20 chapters · 1,347 sections in this title.
ORS 537.010 Definition of Water Rights Act.
0.3K chars
As used in this chapter, Water Rights Act means and embraces ORS 536.050, 537.120, 537.130, 537.140 to 537.252, 537.390 to 537.400, 538.420, 540.010 to 540.120, 540.210 to 540.230, 540.310 to 540.430, 540.443 to 540.491, 540.505 to 540.586 and 540.710 to 540.750. [Amended by 19…
ORS 537.040 Registration of water for road construction, maintenance or reconstruction; fee; annual renewal statement; limitations; rules
3.1K chars
(1) In lieu of applying for a permit for a water right under ORS 537.130, a public agency having jurisdiction over roads or highways may register a water use for road and highway maintenance, construction and reconstruction purposes. (2) A public agency applying to register a wat…
ORS 537.090 Laws applicable to geothermal wells
0.9K chars
(1) The provisions of this chapter relating to appropriation and water rights do not apply to the production of fluid from a well with a bottom hole temperature of at least 250 degrees Fahrenheit. (2) Production of fluids from a well with a bottom hole temperature of at least 250…
ORS 537.095 Interference between geothermal well and other water appropriation
0.8K chars
If interference between an existing geothermal well permitted under ORS chapter 522 and an existing water appropriation permitted under this chapter is found by either the State Geologist or the Water Resources Commission, the State Geologist and the Water Resources Commission sh…
ORS 537.097 Verification of land ownership; time limits; exception
0.9K chars
(1) As the Water Resources Commission updates its water right and permit records with current land ownership information from county records or other sources, the commission shall request the person shown in those updated records to verify that the person owns the land to which a…
ORS 537.099 Water use report from governmental entity
0.8K chars
(1) Except as provided in subsection (3) of this section, any governmental entity that holds a water right shall submit an annual water use report to the Water Resources Department. The report shall include, but need not be limited to the amount of water used by the governmental …
ORS 537.101 Reporting measured water use; rules
0.8K chars
(1) If the Water Resources Department requires an entity to measure the use of water diverted, stored or otherwise appropriated by the entity under a right established by a water right permit, water right certificate, limited license, decree, order of determination or ground wate…
ORS 537.110 Public ownership of waters
0.1K chars
All water within the state from all sources of water supply belongs to the public.
ORS 537.120 Right of appropriation; vested rights protected
0.4K chars
Subject to existing rights, and except as otherwise provided in ORS chapter 538, all waters within the state may be appropriated for beneficial use, as provided in the Water Rights Act and not otherwise; but nothing contained in the Water Rights Act shall be so construed as to ta…
ORS 537.130 Permit to appropriate water required; notification to owner of certain land
1.8K chars
(1) Except for a use exempted under ORS 537.040, 537.141, 537.142, 537.143 or 537.800 or under the registration system set forth in ORS 537.132, any person intending to acquire the right to the beneficial use of any of the surface waters of this state shall, before beginning cons…
ORS 537.131 Reclaimed water
0.6K chars
As used in ORS 537.132, 540.510 and 540.610, reclaimed water means water that has been used for municipal purposes and after such use has been treated in a treatment works as defined in ORS 454.010, and that, as a result of treatment, is suitable for a direct beneficial purpose…
ORS 537.132 Exemption from permit requirement for use of reclaimed water; rules
3.9K chars
(1) The provisions of ORS 537.130 requiring application for a permit to appropriate water shall not apply to the use of reclaimed water, if: (a) The use of reclaimed water is authorized by the national pollutant discharge elimination system or water pollution control facilities p…
ORS 537.133 Permittees right to enter on forestland; notice
1.1K chars
(1) A permittee may not enter upon forestland adjacent to the point of diversion designated in the permit until such person provides notice to the landowner of the permittees intention to enter upon such property. The notice shall: (a) Be in writing; (b) Be mailed to the landown…
ORS 537.135 Permit required to appropriate water for recharging ground water sources; minimum perennial streamflow required for permit; exception
1.8K chars
(1) The appropriation of water for the purpose of recharging ground water basins or reservoirs is declared to be for a beneficial purpose. Permits for such appropriation may be granted by the Water Resources Department on application made therefor. Any such application shall subs…
ORS 537.139 Failure to obtain authorization for access to certain land
1.1K chars
(1) The failure of an applicant to obtain written authorization, obtain an easement or acquire ownership of land if required as a condition to issuance of a permit under ORS 537.211 (2) shall be a ground for refusal to issue a permit. (2) If an applicant makes a statement under O…
