Allowable retention of estimates - Interest on retainage

N.D.C.C. § 43-07-23 — under Contractors.

N.D.C.C. § 43-07-23

Contracts entered between persons for the performance of work to be done by a contractor, except those contracts subject to section 40-22-37 or 48-01.2-13, or contracts governed by federal statutes or regulations which require other provisions with respect to retention, are subject to a maximum retention on amounts due under the contract as follows: retention of ten

percent of each estimate presented is allowable until such time as the project is fifty percent complete, with no further retainage on estimates during the continuance of the contract. If the owner, governing board, or authorized committee invests the retained estimate funds, the interest earned on those retained funds is payable at the time of final payment on the contract to the contractor on whose account the moneys were held.

43-07-24. Duty to supply license number when applying for building permit - Display of number. When applying for a building permit, a contractor shall supply the permit issuing official that contractor's license number. That official shall enter those numbers on the permit. A person performing general contractor's work on that person's own property, even if exempt from the licensing requirements of this chapter, shall, when applying for a building permit, supply the building permit issuing official the license number, as soon as available, of each subcontractor engaged on the project and doing work covered by the permit. That official shall enter each number so supplied before inspection of the work.