67 chapters · 710 sections in this title.
35-A M.R.S. § 3481 Definitions
4.2K chars
As used in this chapter, unless the context otherwise indicates, the following terms have the following meanings. [PL 2019, c. 478, Pt. B, §1 (NEW).] 1. Bid rate. "Bid rate" means the rate proposed under a qualified bid for the output of a distributed generation resource in respo…
35-A M.R.S. § 3482 Specific measures to support distributed generation
1.6K chars
1. Procurements. The commission may not procure distributed generation resources in the shared distributed generation and commercial or institutional distributed generation market segments using the targets and procurement methods described in this chapter. 2. Participation in wh…
35-A M.R.S. § 3483 Timely interconnection
3.2K chars
A standard buyer designated pursuant to this section shall aggregate the output of the portfolio of distributed generation resources procured pursuant to this chapter and sell or use the output of the resources in a manner that maximizes the value of the portfolio of the resource…
35-A M.R.S. § 3484 Procurement methods
14.3K chars
1. Initial competitive procurement. The following standards and methods apply to the initial competitive procurement of distributed generation resources associated with commercial or institutional customer accounts under section 3485 and of shared distributed generation resources…