ORS 537.140 Application for permit; contents; maps and drawings
4.5K chars
(1)(a) Each application for a permit to appropriate water shall be made to the Water Resources Department on a form prescribed by the department and shall set forth: (A) The name and mailing address of the applicant; (B) The source of water supply including the name and mailing a…
ORS 537.141 Uses of water not requiring water right application, permit or certificate; rules
6.0K chars
(1) The following water uses do not require an application under ORS 537.130 or 537.615, a water right permit under ORS 537.211 or a water right certificate under ORS 537.250: (a) Emergency fire-fighting uses; (b) Nonemergency fire-fighting training, provided: (A) The source of t…
ORS 537.142 Water right permit or certificate not required for egg incubation project under salmon and trout enhancement program
1.3K chars
(1) No water right certificate or permit is required for the use of the surface waters of this state if the water is to be used for a salmon and trout enhancement project certified by the State Department of Fish and Wildlife under ORS 496.430 to 496.460. (2) The use of water for…
ORS 537.143 Limited license to use or store surface or ground water or to use stored water; rules
5.3K chars
(1) Notwithstanding the provisions of ORS 537.130, the Water Resources Commission may establish by rule a procedure to allow a person to obtain a limited license to use or store ground water not otherwise exempt under ORS 537.545, to use or store surface water, to use stored wate…
ORS 537.144 Request for right to use water under limited license; fee
2.0K chars
(1) Any person requesting the right to use water under a limited license under ORS 537.143 shall notify the Water Resources Department on a form provided by the department. (2) If the request submitted under subsection (1) of this section is to use stored water for purposes for w…
ORS 537.145 Notice of filing of application to appropriate water for hydroelectric purposes
1.1K chars
(1) If an application is made for a permit to appropriate water for hydroelectric purposes, the Water Resources Department shall give written notice of the filing of the application to the owner of any land that is: (a) Adjacent to any portion of the stream in which the quantity …
ORS 537.147 Permit to use stored water; fee
2.5K chars
(1) Notwithstanding the process for applying for a water right permit established in ORS 537.150 to 537.230, a person may, pursuant to this section, apply to the Water Resources Department for a water right permit to use stored water. A person applying under this section for a wa…
ORS 537.150 Filing of application; determination of completeness; initial review; preliminary determination; notice; public comments; fees
4.3K chars
(1)(a) Within 15 days after receiving an application, the Water Resources Department shall determine whether the application contains the information listed under ORS 537.140 (1) and is complete and not defective, including the payment of all applicable fees or fee amounts requir…
ORS 537.153 Review of application; proposed final order; presumption that use will not impair or be detrimental to public interest; standing; protest; final order; contested case hearing
5.6K chars
(1) Within 60 days after the Water Resources Department proceeds with the application under ORS 537.150 (5)(c), the department shall complete application review and issue a proposed final order approving or denying the application or approving the application with modifications o…
ORS 537.160 Approval for beneficial use; agreement authorizing use of ditch for waste or seepage water
1.0K chars
(1) Subject to the provisions of subsections (2) and (3) of this section, and of ORS 537.170 and 537.190, the Water Resources Department shall approve all applications made in proper form which contemplate the application of water to a beneficial use, unless the proposed use conf…
ORS 537.170 Protest of proposed final order; final order; appeal
4.3K chars
(1) If a protest of a proposed final order issued under ORS 537.153 is filed under ORS 536.077 and, after the contested case hearing or, if a hearing is not held, after the close of the period allowed to file a protest, the Water Resources Director determines that the proposed us…
ORS 537.173 Exceptions to final order; modified order
0.5K chars
(1) Within 20 days after the Water Resources Director issues a final order under ORS 537.170 after the conclusion of a contested case hearing, any party may file exceptions to the order with the Water Resources Commission. (2) The commission shall issue a modified order, if allow…
ORS 537.175 Time limit for issuing final order or scheduling contested case hearing; applicant request for extension
1.3K chars
(1) Except as provided in subsection (2) of this section, the Water Resources Department shall issue a final order or schedule a contested case hearing on an application for a water right referred to in ORS 537.140 or 537.400 within 180 days after the department proceeds with the…
ORS 537.190 Terms and conditions of approval; municipal water supplies; release of stored water
