to prepare a detailed proposal which would normally include both a technical proposal and pri…
27.5.B.92-92-507 27 CAR § 92-507. Step 5A: Acquire and organize reference material — Reference information documents
1.2K chars
27 CAR § 92-507. Step 5A: Acquire and organize reference material — Reference information documents. (a) The reference material available in the project corridor should be gathered by the DPT from the Arkansas Department of Transportation, other agencies, and other private source…
27.5.B.92-92-508 27 CAR § 92-508. Step 5B: Instructions to proposers
14.9K chars
27 CAR § 92-508. Step 5B: Instructions to proposers. (a) General requirements. (1) The general requirements detail how the short-list proposer should respond to the RFP and prepare the proposal. (2) The general requirements section is similar to the general requirements of a DB-B…
27.5.B.92-92-509 27 CAR § 92-509. Step 5C: Agreement and technical provisions
24.5K chars
27 CAR § 92-509. Step 5C: Agreement and technical provisions. (a) Project scope. (1)(A) The primary goal in the development of the project scope is to define, obtain, or develop all pertinent information required to describe performance-based criteria for the short-list proposers…
27.5.B.92-92-510 27 CAR § 92-510. Step 5D: Prepare the request for proposals forms
0.6K chars
27 CAR § 92-510. Step 5D: Prepare the request for proposals forms. (a) The request for proposals (RFP) forms should be acquired and/or prepared for the project by the department procurement team (DPT). (b) The typical D-B proposal forms would include, but are not limited to the: …
27.5.B.92-92-511 27 CAR § 92-511. Step 5E: Publish the RFP documents
0.7K chars
27 CAR § 92-511. Step 5E: Publish the RFP documents. (a) The assembly and printing production of the RFP will be a similar, although more in-depth, operation to the Arkansas Department of Transportation procedure to publish specifications. (b) The RFP will have attachments, such …
27.5.B.92-92-512 27 CAR § 92-512. Step 5F: Respond to proposer requests for clarification
4.2K chars
27 CAR § 92-512. Step 5F: Respond to proposer requests for clarification. (a)(1) A short-list proposer that will develop a proposal will require a clear understanding of the project to be successful. (2) Project understanding can be derived from the information provided by the Ar…
27.5.B.92-92-513 27 CAR § 92-513. Step 5G: Alternative technical concepts
3.3K chars
27 CAR § 92-513. Step 5G: Alternative technical concepts. (a)(1) Throughout the RFP phase, each short-list proposer will normally propose modifications to the project scope that the short-list proposer would like the Arkansas Department of Transportation to either include in the …
27.5.B.92-92-514 27 CAR § 92-514. Step 5H: Schedule of values
2.1K chars
27 CAR § 92-514. Step 5H: Schedule of values. (a)(1) Most D-B projects are bid on a lump-sum basis and the RFP should require a bid breakdown to be submitted in the proposal in the form of a schedule of values (SOV). (2) The RFP should specify any specific subordinate breakdown r…
27.5.B.92-92-515 27 CAR § 92-515. Step 6: Evaluate the proposal
2.5K chars
27 CAR § 92-515. Step 6: Evaluate the proposal. (a)(1) For most D-B projects, the short-list proposers will be required to submit a proposal which is comprised of a technical proposal and price proposal. (2) These documents should be submitted to the Arkansas Department of Transp…
27.5.B.92-92-516 27 CAR § 92-516. Step 6A: Technical proposal evaluation
2.0K chars
27 CAR § 92-516. Step 6A: Technical proposal evaluation. (a)(1) The technical proposal should address specific requirements the Arkansas Department of Transportation has established for the project. (2) The technical proposal should be evaluated and scored on how well it meets th…