33 chapters · 351 sections in this title.
N.D.C.C. § 49-03-01 Certificate of public convenience and necessity - Secured by electric public utility
1.4K chars
1. An electric public utility may not begin construction or operation of a public utility plant or system, or of an extension of a plant or system without first obtaining from the commission a certificate that public convenience and necessity require or will require the construct…
N.D.C.C. § 49-03-01.1 Limitation on electric transmission and distribution lines, extensions, and service by electric public utilities
0.9K chars
No electric public utility henceforth shall begin in the construction or operation of a public utility plant or system or extension thereof without first obtaining from the commission a certificate that public convenience and necessity require or will require such construction an…
N.D.C.C. § 49-03-01.3 Exclusions from limitations on electric distribution lines, extension, and service and on issuance of certificates of public convenience and necessity
1.6K chars
Sections 49-03-01 through 49-03-01.5 shall not be construed to require any such electric public utility to secure such order or certificate for an extension of its electric distribution lines within the corporate limits of any municipality within which it has lawfully commenced o…
Enforcement of act
1.1K chars
1. If any electric public utility or electric transmission provider violates or threatens to violate any of the provisions of sections 49-03-01 through 49-03-01.5 or interferes with or threatens to interfere with the service or system of any other electric public utility or rural…