35-A M.R.S. § 3102 Recovery of cost of canceled or abandoned electric generating facility or transmission or distribution plant
1.1K chars
1. Determining rate-making treatment. In determining the rate-making treatment for a utility's investment in a canceled or abandoned electric generating facility or transmission or distribution plant, the commission shall balance the interests of the utility and ratepayers in a j…
35-A M.R.S. § 3103 Minimum charge
0.7K chars
1. Utilities required to provide minimum charge. Any transmission and distribution utility serving more than 5,000 customers that has a residential rate combining energy and demand costs in a single rate that neither declines nor increases, but is flat as consumption increases sh…
35-A M.R.S. § 3104 Schedule of regular meter readings required
0.7K chars
1. Definitions. As used in this section, unless the context otherwise indicates, the following terms have the following meanings. A. "Investor-owned transmission and distribution utility" means a transmission and distribution utility other than a consumer-owned transmission and d…
35-A M.R.S. § 3104-A Metering and billing system accuracy
2.1K chars
A transmission and distribution utility shall conduct testing of its metering and billing systems in accordance with rules adopted by the commission. [PL 2017, c. 448, §2 (NEW).] 1. System accuracy; rulemaking. The commission shall amend or adopt rules governing the testing of th…