12 NYCRR 23-3.2 § 23-3.2 General requirements.
2.2K chars
(1) Before demolition is started, all glass in the exterior openings of the building or other structure to be demolished shall be removed. (2) Before demolition is started, all gas, electric, water, steam and other supply lines shall be shut off and capped or otherwise sealed. In…
12 NYCRR 23-3.3 § 23-3.3 Demolition by hand.
9.8K chars
The provisions of this section shall not apply to mechanical means of demolition. (1) The demolition of walls and partitions shall proceed in a systematic manner and all demolition work above each tier of floor beams shall be completed before any demolition work is performed on t…
12 NYCRR 23-3.4 § 23-3.4 Mechanical methods of demolition.
0.0K chars