1.7K chars
(1) The Water Resources Department may approve an application for less water than applied for, or upon terms, limitations and conditions necessary for the protection of the public interest, including terms, limitations and conditions relating to the release of water from an impou…
ORS 537.211 Issuance of permit if application approved; contents of permit; effect; rejection of application; change in permit terms; grounds for denial
7.3K chars
(1) The approval of an application referred to in ORS 537.140 or 537.400 shall be set forth in a water right permit issued by the Water Resources Department. The permit shall specify the details of the authorized use and shall set forth any terms, limitations and conditions as th…
ORS 537.220 Assignment of application, permit or license
0.7K chars
(1) Any application, permit or license to appropriate water may be assigned, subject to the conditions of the application or permit, but no such assignment shall be binding, except upon the parties to the assignment, unless filed for record in the Water Resources Department. (2) …
ORS 537.225 Full or partial assignment of water right permit; issuance of replacement permits
5.6K chars
(1) Notwithstanding ORS 537.220 and 537.635, except as provided in subsection (7) of this section, a record landowner holding a water right permit for an irrigation, nursery, temperature control, stock watering or agricultural water use that has a subsequent completion date may a…
ORS 537.227 Informal resolution of water rights assignment protests; limitations on parties
0.7K chars
(1) In addition to any other authority the Water Resources Department may have, if a protest is properly filed, the department may work with the applicant for the water right assignment and the person filing the protest to determine whether the issues raised by the protest can be…
ORS 537.230 Time allowed for construction of irrigation or other work; extension; survey; map; requirements for supplemental water right
6.6K chars
(1) As used in this section, undeveloped portion means the difference between the maximum rate or duty specified in a water right permit and the maximum rate or duty diverted as of the later of: (a) June 29, 2005; (b) The time specified in the permit to perfect the water right;…
ORS 537.240 Federal permit; time for obtaining; cancellation; time for beginning and completing work
1.9K chars
(1) In any case where a permit from the Federal Energy Regulatory Commission is or shall be required in connection with the development of the applicants proposed project, the applicant shall make application for the necessary federal permit or license within six months, or, if …
ORS 537.248 Requirement to include in reservoir permit date for beginning and completing construction and for perfecting water right; extension
1.4K chars
(1) When the Water Resources Department issues a reservoir permit for a new storage project to a county, municipality or district, the department shall include in the permit a date, not more than 10 years after the date the permit is issued, to begin and complete construction of …
ORS 537.249 Election to have proposed reservation considered as application for permit or rulemaking proceeding
1.9K chars
(1) In lieu of the procedure established pursuant to ORS 537.358, for any reservation pending on July 5, 1995, the state agency that requested the reservation may elect to have the proposed reservation considered: (a) As an application for a permit under ORS 537.140 to 537.211 an…
ORS 537.250 Water right certificate; issuance; inclusion of land not described in permit; recordation; duration of rights
1.7K chars
(1) After the Water Resources Department has received a request for issuance of a water right certificate accompanied by the survey required under ORS 537.230 that shows, to the satisfaction of the department, that an appropriation has been perfected in accordance with the provis…
ORS 537.252 Certificate issued for land not described in permit; notice
3.0K chars
(1) When issuing a water right certificate under ORS 537.250 to a district, or to a government agency for a district, the Water Resources Department may issue the water right certificate for land not described in the permit if: (a) Water furnished by the district under the permit…
ORS 537.260 Cancellation of permit for failure of proof of completion of appropriation; issuance of limited certificate; contest of issuance of certificate; exception for municipalities
3.1K chars
(1) Except as provided under subsection (4) of this section for a permit issued to a municipality, whenever the time within which any appropriation under a permit should have been perfected has expired and the owner of the permit fails or refuses within three months thereafter to…
ORS 537.270 Conclusiveness of certificate
0.6K chars
A water right certificate issued in accordance with the provisions of ORS 537.250 which, after the expiration of three months from the date it is issued, has not been contested and canceled in the manner provided in ORS 537.260, and a water right certificate, when issued under OR…
ORS 537.282 Definition of municipal applicant.
