1,157 sections in this chapter.
33.1-24-05-N.D. Admin. Code § 33.1-24-05-994 Amendment of contingency plan
0.8K chars
The owner or operator must review, and immediately amend the contingency plan, if necessary, whenever: 1. The facility permit is revised; 2. The plan fails in an emergency; 3. The facility changes in its design, construction, operation, maintenance, or other circumstances in a wa…
33.1-24-05-N.D. Admin. Code § 33.1-24-05-995 Emergency coordinator
0.8K chars
At least one employee must be either on the facility premises or on call at all times, for example, available to respond to an emergency by reaching the facility within a short period of time, who has the responsibility for coordinating all emergency response measures. This emerg…
33.1-24-05-N.D. Admin. Code § 33.1-24-05-996 Emergency procedures
3.6K chars
1. Whenever there is an imminent or actual emergency situation, the emergency coordinator, or the coordinator's designee when the emergency coordinator is on call, must immediately: a. Activate internal facility alarm or communication systems, where applicable, to notify all faci…