14 chapters · 667 sections in this title.
Mont. Code Ann. § 75-26-301 Definitions
2.3K chars
As used in this part, unless the context requires otherwise, the following definitions apply: (1) "Board" means the board of environmental review provided for in 2-15-3502. (2) "Decommission" or "decommissioning" means: (a) except as provided in 75-26-304(2), the removal of build…
Mont. Code Ann. § 75-26-304 Bond -- Penalty For Failure To Submit
8.5K chars
(1) (a) Within 12 months of a wind generation facility or solar facility commencing commercial operation, the owner of a wind generation facility or solar facility operating in Montana shall: (i) notify the department in writing of the date that the facility began commercial oper…
Mont. Code Ann. § 75-26-305 Decommissioning Lien
1.1K chars
(1) For a wind generation facility or solar facility that has not submitted a bond to the department or within 30 days of abandonment of a wind generation facility or solar facility, the department shall file a lien on the generation assets of the facility in an amount not less t…
Mont. Code Ann. § 75-26-308 Wind And Solar Decommissioning Account -- Use Of Existing Resources
1.0K chars
(1) There is a wind and solar decommissioning account within the state special revenue fund established in 17-2-102. There must be paid into the account: (a) penalties collected in accordance with 75-26-304(9); (b) proceeds from the sale of assets secured by liens on a wind gener…