0.4K chars
As used in ORS 537.282 to 537.299, municipal applicant means any municipal corporation or district as defined in ORS 543.655 that has applied for a permit to appropriate water for the purpose of generating hydroelectric power under the provisions of this chapter, or that has be…
ORS 537.283 Procedure for applications to appropriate water for hydroelectric power; rules
1.3K chars
(1) Notwithstanding any other provision of ORS 537.140 to 537.350, in accordance with the applicable provisions of ORS chapter 183, the Water Resources Commission shall by rule establish a procedure for processing applications to appropriate water for hydroelectric power under OR…
ORS 537.285 Municipal applicant may develop hydroelectric project jointly with private person; restrictions
0.5K chars
A municipal applicant may contract with a private person for the purpose of generating hydroelectric power. The municipal applicant shall retain sufficient benefit and interest in, and control of a joint project as necessary for the project to be considered a municipal project. A…
ORS 537.287 Rules for joint project of municipal applicant and private person
0.4K chars
The Water Resources Commission shall establish rules necessary to carry out the provisions of ORS 537.285. The rules shall include the amount of control over and interest in a joint project a municipal applicant must retain in order to receive the benefit of the municipal prefere…
ORS 537.289 Conditions to be imposed on permit of municipal corporation or district
1.4K chars
(1) Whenever the Water Resources Department issues a permit under ORS 537.211 allowing a municipal corporation or district, as defined in ORS 543.655, to appropriate water for the purpose of generating hydroelectric power, the department shall impose the following conditions on t…
ORS 537.292 Conditions to be imposed on certificate of municipal corporation or district
1.5K chars
(1) Whenever the Water Resources Commission issues a certificate under ORS 537.250 granting a municipal corporation or district as defined in ORS 543.655 the right to appropriate water for the purpose of generating hydroelectric power, the commission shall impose the following co…
ORS 537.295 Cancellation of permit when holder fails to continue to qualify as municipal applicant
0.7K chars
(1) If the holder of a permit to appropriate water for hydroelectric purposes under this chapter fails, after receiving notice under ORS 537.289 (2), to amend the joint agreement so the holder continues to qualify as a municipal applicant, or if the holder of the permit has assig…
ORS 537.297 Cancellation of water right certificate when holder fails to continue to qualify as municipal applicant
0.7K chars
(1) If the owner of a certificate to appropriate water for hydroelectric purposes under this chapter fails, after receiving notice under ORS 537.289 (2), to amend the joint agreement so the owner continues to qualify as a municipal applicant, or if the holder of the certificate h…
ORS 537.299 Consequences of cancellation of permit or certificate if holder no longer municipal applicant; conditions to protect public health and welfare
1.0K chars
(1) If the Water Resources Commission cancels a permit or certificate under ORS 537.295 or 537.297, the municipal applicant may apply for a permit to appropriate water for hydroelectric purposes under this chapter, or the private developer may apply for a hydroelectric license un…